NPDES ORR323464 · Clean Water Act
GRAHAM QUARRY, Clatskanie, OR: NPDES ORR323464 discharge permit, effluent exceedances, inspections, penalties
GRAHAM QUARRY, Clatskanie, Oregon: General permit coverage ORR323464, held by Kynsi Construction, Inc.; Industrial stormwater; Administratively continued; issued June 25, 2013, term to December 3, 2017, by STA.
- April 20, 2023: Failure to comply with a requirement regarding Industrial Stormwater Control (ST6).
Oregon holds 595 Industrial stormwater coverages of this permit type in EPA’s file; 40 were issued before ORR323464.
Coverages issued nearest ORR323464
- 2013-06-21: KLAMATH PACIFIC COMPANY, Klamath Falls: ORR328088, held by Rocky Mountain Construction, LLC
- 2013-06-24: MOLALLA REDI-MIX PLANT, Molalla: ORR328060, held by MOLALLA REDI-MIX & PRODUCTS, INC.
- 2013-06-25: HANKEY ROAD PIT, Saint Helens: ORR320043, held by Eagle Star Rock Products, LLC
- 2013-06-25: PARKIN QUARRY, Forest Grove: ORR323181, held by Farmington Mobile Crushing, LLC
- 2013-06-25: HOWARD CANYON PIT, Corbett: ORR323340, held by Smith, Leroy
- 2013-06-25: CARVER STONE, Clackamas: ORR328056, held by Griffin Oaks Business Park, LLC
- 2013-06-25: OAK RANCH QUARRY, Rainier: ORR328093, held by Teevin & Fischer Quarry LLC
- 2013-06-28: JOHNSON QUARRY, Seaside: ORR323379, held by Teevin & Fischer Quarry, LLC
- 2013-06-28: OLD COUNTY PIT, Nehalem: ORR327172, held by Nehalem Bay Ready Mix Mohler Sand & Grav
- 2013-06-28: RIPPET PIT, Seaside: ORR327182, held by Teevin & Fischer Quarry, LLC
GRAHAM QUARRY among its neighbors
2 discharge permits are in the West Creek-Frontal Columbia River subwatershed (HUC 170800030601); ORR323464 is one.
Other permits in the West Creek-Frontal Columbia River subwatershed (HUC 170800030601)
- WESTPORT SEWER SERVICE DISTRICT STP, Westport: OR0031496, minor, term to 2024-08-31
What stands out
- Its term runs 4 years and 161 days, June 25, 2013 to December 3, 2017; the term ended 3,208 days before EPA's file was loaded on September 15, 2026, and the file lists the permit as administratively continued.
- Its newest dated event on file is a single-event violation on April 20, 2023, 1,244 days before EPA's file was loaded.
- No dated event in the 365 days to September 15, 2026.
- EPA's file dates 1 event for it, all in 2023.
- It is one of 1,616 discharge permits on the register in Oregon; 598 of them (37%) are in its program, Industrial stormwater, and it is a minor discharger.
Identity
| Facility | GRAHAM QUARRY |
|---|---|
| Permittee | Kynsi Construction, Inc. |
| NPDES ID | ORR323464 |
| Status | Administratively continued |
| Type | General permit coverage |
| Class | Minor |
| Facility type | Non-POTW |
| Program | Industrial stormwater |
| Issued | June 25, 2013 |
| Expires | December 3, 2017 |
| Agency | STA |
| Address | Clatskanie, OR 97016 |
| Subwatershed | West Creek-Frontal Columbia River (HUC 170800030601) |
NPDES ORR323464: effluent limits and exceedances
GRAHAM QUARRY (NPDES ORR323464): 0 pollutants on file, 0 limited; 0 with a violation of any kind, 0 with an exceedance.
NPDES ORR323464: no pollutant row on file.
NPDES ORR323464: inspections, violations and enforcement
NPDES ORR323464: 1 single-event violation
| Date | What EPA recorded | Agency |
|---|---|---|
| April 20, 2023 | Failure to comply with a requirement regarding Industrial Stormwater Control | ST6 |
NPDES ORR323464 (GRAHAM QUARRY): no inspection, formal enforcement action and informal enforcement action on file.
Watch NPDES ORR323464
NPDES ORR323464: one email when its EPA record changes — $99/month.
Permits near NPDES ORR323464
NPDES ORR323464: 0 pollutant rows, 1 dated events; ICIS-NPDES download, loaded September 15, 2026.