Velarion Records
Free: one email when NPDES TXR05GU82 changes. Unsubscribe any time.

NPDES TXR05GU82 · Clean Water Act

FM 223 PIT, Shepherd, TX: NPDES TXR05GU82 discharge permit, effluent exceedances, inspections, penalties

FM 223 PIT, Shepherd, Texas: General permit coverage TXR05GU82, held by Texas Concrete Sand And Gravel San Jac LLC; Industrial stormwater; Administratively continued; issued September 11, 2025, term to August 13, 2026; Construction Sand and Gravel Mining.

14 of the 15 pollutants listed for NPDES TXR05GU82 have no violation or effluent exceedance.

  • pH: 24 limits, 8 violations of any kind.
  • Solids, total suspended: 4 limits.
  • Nitrite + Nitrate total [as N]: 4 limits.
  • Arsenic, total [as As]: 4 limits.
  • Barium, total [as Ba]: 4 limits.
  • Cadmium, total [as Cd]: 4 limits.
  • Chromium, total [as Cr]: 4 limits.
  • Copper, total [as Cu]: 4 limits.
  • Lead, total [as Pb]: 4 limits.
  • Manganese, total [as Mn]: 4 limits.
  • Nickel, total [as Ni]: 4 limits.
  • Silver, total [as Ag]: 4 limits.
  • Zinc, total [as Zn]: 4 limits.
  • Selenium, total [as Se]: 4 limits.
  • Mercury, total [as Hg]: 4 limits.
  • May 13, 2026: Phone Call/ EMAIL (State).

Texas holds 8,480 Industrial stormwater coverages of this permit type in EPA’s file; 7,109 were issued before TXR05GU82. Texas Concrete Sand And Gravel San Jac LLC holds 2 permits in Texas.

Other permits held by Texas Concrete Sand And Gravel San Jac LLC

  • FM 223 PIT, Shepherd: TXR1505QV, issued 2024-05-09

Coverages issued nearest TXR05GU82

FM 223 PIT among its neighbors

6 discharge permits are in the Big Creek-Trinity River subwatershed (HUC 120302021207); TXR05GU82 is one. Its county: 35, 0 major; TXR05GU82 is minor permit.

Other permits in the Big Creek-Trinity River subwatershed (HUC 120302021207)

What stands out

  • Its term runs 336 days, September 11, 2025 to August 13, 2026; the term ended 62 days before EPA's file was loaded on October 14, 2026, and the file lists the permit as administratively continued.
  • Its newest dated event on file is an informal enforcement action on May 13, 2026, 154 days before EPA's file was loaded.
  • In the 365 days to October 14, 2026, it was dated 1 informal enforcement action.
  • EPA's file dates 1 event for it, all in 2026.
  • It is one of 39,714 discharge permits on the register in Texas; 8,480 of them (21%) are in its program, Industrial stormwater, and it is a minor discharger.

Identity

FacilityFM 223 PIT
PermitteeTexas Concrete Sand And Gravel San Jac LLC
NPDES IDTXR05GU82
StatusAdministratively continued
TypeGeneral permit coverage
ClassMinor
Facility typeNon-POTW
ProgramIndustrial stormwater
IssuedSeptember 11, 2025
ExpiresAugust 13, 2026
AddressShepherd, TX 77371
SubwatershedBig Creek-Trinity River (HUC 120302021207)
NAICS212321 – Construction Sand and Gravel Mining
SIC1442 – Construction Sand And Gravel

NPDES TXR05GU82: effluent limits and exceedances

FM 223 PIT (NPDES TXR05GU82): 15 pollutants on file, 15 limited; 1 with a violation of any kind, 0 with an exceedance.

How exceedances are counted.

PollutantLimitsViolationsExceedancesLatestLargest, as filed
pH2480
Solids, total suspended400
Nitrite + Nitrate total [as N]400
Arsenic, total [as As]400
Barium, total [as Ba]400
Cadmium, total [as Cd]400
Chromium, total [as Cr]400
Copper, total [as Cu]400
Lead, total [as Pb]400
Manganese, total [as Mn]400
Nickel, total [as Ni]400
Silver, total [as Ag]400
Zinc, total [as Zn]400
Selenium, total [as Se]400
Mercury, total [as Hg]400

NPDES TXR05GU82: inspections, violations and enforcement

NPDES TXR05GU82: 1 informal enforcement action

DateWhat EPA recordedAgency
May 13, 2026Phone Call/ EMAILState

NPDES TXR05GU82 (FM 223 PIT): no single-event violation, inspection and formal enforcement action on file.

Watch NPDES TXR05GU82

NPDES TXR05GU82: one email when its EPA record changes — $99/month.

Billing

Privacy

Permits near NPDES TXR05GU82

NPDES TXR05GU82: 15 pollutant rows, 1 dated events; ICIS-NPDES download, loaded October 14, 2026.