WALTON TEXAS WWTP, Howe, Texas: Individual permit TX0134783, held by WALTON TEXAS LP; Administratively continued; issued May 9, 2017, term to October 1, 2021; discharges to SQUIRREL CK;SCS SITE RESV 35A;SQUIRREL CK;E FORK T.
- September 9, 2026: Phone Call/ EMAIL (State).
Other permits held by WALTON TEXAS LP
- CROOKED CROSS WWTP, Gunter: TX0129879, issued 2016-10-10
- PCU-WRRF3 WWTP, Upland: TX0133892, issued 2017-05-19
- HUNT COUNTY WWTF, Greenville: TX0136425, issued 2021-05-24
WALTON TEXAS WWTP among its neighbors
21 discharge permits are in the Squirrel Creek-East Fork Trinity River subwatershed (HUC 120301060201); TX0134783 is one. Its county: 289, 3 major; TX0134783 is minor permit.
Other permits in the Squirrel Creek-East Fork Trinity River subwatershed (HUC 120301060201)
- BNSF LOGISTICS CENTER NORTH DALLAS, Gunter: TXR1527RV, minor, term to 2028-03-04
- CHASE OAKS, Gunter: TXR1599ZB, minor, term to 2028-03-04
- CONCRETE BATCH PLANT SUPPORTING THE BRIDGES, Gunter: TXR1545XT, minor, term to 2028-03-04
- COTTONWOOD, Dorchester: TXR1540XY, minor, term to 2028-03-04
- COTTONWOOD PH 1, Dorchester: TXR1565YE, minor, term to 2028-03-04
- COTTONWOOD PHASE 1 & FORD RD INFRASTRUCTURE, Dorchester: TXR1533QB, minor, term to 2028-03-04
- DEER CROSSING PHASE 2, Van Alstyne Etj: TXR1585TO, minor, term to 2028-03-04
- DORCHESTER SUBSTATION, Dorchester: TXR1593QH, minor, term to 2028-03-04
- DORCHESTER TERMINAL, Gunter: TXR1504YQ, minor, term to 2028-03-04
- GRAYSON CROSSING, Grayson County: TXR1518UD, minor, term to 2028-03-04
What stands out
- Its term runs 4 years and 145 days, May 9, 2017 to October 1, 2021; the term ended 1,839 days before EPA's file was loaded on October 14, 2026, and the file lists the permit as administratively continued.
- Its newest dated event on file is an informal enforcement action on September 9, 2026, 35 days before EPA's file was loaded.
- In the 365 days to October 14, 2026, it was dated 1 informal enforcement action.
- EPA's file dates 1 event for it, all in 2026.
- It is one of 39,714 discharge permits on the register in Texas; the file names no program for it, and it is a minor discharger.
Identity
| Facility | WALTON TEXAS WWTP |
|---|---|
| Permittee | WALTON TEXAS LP |
| NPDES ID | TX0134783 |
| Status | Administratively continued |
| Type | Individual permit |
| Class | Minor |
| Facility type | Non-POTW |
| Issued | May 9, 2017 |
| Expires | October 1, 2021 |
| Address | Howe, TX 75459 |
| Receiving water | SQUIRREL CK;SCS SITE RESV 35A;SQUIRREL CK;E FORK T |
| Subwatershed | Squirrel Creek-East Fork Trinity River (HUC 120301060201) |
| SIC | 4952 – Sewerage Systems |
NPDES TX0134783: effluent limits and exceedances
WALTON TEXAS WWTP (NPDES TX0134783): 0 pollutants on file, 0 limited; 0 with a violation of any kind, 0 with an exceedance.
NPDES TX0134783: no pollutant row on file.
NPDES TX0134783: inspections, violations and enforcement
NPDES TX0134783: 1 informal enforcement action
| Date | What EPA recorded | Agency |
|---|---|---|
| September 9, 2026 | Phone Call/ EMAIL | State |
NPDES TX0134783 (WALTON TEXAS WWTP): no single-event violation, inspection and formal enforcement action on file.
Watch NPDES TX0134783
NPDES TX0134783: one email when its EPA record changes — $99/month.
Permits near NPDES TX0134783
NPDES TX0134783: 0 pollutant rows, 1 dated events; ICIS-NPDES download, loaded October 14, 2026.