NPDES SCR10Z8TX · Clean Water Act
+/- 300K SF BLDG PAD ON PAR 6 AT THE MID-CAR COM PARK, Unincorporated, SC: NPDES SCR10Z8TX discharge permit, effluent exceedances, inspections, penalties
+/- 300K SF BLDG PAD ON PAR 6 AT THE MID-CAR COM PARK, Unincorporated, South Carolina: General permit coverage SCR10Z8TX, held by Henry Livingston III, Newberry County; Construction stormwater; Effective; issued August 25, 2021, term to August 24, 2026, by State.
- November 4, 2026: Other noncompliance related to construction stormwater discharges (ST6).
- November 4, 2026: Failure to develop, maintain, or get approval of an adequate SWPPP (construction stormwater) (ST6).
- November 4, 2026: Failure to properly install, initiate, or fully implement construction stormwater controls (ST6).
- November 4, 2026: Failure to properly operate or maintain construction stormwater controls (ST6).
South Carolina holds 11,300 Construction stormwater coverages of this permit type in EPA’s file; 91 were issued before SCR10Z8TX.
Coverages issued nearest SCR10Z8TX
- 2021-07-29: WHEELER HILL - PHASE 2, Columbia: SCR10Z8P1, held by C David Tuttle, Styx Wheeler Hill LLC
- 2021-08-09: THE GREENS AT CAROLINA CROSSINGS TRACT #1, N/A: SCR10Z8QR, held by Randy Suddreth, N/A
- 2021-08-16: QUAILS RUN, Wellford: SCR10Z8RX, held by Jay Beeson, Mark III Properties Inc
- 2021-08-18: EASTOVER SOLAR PROJECT, Eastover: SCR10Z8SJ, held by Ben Catt, Eastover Solar LLC
- 2021-08-23: WHITEHALL DEVELOPMENT, Beaufort: SCR10Z8TD, held by Sam Levin, Whitehall Development Group LLC
- 2021-09-13: SMYZER ROAD, N/A: SCR10Z8X2, held by Richard Bennett, DGR LLC & HP Properties Of SC LLC
- 2021-09-13: TRACTOR SUPPLY ST. GEORGE, St. George: SCR10Z8X3, held by Kenneth Beuley, TKC CCCI LLC
- 2021-09-13: DEWITT TOWNHOMES, N/A: SCR10Z8X4, held by Kim Pocock, Map Land and Homes LLC (c/o Mr Kim Pocock)
- 2021-09-13: ABNEY HILLS PHASE 4, Town Of Blythewood: SCR10Z8X5, held by Frank Berry, Stanley Martin Companies LLC
- 2021-09-13: TREEMONT COMMONS, Wellford: SCR10Z8X7, held by John Beeson, Mark III Properties Inc
+/- 300K SF BLDG PAD ON PAR 6 AT THE MID-CAR COM PARK among its neighbors
12 discharge permits are in the Lower Cannons Creek subwatershed (HUC 030501060405); SCR10Z8TX is one. Its county: 89, 2 major; SCR10Z8TX is minor permit.
Other permits in the Lower Cannons Creek subwatershed (HUC 030501060405)
- KRA OPERATIONS, LLC, Prosperity: SCRNE0978, minor, term to 2028-04-23
- MM TECHNICS LP, Prosperity: SCRNE1197, minor, term to 2031-03-23
- NCW&SA CANNONS CREEK WWTP, Prosperity: SC0048313, minor, term to 2026-02-28
- NEW BUILDINGS - 168 HENRY ST., Prosperity: SCR10ZKQW, minor, term to 2031-04-06
- P038562 S-82 BACHMAN CHAPEL RD BRIDGE JACKING, N/A: SCR16Z07E, minor, term to 2028-01-08
- P038569 S-99 OLD JOLLYSTREET ROAD BRIDGE JACKING, N/A: SCR16Z07D, minor, term to 2028-01-08
- P038570 SC 773 ST PAULS ROAD BRIDGE JACKING, N/A: SCR16Z07G, minor, term to 2028-01-23
- PHASE IIIB 8-INCH GRAVITY WW LINE IMPROVEMENTS TO SERVE THE MID-CAROLINA COMMERC, (Unknown City): SCR10ZJ3Y, minor, term to 2030-08-06
- ROLLING HILLS SUBDIVISION, Newberry: SCR10ZD2T, minor, term to 2028-06-06
- SCHWEITZER-MAUDUIT INTL, INC - NEWBERRY OPERATION, Prosperity: SCRNE0917, minor, term to 2026-11-10
What stands out
- Its term runs 4 years and 364 days, August 25, 2021 to August 24, 2026; the term ended 22 days before EPA's file was loaded on September 15, 2026, and the file lists the permit as effective.
- Its newest dated event on file is a single-event violation on November 4, 2026.
- No dated event in the 365 days to September 15, 2026.
- EPA's file dates 4 events for it, all in 2026.
- It is one of 13,763 discharge permits on the register in South Carolina; 11,300 of them (82%) are in its program, Construction stormwater, and it is a minor discharger.
Identity
| Facility | +/- 300K SF BLDG PAD ON PAR 6 AT THE MID-CAR COM PARK |
|---|---|
| Permittee | Henry Livingston III, Newberry County |
| NPDES ID | SCR10Z8TX |
| Status | Effective |
| Type | General permit coverage |
| Class | Minor |
| Facility type | Non-POTW |
| Program | Construction stormwater |
| Issued | August 25, 2021 |
| Expires | August 24, 2026 |
| Agency | State |
| Address | Unincorporated, SC 29127 |
| Subwatershed | Lower Cannons Creek (HUC 030501060405) |
NPDES SCR10Z8TX: effluent limits and exceedances
+/- 300K SF BLDG PAD ON PAR 6 AT THE MID-CAR COM PARK (NPDES SCR10Z8TX): 0 pollutants on file, 0 limited; 0 with a violation of any kind, 0 with an exceedance.
NPDES SCR10Z8TX: no pollutant row on file.
NPDES SCR10Z8TX: inspections, violations and enforcement
NPDES SCR10Z8TX: 4 single-event violations
| Date | What EPA recorded | Agency |
|---|---|---|
| November 4, 2026 | Other noncompliance related to construction stormwater discharges | ST6 |
| November 4, 2026 | Failure to develop, maintain, or get approval of an adequate SWPPP (construction stormwater) | ST6 |
| November 4, 2026 | Failure to properly install, initiate, or fully implement construction stormwater controls | ST6 |
| November 4, 2026 | Failure to properly operate or maintain construction stormwater controls | ST6 |
NPDES SCR10Z8TX (+/- 300K SF BLDG PAD ON PAR 6 AT THE MID-CAR COM PARK): no inspection, formal enforcement action and informal enforcement action on file.
Watch NPDES SCR10Z8TX
NPDES SCR10Z8TX: one email when its EPA record changes — $99/month.
Permits near NPDES SCR10Z8TX
NPDES SCR10Z8TX: 0 pollutant rows, 4 dated events; ICIS-NPDES download, loaded September 15, 2026.