BOXCAR 150MW300 MWH BESS & 13834.5KV SUBSTATION, Wylie, TX: NPDES TXR1585VU discharge permit, effluent exceedances, inspections, penalties
BOXCAR 150MW300 MWH BESS & 13834.5KV SUBSTATION, Wylie, Texas: General permit coverage TXR1585VU, held by Saber Power Services, LLC; Construction stormwater; Effective; issued September 10, 2025, term to March 4, 2028; discharges to LAKE RAY HUBBARD.
Texas holds 23,986 Construction stormwater coverages of this permit type in EPA’s file; 15,741 were issued before TXR1585VU. Saber Power Services, LLC holds 27 permits in Texas.
Other permits held by Saber Power Services, LLC
- EAST WEST 120MW BESS & 13834.5KV SUBSTATION, Mountain Home: TXR1501VY, issued 2025-09-23
- OVERLAND SUBSTATION S812 ADDITION, Fort Stockton: TXR1503XK, issued 2026-02-19
- SAN MARCOS SUBSTATION, San Marcos: TXR1508SL, issued 2024-10-15
- BAKERFIELD SYNCHRONOUS CONDENSER, Fort Stockton: TXR1514WJ, issued 2025-11-05
- PASTOR SUBSTATION S805 ADDITON, Paint Rock: TXR1519XD, issued 2026-01-28
- JOHN DUMAS SUBSTATION ADDITION, Maxwell: TXR1520NY, issued 2023-08-10
- ROCK ROSE BESS, Needville: TXR1521WT, issued 2025-12-15
- COUNTY LINE SUBSTATION, Cedar Creek: TXR1523YE, issued 2026-05-07
- HIGHLINE SUBSTATION, Cedar Creek: TXR1530XS, issued 2026-03-23
- MULSHOE 345 KV SUBSTATION, Gail: TXR1531YP, issued 2026-06-18
Coverages issued nearest TXR1585VU
- 2025-09-10: OUR REDEEMER LUTHERAN CHURCH CLASSROOM, Dallas: TXR1578VU, held by Artisan, Inc. Dba Acs Commercial
- 2025-09-10: B24-0402 - SOIL SLOPES REMEDIATION - PHASE 3, Dfw Airport: TXR1579VU, held by Urban Infraconstruction LLC
- 2025-09-10: COPPER RANCH IMPROVEMENT, Fort Worth: TXR1580VU, held by MLGP, LLC
- 2025-09-10: DECKER COVE, Magnolia: TXR1581VU, held by Woodmere Development Co.,Ltd
- 2025-09-10: SOLID ROCK VILLAGE, Houston: TXR1583VU, held by Burghli Land Development LLC
- 2025-09-10: PANTHER HOLLOW GAS STATION, Marble Falls: TXR1588VU, held by Primehaven Development LLC
- 2025-09-10: NORTH SEGUIN COMMERCIAL GAS STATION, Seguin: TXR1589VU, held by Primehaven Development LLC
- 2025-09-10: TEEL 380 ADDITION - LOT 6 & 7 BLOCK A, Prosper: TXR1590VU, held by Novel Builders LLC
- 2025-09-10: JJCH DIGESULADO RESIDENCE, Austin: TXR1591VU, held by Hagy Custom Homes, Inc.
- 2025-09-11: CHAPEL ROAD WIDENING, Waco: TXR1502VV, held by Ttg Utilities, Inc.
BOXCAR 150MW300 MWH BESS & 13834.5KV SUBSTATION among its neighbors
74 discharge permits are in the Cottonwood Creek-East Fork Trinity River subwatershed (HUC 120301060402); TXR1585VU is one. Its county: 1,523, 14 major; TXR1585VU is minor permit.
Other permits in the Cottonwood Creek-East Fork Trinity River subwatershed (HUC 120301060402)
- 260 FOX HOLLOW BEAVER CREEK ESTATES - HOME BUILDING, Wylie: TXR1502YQ, minor, term to 2028-03-04
- CITY OF ROCKWALL MS4, Rockwall: TXR040278, minor, term to 2024-01-24
- CITY OF WYLIE FM 544 RECONSTRUCTION, Wylie: TXR1575PR, minor, term to 2028-03-04
- CITY OF WYLIE MS4, Wylie: TXR040075, minor, term to 2024-01-23
- CROSSPOINT COMMUNITY CHURCH, Rockwall: TXR1558XY, minor, term to 2028-03-04
- DUWEST ROCKWALL, Rockwall: TXR1504QN, minor, term to 2028-03-04
- FLORIDAYS SAPPHIRE BAY - EAST BLOCK, Rowlett: TXR1577MR, minor, term to 2028-03-04
- GIDEON GROVE, Rockwall: TXR1546SF, minor, term to 2028-03-04
- GOLIAD FLEXSPACE, Rockwall: TXR1526XH, minor, term to 2028-03-04
- GP&L TRANSMISSION SERVICES STORAGE FACILTY, Garland: TXR1596UY, minor, term to 2028-03-04
What stands out
- Its term runs 2 years and 176 days, September 10, 2025 to March 4, 2028.
- No dated event in the 365 days to September 15, 2026.
- It is one of 39,714 discharge permits on the register in Texas; 23,986 of them (60%) are in its program, Construction stormwater, and it is a minor discharger.
Identity
| Facility | BOXCAR 150MW300 MWH BESS & 13834.5KV SUBSTATION |
|---|---|
| Permittee | Saber Power Services, LLC |
| NPDES ID | TXR1585VU |
| Status | Effective |
| Type | General permit coverage |
| Class | Minor |
| Facility type | Non-POTW |
| Program | Construction stormwater |
| Issued | September 10, 2025 |
| Expires | March 4, 2028 |
| Address | Wylie, TX 75098 |
| Receiving water | LAKE RAY HUBBARD |
| Subwatershed | Cottonwood Creek-East Fork Trinity River (HUC 120301060402) |
NPDES TXR1585VU: effluent limits and exceedances
BOXCAR 150MW300 MWH BESS & 13834.5KV SUBSTATION (NPDES TXR1585VU): 0 pollutants on file, 0 limited; 0 with a violation of any kind, 0 with an exceedance.
NPDES TXR1585VU: no pollutant row on file.
NPDES TXR1585VU: inspections, violations and enforcement
NPDES TXR1585VU (BOXCAR 150MW300 MWH BESS & 13834.5KV SUBSTATION): no single-event violation, inspection, formal enforcement action and informal enforcement action on file.
Watch NPDES TXR1585VU
NPDES TXR1585VU: one email when its EPA record changes — $99/month.
Permits near NPDES TXR1585VU
NPDES TXR1585VU: 0 pollutant rows, 0 dated events; ICIS-NPDES download, loaded September 15, 2026.