NPDES TXR1580WS · Clean Water Act
AMRIZE SILO EXPANSION PROJECT, Midlothian, TX: NPDES TXR1580WS discharge permit, effluent exceedances, inspections, penalties
AMRIZE SILO EXPANSION PROJECT, Midlothian, Texas: General permit coverage TXR1580WS, held by Amrize Cement Inc.; Construction stormwater; Effective; issued December 12, 2025, term to March 4, 2028; discharges to UNNAMED TRIBUTARY TO WAXAHACHIE CREEK.
Texas holds 23,986 Construction stormwater coverages of this permit type in EPA’s file; 17,597 were issued before TXR1580WS.
Coverages issued nearest TXR1580WS
- 2025-12-12: THE MEADOW ONSITE, North Richland Hills: TXR1575WS, held by Atmos Energy Corporation
- 2025-12-12: THE MEADOW ONSITE, North Richland Hills: TXR1576WS, held by D C G Construction LLC
- 2025-12-12: MAPLEWOOD MEADOWS, City Of Talty Etj: TXR1577WS, held by D.R. Horton - Texas, Ltd.
- 2025-12-12: ALAMO CITY SUBSTATION ESS, San Antonio: TXR1578WS, held by SCHIGUT, MICHA ZANE
- 2025-12-12: EMBARCADERO WATER SUPPLY COMPANY-RIVER PUMPING FACILITY TRAN, Laredo: TXR1579WS, held by Mtz Construction, Inc.
- 2025-12-12: RADIANT SPRINGS - LAND DEVELOPMENT, Forney: TXR1581WS, held by Sixth Element Developments LLC
- 2025-12-12: PRESERVE AT CULEBRA AMENITY EXPANSION, San Antonio: TXR1582WS, held by KB Home Lone Star Inc.
- 2025-12-12: MIDLINE, Clear Lake: TXR1583WS, held by Toll Bros., Inc.
- 2025-12-12: RVISION HOMES, Plantersville: TXR1584WS, held by Rvision Homes Ltd
- 2025-12-12: T1 ENERGY G2, Rockdale: TXR1585WS, held by Mine Service, Inc.
AMRIZE SILO EXPANSION PROJECT among its neighbors
41 discharge permits are in the Headwaters Waxahachie Creek subwatershed (HUC 120301090301); TXR1580WS is one. Its county: 460, 4 major; TXR1580WS is minor permit.
Other permits in the Headwaters Waxahachie Creek subwatershed (HUC 120301090301)
- 7-ELEVEN MIDLOTHIAN TX, Midlothian: TXR1551YK, minor, term to 2028-03-04
- BRIDGEWATER, Midlothian: TXR1560MG, minor, term to 2028-03-04
- BRIDGEWATER, Midlothian: TXR1596MH, minor, term to 2028-03-04
- BRIDGEWATER, Midlothian: TXR1597MD, minor, term to 2028-03-04
- BRIDGEWATER - HOME BUILDING, Midlothian: TXR1504XF, minor, term to 2028-03-04
- BRIDGEWATER PHASE 2A, Midlothian: TXR1507SC, minor, term to 2028-03-04
- BRIDGEWATER PHASE 2A, Midlothian: TXR1522RR, minor, term to 2028-03-04
- BRIDGEWATER PHASE 2A, Midlothian: TXR1525RS, minor, term to 2028-03-04
- BRIDGEWATER PHASE 2B BATCH PLANT AND PAVING, Midlothian: TXR1542QO, minor, term to 2028-03-04
- BRIDGEWATER PHS 2B, Midlothian: TXR1593PV, minor, term to 2028-03-04
What stands out
- Its term runs 2 years and 83 days, December 12, 2025 to March 4, 2028.
- No dated event in the 365 days to September 15, 2026.
- It is one of 39,714 discharge permits on the register in Texas; 23,986 of them (60%) are in its program, Construction stormwater, and it is a minor discharger.
Identity
| Facility | AMRIZE SILO EXPANSION PROJECT |
|---|---|
| Permittee | Amrize Cement Inc. |
| NPDES ID | TXR1580WS |
| Status | Effective |
| Type | General permit coverage |
| Class | Minor |
| Facility type | Non-POTW |
| Program | Construction stormwater |
| Issued | December 12, 2025 |
| Expires | March 4, 2028 |
| Address | Midlothian, TX 76065 |
| Receiving water | UNNAMED TRIBUTARY TO WAXAHACHIE CREEK |
| Subwatershed | Headwaters Waxahachie Creek (HUC 120301090301) |
NPDES TXR1580WS: effluent limits and exceedances
AMRIZE SILO EXPANSION PROJECT (NPDES TXR1580WS): 0 pollutants on file, 0 limited; 0 with a violation of any kind, 0 with an exceedance.
NPDES TXR1580WS: no pollutant row on file.
NPDES TXR1580WS: inspections, violations and enforcement
NPDES TXR1580WS (AMRIZE SILO EXPANSION PROJECT): no single-event violation, inspection, formal enforcement action and informal enforcement action on file.
Watch NPDES TXR1580WS
NPDES TXR1580WS: one email when its EPA record changes — $99/month.
Permits near NPDES TXR1580WS
NPDES TXR1580WS: 0 pollutant rows, 0 dated events; ICIS-NPDES download, loaded September 15, 2026.