NPDES PAC360143 · Clean Water Act
STONEYBROOK PHASE 4A & 4B, Elizabethtown, PA: NPDES PAC360143 discharge permit, effluent exceedances, inspections, penalties
STONEYBROOK PHASE 4A & 4B, Elizabethtown, Pennsylvania: General permit coverage PAC360143, held by RGR Developers LP; Construction stormwater; Effective; issued December 17, 2024, term to December 7, 2029, by Lancaster County Conservation District; New Housing For-Sale Builders.
- June 8, 2022: WW Storm Water Construction - Narrative effluent violation (CT6).
- June 8, 2022: WW Storm Water Construction - Failure to properly install/implement BMPs (CT6).
- June 8, 2022: WW Storm Water Construction - Failure to Implement SWPPP/SWMP (CT6).
- February 13, 2020: WW Storm Water Construction - Narrative effluent violation (CT6).
- October 22, 2019: WW Storm Water Construction - Failure to properly operate and maintain BMPs (CT6).
- October 22, 2019: WW Storm Water Construction - Failure to Implement SWPPP/SWMP (CT6).
- October 22, 2019: WW Storm Water Construction - Failure to properly install/implement BMPs (CT6).
- May 24, 2019: WW Storm Water Construction - Failure to properly install/implement BMPs (CT6).
- February 6, 2019: WW Storm Water Construction - Failure to properly operate and maintain BMPs (CT6).
- November 8, 2018: WW Storm Water Construction - Narrative effluent violation (CT6).
- November 8, 2018: WW Storm Water Construction - Failure to properly install/implement BMPs (CT6).
- November 8, 2018: WW Storm Water Construction - Failure to Implement SWPPP/SWMP (CT6).
Pennsylvania holds 4,048 Construction stormwater coverages of this permit type in EPA’s file; 2,497 were issued before PAC360143.
Coverages issued nearest PAC360143
- 2024-12-16: LCFPA STORMWATER BIO-RETENTION BMPS/MAINTENANCE BUILDING EXPANSION, Forty Fort, Borough Of: PAC400326, held by Luzerne County Flood Protection Authority
- 2024-12-17: THE SMITH FARM, Littlestown Borough: PAC010121, held by Donald R. Smith
- 2024-12-17: WYSOX COMMUNITY PARK, Wysox, Township Of: PAC080094, held by Wysox Township
- 2024-12-17: ETMA 2 WATERLINE REPLACEMENT, East Taylor, Township Of: PAC110133, held by East Taylor Municipal Authority
- 2024-12-17: ASTON CARE FACILITY, Aston, Township Of: PAC230311, held by Christiana Care Pennsylvania, Inc.
- 2024-12-17: MANUFACTURING PLANT EXPANSION, Mountain Top: PAC400060, held by CornellCookson
- 2024-12-17: ALLISON CRANE & RIGGING, Hazle, Township Of: PAC400216, held by High Hook Enterprises, Inc.
- 2024-12-18: MCCARVER, Silver Spring, Township Of: PAC210373, held by Brian McCarver
- 2024-12-18: ELIZABETHVILLE CSG 1 LLC SOLAR PROJECT, Washington, Township Of: PAC220449, held by Elizabethville CSG 1 LLC
- 2024-12-18: CUMULUS DATA CENTER, Salem, Township Of: PAC400193, held by Amazon Data Services, Inc.
STONEYBROOK PHASE 4A & 4B among its neighbors
15 discharge permits are in the Conoy Creek subwatershed (HUC 020503061701); PAC360143 is one. Its county: 724, 5 major; PAC360143 is minor permit.
Other permits in the Conoy Creek subwatershed (HUC 020503061701)
- 1376 CAMPUS ROAD, Mount Joy, Township Of: PAC360735, minor, term to 2024-12-07
- BEAR CRK ESTS, Elizabethtown: PAC360938, minor, term to 2029-12-07
- BOROUGH OF ELIZABETHTOWN, Elizabethtown: PAL023108, minor, term to 2025-12-31
- E-TOWN NEW PUBLIC WORKS GARAGE RENEWAL, Elizabethtown, Borough Of: PAC360624, minor, term to 2024-12-07
- ELIZABETH RD SELF STORAGE LLC, Elizabethtown: PAC360488, minor, term to 2029-12-07
- ELIZABETHTOWN AREA HIGH SCHOOL, Elizabethtown: PAC360886, minor, term to 2024-12-07
- ELIZABETHTOWN COLLEGE - IRA R. HERR FIELD, Elizabethtown, Borough Of: PAC361150, minor, term to 2029-12-07
- LEON ZIMMERMAN FARM, Elizabethtown: PAG123781, minor, term to 2028-12-31
- MARS CHOCOLATE NORTH AMERICA, Elizabethtown: PAG033761, minor, term to 2028-03-23
- MARS CHOCOLATE NORTH AMERICA, Elizabethtown: PAR123508, minor, term to 2015-02-28
What stands out
- Its term runs 4 years and 355 days, December 17, 2024 to December 7, 2029.
- Its newest dated event on file is a single-event violation on June 8, 2022, 1,589 days before EPA's file was loaded.
- No dated event in the 365 days to October 14, 2026.
- EPA's file dates 12 events for it, from 2018 to 2022; the busiest year is 2019 with 5.
- It is one of 14,586 discharge permits on the register in Pennsylvania; 4,395 of them (30%) are in its program, Construction stormwater, and it is a minor discharger.
Identity
| Facility | STONEYBROOK PHASE 4A & 4B |
|---|---|
| Permittee | RGR Developers LP |
| NPDES ID | PAC360143 |
| Status | Effective |
| Type | General permit coverage |
| Class | Minor |
| Facility type | Non-POTW |
| Program | Construction stormwater |
| Issued | December 17, 2024 |
| Expires | December 7, 2029 |
| Agency | Lancaster County Conservation District |
| Address | Elizabethtown, PA 17022 |
| Receiving water impaired | 303(D) Listed |
| Subwatershed | Conoy Creek (HUC 020503061701) |
| NAICS | 236117 – New Housing For-Sale Builders |
NPDES PAC360143: effluent limits and exceedances
STONEYBROOK PHASE 4A & 4B (NPDES PAC360143): 0 pollutants on file, 0 limited; 0 with a violation of any kind, 0 with an exceedance.
NPDES PAC360143: no pollutant row on file.
NPDES PAC360143: inspections, violations and enforcement
NPDES PAC360143: 12 single-event violations
| Date | What EPA recorded | Agency |
|---|---|---|
| June 8, 2022 | WW Storm Water Construction - Narrative effluent violation | CT6 |
| June 8, 2022 | WW Storm Water Construction - Failure to properly install/implement BMPs | CT6 |
| June 8, 2022 | WW Storm Water Construction - Failure to Implement SWPPP/SWMP | CT6 |
| February 13, 2020 | WW Storm Water Construction - Narrative effluent violation | CT6 |
| October 22, 2019 | WW Storm Water Construction - Failure to properly operate and maintain BMPs | CT6 |
| October 22, 2019 | WW Storm Water Construction - Failure to Implement SWPPP/SWMP | CT6 |
| October 22, 2019 | WW Storm Water Construction - Failure to properly install/implement BMPs | CT6 |
| May 24, 2019 | WW Storm Water Construction - Failure to properly install/implement BMPs | CT6 |
| February 6, 2019 | WW Storm Water Construction - Failure to properly operate and maintain BMPs | CT6 |
| November 8, 2018 | WW Storm Water Construction - Narrative effluent violation | CT6 |
| November 8, 2018 | WW Storm Water Construction - Failure to properly install/implement BMPs | CT6 |
| November 8, 2018 | WW Storm Water Construction - Failure to Implement SWPPP/SWMP | CT6 |
NPDES PAC360143 (STONEYBROOK PHASE 4A & 4B): no inspection, formal enforcement action and informal enforcement action on file.
Watch NPDES PAC360143
NPDES PAC360143: one email when its EPA record changes — $99/month.
Permits near NPDES PAC360143
NPDES PAC360143: 0 pollutant rows, 12 dated events; ICIS-NPDES download, loaded October 14, 2026.