Clean Water Act discharge permit · NPDES OK0028614

NEWCASTLE PUBLIC WORKS AUTH., Newcastle, OK: NPDES OK0028614 discharge permit, effluent exceedances, inspections, penalties

NEWCASTLE PUBLIC WORKS AUTH., held by Newcastle PWA, holds NPDES permit OK0028614, which discharges to 520610010215_00 Tim'S Ck/Pond Ck/S Canadian. EPA’s file records it issued December 7, 2015 and expiring December 31, 2020. The status and dates are as EPA’s permit file stood when Velarion loaded it (September 15, 2026); EPA’s free Detailed Facility Report on ECHO carries the permit’s current standing.

Identity

Facility as filedNEWCASTLE PUBLIC WORKS AUTH.
Permittee as filedNewcastle PWA
NPDES IDOK0028614
Permit statusAdministratively continued (past its expiration date and still in force until reissued)
Permit typeIndividual permit
Discharger classMinor discharger
Facility typePublicly owned treatment works
ProgramPublicly owned treatment works
IssuedDecember 7, 2015
Expiration dateDecember 31, 2020
Issuing agencyODEQ
AddressNewcastle, OK 73065
Receiving water520610010215_00 Tim's Ck/Pond Ck/S Canadian
SubwatershedPond Creek-Canadian River (HUC 110902020303)

Cited to the EPA ICIS-NPDES permit file (ECHO download).

Effluent limits and exceedances

An effluent exceedance is a discharge monitoring report value over the permit’s numeric limit (EPA’s violation code E90). A violation of any kind also counts a report not filed. Each row is EPA’s own count for that pollutant.

Pollutant or measureLimitsViolations, any kindEffluent exceedancesLatest exceedanceLargest exceedance, as filed
BOD, 5-day, 20 deg. C36449March 31, 2025963% over the limit
Solids, total suspended35638July 31, 2025447% over the limit
E. coli02020August 31, 202598,422% over the limit
pH22513August 31, 2024
Coliform, fecal general2209July 31, 20211,900% over the limit
Chlorine, total residual1107May 31, 20252,122% over the limit
Flow, in conduit or thru treatment plant2120

Cited to the EPA ICIS-NPDES limits and effluent violations files (ECHO download); up to 60 rows shown, most exceedances first.

Inspections, violations and enforcement

DateWhat EPA recordedAgency
June 19, 2025Effluent Violations - Unapproved BypassST6
June 9, 2025Effluent Violations - Unapproved BypassST6
June 4, 2025Effluent Violations - Unapproved BypassST6
November 22, 2023Effluent Violations - Unapproved BypassST6
November 14, 2023Effluent Violations - Unapproved BypassST6
November 8, 2023Effluent Violations - Unapproved BypassST6
October 31, 2023Effluent Violations - Unauthorized DischargeST6
October 24, 2023Effluent Violations - Unauthorized DischargeST6
October 17, 2023Effluent Violations - Unauthorized DischargeST6
October 5, 2023Management Practice Violations - Improper Operation and MaintenanceST6
October 3, 2023Management Practice Violations - Improper Operation and MaintenanceST6
September 28, 2023Effluent Violations - Unauthorized DischargeST6
September 26, 2023Management Practice Violations - Improper Operation and MaintenanceST6
July 26, 2023Effluent Violations - Unauthorized DischargeST6
May 5, 2021Effluent Violations - Unauthorized DischargeST6
April 28, 2021Effluent Violations - Unauthorized DischargeST6
April 24, 2021Effluent Violations - Unauthorized DischargeST6

Velarion’s copy of EPA’s ICIS-NPDES files does not include the inspections, formal enforcement actions and informal enforcement actions files, so this page shows none of them. EPA’s free Detailed Facility Report on ECHO lists this permit’s inspections, enforcement actions and penalties.

Cited to the EPA ICIS-NPDES violation, inspection and enforcement files (ECHO download); up to 50 rows of each shown, newest first.

Watch this permit

One permit holder, $99/month. Watch the register for one permit holder and the places and receiving waters tied to its permits. Choose “One permit holder” and enter this permit’s NPDES ID, OK0028614.

Start the watch

How often?
  • One permit holder — $99/month
  • One watershed — $2,990/year
  • One state — $4,990/year
  • The whole register — $18,000/year

How we handle your data → Privacy

EPA publishes a free Detailed Facility Report for every permit on ECHO: its compliance status quarter by quarter, its inspections, and its enforcement actions and penalties. EPA also sends free notices of new inspections and enforcement actions through ECHO Notify; enter NPDES ID OK0028614 there.

Nearby on the register

Figures from EPA’s ICIS-NPDES download, loaded September 15, 2026.