NPDES SCR10ZH7P · Clean Water Act
FORTUNE SPRINGS PARK STORMWATER PROJECT, Winnsboro, SC: NPDES SCR10ZH7P discharge permit, effluent exceedances, inspections, penalties
FORTUNE SPRINGS PARK STORMWATER PROJECT, Winnsboro, South Carolina: General permit coverage SCR10ZH7P, held by Chris Clauson; Construction stormwater; Effective; issued March 24, 2025, term to March 23, 2030, by State.
- April 10, 2026: Evaluation (S).
- April 3, 2026: Failure to comply with recordkeeping requirements - construction stormwater [40 CFR 122.41(j)] (ST6).
- April 3, 2026: Other noncompliance related to construction stormwater discharges (ST6).
- April 3, 2026: Failure to develop, maintain, or get approval of an adequate SWPPP (construction stormwater) (ST6).
- April 3, 2026: Failure to properly operate or maintain construction stormwater controls (ST6).
- April 3, 2026: Failure to properly install, initiate, or fully implement construction stormwater controls (ST6).
- April 3, 2026: Evaluation (S).
- March 24, 2026: Failure to properly install, initiate, or fully implement construction stormwater controls (ST6).
- March 20, 2026: Failure to develop, maintain, or get approval of an adequate SWPPP (construction stormwater) (ST6).
- March 20, 2026: Failure to properly conduct construction stormwater inspections (ST6).
- March 20, 2026: Other noncompliance related to construction stormwater discharges (ST6).
- March 20, 2026: Failure to properly install, initiate, or fully implement construction stormwater controls (ST6).
- March 20, 2026: Failure to comply with recordkeeping requirements - construction stormwater [40 CFR 122.41(j)] (ST6).
- March 20, 2026: Failure to properly operate or maintain construction stormwater controls (ST6).
- March 20, 2026: Evaluation (S).
- March 6, 2026: Notice of Noncompliance Issued (State).
- February 26, 2026: Other noncompliance related to construction stormwater discharges (ST6).
- February 26, 2026: Failure to comply with recordkeeping requirements - construction stormwater [40 CFR 122.41(j)] (ST6).
- February 26, 2026: Failure to develop, maintain, or get approval of an adequate SWPPP (construction stormwater) (ST6).
- February 26, 2026: Failure to properly conduct construction stormwater inspections (ST6).
- February 26, 2026: Failure to properly install, initiate, or fully implement construction stormwater controls (ST6).
- February 26, 2026: Failure to properly operate or maintain construction stormwater controls (ST6).
- February 26, 2026: Evaluation (S).
South Carolina holds 11,300 Construction stormwater coverages of this permit type in EPA’s file; 7,902 were issued before SCR10ZH7P.
Coverages issued nearest SCR10ZH7P
- 2025-03-21: SANDRIDGE POD 1, North Myrtle Beach: SCR10ZH7H, held by Gilford Edwards
- 2025-03-21: BLUEGATE MONCKS CORNER, Moncks Corner: SCR10ZH7J, held by Neil Dyer
- 2025-03-24: CHANDLER SUMMIT, Florence: SCR10ZH7L, held by Gary Kooper
- 2025-03-24: VELOCITY TRUCK CENTER JEDBURG, Summerville: SCR10ZH7M, held by Scott Zeppenfeldt
- 2025-03-24: DROZE ROAD TOWNHOME DEVELOPMENT, Summerville: SCR10ZH7N, held by Jeffrey Roberts
- 2025-03-24: 1200 NORTH OKATIE HIGHWAY MULTIFAMILY, Ridgeland: SCR10ZH7R, held by Steven Campisi
- 2025-03-24: VITORIA EXPANSION, North Charleston: SCR10ZH7S, held by Adriene Araujo
- 2025-03-24: BUCKSPORT MAINTENANCE BUILDING, Conway: SCR10ZH7T, held by Dexter Farmer
- 2025-03-24: COLLINS FLEX, North Charleston: SCR10ZH7U, held by Troy Barber
- 2025-03-24: ST. JOHNS PARISH CHURCH, John'S Island: SCR10ZH7V, held by Robert Reynolds
FORTUNE SPRINGS PARK STORMWATER PROJECT among its neighbors
12 discharge permits are in the Jackson Creek-Little River subwatershed (HUC 030501060504); SCR10ZH7P is one. Its county: 45, 1 major; SCR10ZH7P is minor permit.
Other permits in the Jackson Creek-Little River subwatershed (HUC 030501060504)
- CREIGHTON COLEMAN PROPERTY - PUMPHOUSE ROAD RV PARK PHASE III, Winnsboro: SCR10ZKYA, minor, term to 2031-05-07
- DESC - WINNSBORO WEST SUBSTATION, Winnsboro: SCR10ZL5K, minor, term to 2031-06-08
- DSNB PARK, Winnsboro: SCR10ZD3N, minor, term to 2028-06-08
- MIDLANDS STEM INSTITUTE FOR HUBRICH CONTRACTING, Winnsboro: SCR10ZDSY, minor, term to 2028-10-01
- PERFORMANCE FIBERS INC/WINNSBO, Winnsboro: SCG250246, minor, term to 2011-04-30
- PUMPHOUSE ROAD RV PARK-CB COLEMAN, Newberry: SCR10ZE2G, minor, term to 2028-11-12
- SATELLITE OFFICE FAIRFIELD ELECTRIC COOPERATIVE INC, N/A: SCR10ZAQZ, minor, term to 2027-06-20
- WINNSBORO FIBRES LLC, Winnsboro: SCRNE0937, minor, term to 2027-05-08
- WINNSBORO JACKSON CREEK PLANT, Winnsboro: SC0020125, major, term to 2023-09-30
- WINNSBORO WTP, Winnsboro: SCG646041, minor, term to 2020-12-30
What stands out
- Its term runs 4 years and 364 days, March 24, 2025 to March 23, 2030.
- Its newest dated event on file is an inspection on April 10, 2026, 158 days before EPA's file was loaded.
- In the 365 days to September 15, 2026, it was dated 18 single-event violations, 4 inspections, 1 informal enforcement action.
- EPA's file dates 23 events for it, all in 2026.
- It is one of 13,763 discharge permits on the register in South Carolina; 11,300 of them (82%) are in its program, Construction stormwater, and it is a minor discharger.
Identity
| Facility | FORTUNE SPRINGS PARK STORMWATER PROJECT |
|---|---|
| Permittee | Chris Clauson |
| NPDES ID | SCR10ZH7P |
| Status | Effective |
| Type | General permit coverage |
| Class | Minor |
| Facility type | Non-POTW |
| Program | Construction stormwater |
| Issued | March 24, 2025 |
| Expires | March 23, 2030 |
| Agency | State |
| Address | Winnsboro, SC 29180 |
| Subwatershed | Jackson Creek-Little River (HUC 030501060504) |
NPDES SCR10ZH7P: effluent limits and exceedances
FORTUNE SPRINGS PARK STORMWATER PROJECT (NPDES SCR10ZH7P): 0 pollutants on file, 0 limited; 0 with a violation of any kind, 0 with an exceedance.
NPDES SCR10ZH7P: no pollutant row on file.
NPDES SCR10ZH7P: inspections, violations and enforcement
NPDES SCR10ZH7P: 18 single-event violations
| Date | What EPA recorded | Agency |
|---|---|---|
| April 3, 2026 | Failure to comply with recordkeeping requirements - construction stormwater [40 CFR 122.41(j)] | ST6 |
| April 3, 2026 | Other noncompliance related to construction stormwater discharges | ST6 |
| April 3, 2026 | Failure to develop, maintain, or get approval of an adequate SWPPP (construction stormwater) | ST6 |
| April 3, 2026 | Failure to properly operate or maintain construction stormwater controls | ST6 |
| April 3, 2026 | Failure to properly install, initiate, or fully implement construction stormwater controls | ST6 |
| March 24, 2026 | Failure to properly install, initiate, or fully implement construction stormwater controls | ST6 |
| March 20, 2026 | Failure to develop, maintain, or get approval of an adequate SWPPP (construction stormwater) | ST6 |
| March 20, 2026 | Failure to properly conduct construction stormwater inspections | ST6 |
| March 20, 2026 | Other noncompliance related to construction stormwater discharges | ST6 |
| March 20, 2026 | Failure to properly install, initiate, or fully implement construction stormwater controls | ST6 |
| March 20, 2026 | Failure to comply with recordkeeping requirements - construction stormwater [40 CFR 122.41(j)] | ST6 |
| March 20, 2026 | Failure to properly operate or maintain construction stormwater controls | ST6 |
| February 26, 2026 | Other noncompliance related to construction stormwater discharges | ST6 |
| February 26, 2026 | Failure to comply with recordkeeping requirements - construction stormwater [40 CFR 122.41(j)] | ST6 |
| February 26, 2026 | Failure to develop, maintain, or get approval of an adequate SWPPP (construction stormwater) | ST6 |
| February 26, 2026 | Failure to properly conduct construction stormwater inspections | ST6 |
| February 26, 2026 | Failure to properly install, initiate, or fully implement construction stormwater controls | ST6 |
| February 26, 2026 | Failure to properly operate or maintain construction stormwater controls | ST6 |
NPDES SCR10ZH7P: 4 inspections
| Date | What EPA recorded | Agency |
|---|---|---|
| April 10, 2026 | Evaluation | S |
| April 3, 2026 | Evaluation | S |
| March 20, 2026 | Evaluation | S |
| February 26, 2026 | Evaluation | S |
NPDES SCR10ZH7P: 1 informal enforcement action
| Date | What EPA recorded | Agency |
|---|---|---|
| March 6, 2026 | Notice of Noncompliance Issued | State |
NPDES SCR10ZH7P (FORTUNE SPRINGS PARK STORMWATER PROJECT): no formal enforcement action on file.
Watch NPDES SCR10ZH7P
NPDES SCR10ZH7P: one email when its EPA record changes — $99/month.