NPDES TXR1587JR · Clean Water Act
ENCHANTED BLUFF UNIT 1, San Antonio, TX: NPDES TXR1587JR discharge permit, effluent exceedances, inspections, penalties
ENCHANTED BLUFF UNIT 1, San Antonio, Texas: General permit coverage TXR1587JR, held by 2020 FI Dierks, LLC; Construction stormwater; Administratively continued; issued July 1, 2022, term to March 4, 2023; discharges to CIBOLO CREEK.
- September 4, 2026: Follow-Up (S).
- December 6, 2023: Permit Violations - Violation Specified in Comment (ST6).
Texas holds 23,986 Construction stormwater coverages of this permit type in EPA’s file; 730 were issued before TXR1587JR.
Coverages issued nearest TXR1587JR
- 2022-07-01: THE RESERVE AT SKYLINE MOUNTAIN, Copperas Cove: TXR1509JS, held by Dmd Construction LLC
- 2022-07-01: SOMERSET AT SINTON SUBDIVISION UNIT 1 & 2, Sinton: TXR1510JS, held by MAX Underground Construction, LLC
- 2022-07-01: CITADEL RIDGE, Lubbock: TXR1584JR, held by Citadel Construction, LLC
- 2022-07-01: WHITE ROCK BLUFFS, Dallas: TXR1585JR, held by Stillwater Gc, LLC
- 2022-07-01: KATY MANOR SOUTH PHASE 3 DETENTION FACILITIES, Katy: TXR1586JR, held by Sterling Site Services LLC
- 2022-07-01: SCHMALZ ELEMENTARY SCHOOL - RENO & ADDITION, Houston: TXR1588JR, held by Stewart Builders, Inc.
- 2022-07-01: PASEO DEL ESTE UNIT 9 PH 3, El Paso: TXR1589JR, held by Hunt Communities GP, LLC
- 2022-07-01: MERIDIANA SECTION 56, Iowa Colony: TXR1590JR, held by Rodriguez Construction Group LLC
- 2022-07-01: MATHIS SUBSTATION CONSTRUCTION PROJECT, Mathis: TXR1591JR, held by AEP Texas Inc.
- 2022-07-01: CAMELOT 2920, Spring: TXR1592JR, held by SEMARCK LANDSCAPE SERVICES, INC.
ENCHANTED BLUFF UNIT 1 among its neighbors
26 discharge permits are in the Clear Fork-Cibolo Creek subwatershed (HUC 121003040201); TXR1587JR is one. Its county: 336, 4 major; TXR1587JR is minor permit.
Other permits in the Clear Fork-Cibolo Creek subwatershed (HUC 121003040201)
- 1604 LOGISTICS CENTER PHASE-1 SITE INFRASTRUCTURE, San Antonio: TXR1561WM, minor, term to 2028-03-04
- 4 VINES, San Antonio: TXRNEBP70, minor, term to 2026-08-13
- ALAMO CONCRETE PRODUCTS PLANT 8, San Antonio: TXG110095, minor, term to 2021-11-07
- ALAMO CONCRETE PRODUCTS SAN ANTONIO RM PLANT 8, San Antonio: TXR05FB87, minor, term to 2026-08-13
- ALAMO NEX EVANS YARD, San Antonio: TXR1595QV, minor, term to 2028-03-04
- COMPLETE LINE GLASS, San Antonio: TXR1515TE, minor, term to 2028-03-04
- COSTA OIL - NACO LOT 6, San Antonio: TXR1548TR, minor, term to 2028-03-04
- ENCHANTED BLUFF UNIT 1, San Antonio: TXR1524PV, minor, term to 2028-03-04
- ENCHANTED BLUFF UNIT 1, San Antonio: TXR1578PT, minor, term to 2028-03-04
- ENCHANTED BLUFF UNIT 1 AND 2, San Antonio: TXR1595VJ, minor, term to 2028-03-04
What stands out
- Its term runs 246 days, July 1, 2022 to March 4, 2023; the term ended 1,320 days before EPA's file was loaded on October 14, 2026, and the file lists the permit as administratively continued.
- Its newest dated event on file is an inspection on September 4, 2026, 40 days before EPA's file was loaded.
- In the 365 days to October 14, 2026, it was dated 1 inspection.
- EPA's file dates 2 events for it, from 2023 to 2026.
- It is one of 39,714 discharge permits on the register in Texas; 23,986 of them (60%) are in its program, Construction stormwater, and it is a minor discharger.
Identity
| Facility | ENCHANTED BLUFF UNIT 1 |
|---|---|
| Permittee | 2020 FI Dierks, LLC |
| NPDES ID | TXR1587JR |
| Status | Administratively continued |
| Type | General permit coverage |
| Class | Minor |
| Facility type | Non-POTW |
| Program | Construction stormwater |
| Issued | July 1, 2022 |
| Expires | March 4, 2023 |
| Address | San Antonio, TX 78266 |
| Receiving water | CIBOLO CREEK |
| Subwatershed | Clear Fork-Cibolo Creek (HUC 121003040201) |
| SIC | 6552 – Subdividers And Developers |
NPDES TXR1587JR: effluent limits and exceedances
ENCHANTED BLUFF UNIT 1 (NPDES TXR1587JR): 0 pollutants on file, 0 limited; 0 with a violation of any kind, 0 with an exceedance.
NPDES TXR1587JR: no pollutant row on file.
NPDES TXR1587JR: inspections, violations and enforcement
NPDES TXR1587JR: 1 single-event violation
| Date | What EPA recorded | Agency |
|---|---|---|
| December 6, 2023 | Permit Violations - Violation Specified in Comment | ST6 |
NPDES TXR1587JR: 1 inspection
| Date | What EPA recorded | Agency |
|---|---|---|
| September 4, 2026 | Follow-Up | S |
NPDES TXR1587JR (ENCHANTED BLUFF UNIT 1): no formal enforcement action and informal enforcement action on file.
Watch NPDES TXR1587JR
NPDES TXR1587JR: one email when its EPA record changes — $99/month.
Permits near NPDES TXR1587JR
NPDES TXR1587JR: 0 pollutant rows, 2 dated events; ICIS-NPDES download, loaded October 14, 2026.