NPDES SDR10P5V3 · Clean Water Act
EAST 6TH AVE RECONSTRUCTION, Mitchell, SD: NPDES SDR10P5V3 discharge permit, effluent exceedances, inspections, penalties
EAST 6TH AVE RECONSTRUCTION, Mitchell, South Dakota: General permit coverage SDR10P5V3, held by Metro Construction Inc.; Construction stormwater; Effective; issued March 30, 2026, term to October 31, 2028, by SDDANR.
South Dakota holds 1,358 Construction stormwater coverages of this permit type in EPA’s file; 1,130 were issued before SDR10P5V3.
Coverages issued nearest SDR10P5V3
- 2026-03-27: SIOUX FALLS FIRE STATION 13, Sioux Falls: SDR10P5UP, held by City of Sioux Falls
- 2026-03-30: LEGACY COURT UTILITY AND STREET IMPROVEMENTS, Mitchell: SDR10P5U1, held by Groeneweg Construction
- 2026-03-30: RAISING CANE'S #C1547 SIOUX FALLS, SD, Sioux Falls: SDR10P5UA, held by Zernco, Inc.
- 2026-03-30: B-21 EAST ALERT APRON EPS, Ellsworth Air Force Base: SDR10P5UV, held by BRYAN CONSTRUCTION
- 2026-03-30: EAST 5TH AVENUE RECONSTRUCTION, Mitchell: SDR10P5V1, held by Halme, Inc.
- 2026-03-30: MINNEHAHA COUNTY SUBSTATION GRADING, Lyons: SDR10P5V4, held by East River Electric Power Cooperative, Inc.
- 2026-03-30: ROCHFORD MINERAL EXPLORATION, Rochford: SDR10P5V5, held by Pete Lien & Sons, Inc.
- 2026-04-07: OAHE DAM SPILLWAY REHABILITATION, Fort Pierre: SDR10P5UK, held by Construction Leaders Company, LLC
- 2026-04-20: BMU RAW & TREATED WATER PIPELINE - PHASE 6, Brookings: SDR10P5UG, held by Brookings Municipal Utilities
- 2026-04-20: HWY 105 & HWY 116 ROUNDABOUT, Lennox: SDR10P5UI, held by BX Civil & Construction
EAST 6TH AVE RECONSTRUCTION among its neighbors
13 discharge permits are in the Lake Mitchell-Firesteel Creek subwatershed (HUC 101600110908); SDR10P5V3 is one.
Other permits in the Lake Mitchell-Firesteel Creek subwatershed (HUC 101600110908)
- 23RD AND OHLMAN UTILITY AND STREET IMPROVEMENTS, Mitchell: SDR10P5YJ, minor, term to 2028-10-31
- ASHBROOK TRAIL APARTMENTS, Mitchell: SDR10P5LY, minor, term to 2028-10-31
- EAST 5TH AVENUE RECONSTRUCTION, Mitchell: SDR10P5V1, minor, term to 2028-10-31
- LEGACY COURT UTILITY AND STREET IMPROVEMENTS, Mitchell: SDR10P5U1, minor, term to 2028-10-31
- PCN 05UY, Mitchell: SDR10P442
- PCN 06FU, Mitchell: SDR10P581, minor, term to 2028-10-31
- PCN 06WT, Mitchell: SDR10P5UB, minor, term to 2028-10-31
- PEACEFUL PINES MITCHELL, Mitchell: SDR10P5RL, minor, term to 2028-10-31
- SOUTH LAKE ESTATES PHASE 1, Mitchell: SDR10P5CP, minor, term to 2028-10-31
- TORREY PINES - LAKE VIEW SECOND ADDITION, Mitchell: SDR10H280, minor, term to 2023-03-31
What stands out
- Its term runs 2 years and 215 days, March 30, 2026 to October 31, 2028.
- No dated event in the 365 days to October 14, 2026.
- It is one of 2,151 discharge permits on the register in South Dakota; 1,370 of them (64%) are in its program, Construction stormwater, and it is a minor discharger.
Identity
| Facility | EAST 6TH AVE RECONSTRUCTION |
|---|---|
| Permittee | Metro Construction Inc. |
| NPDES ID | SDR10P5V3 |
| Status | Effective |
| Type | General permit coverage |
| Class | Minor |
| Facility type | Non-POTW |
| Program | Construction stormwater |
| Issued | March 30, 2026 |
| Expires | October 31, 2028 |
| Agency | SDDANR |
| Address | Mitchell, SD 57301 |
| Subwatershed | Lake Mitchell-Firesteel Creek (HUC 101600110908) |
NPDES SDR10P5V3: effluent limits and exceedances
EAST 6TH AVE RECONSTRUCTION (NPDES SDR10P5V3): 0 pollutants on file, 0 limited; 0 with a violation of any kind, 0 with an exceedance.
NPDES SDR10P5V3: no pollutant row on file.
NPDES SDR10P5V3: inspections, violations and enforcement
NPDES SDR10P5V3 (EAST 6TH AVE RECONSTRUCTION): no single-event violation, inspection, formal enforcement action and informal enforcement action on file.
Watch NPDES SDR10P5V3
NPDES SDR10P5V3: one email when its EPA record changes — $99/month.
Permits near NPDES SDR10P5V3
NPDES SDR10P5V3: 0 pollutant rows, 0 dated events; ICIS-NPDES download, loaded October 14, 2026.