NPDES UTR266299 · Clean Water Act
HUNTINGTON POWER PLANT, Huntington, UT: NPDES UTR266299 discharge permit, effluent exceedances, inspections, penalties
HUNTINGTON POWER PLANT, Huntington, Utah: General permit coverage UTR266299, held by Pacificorp Energy-Huntington Plant; Industrial stormwater; Administratively continued; issued January 1, 2020, term to December 31, 2023, by Utah Division of Water Quality; discharges to Huntington Creek, Deer Creek.
Utah holds 1,101 Industrial stormwater coverages of this permit type in EPA’s file; 595 were issued before UTR266299.
Coverages issued nearest UTR266299
- 2020-01-01: TALONS COVE ASPHALT PLANT, Eagle Mountain: UTR263683, held by Granite Construction Company
- 2020-01-01: OGDEN RECYCLING, Ogden: UTR263977, held by Ogden Recycling
- 2020-01-01: PACIFICORP ENERGY - BLUNDELL GEOTHERMAL PLANT, Milford: UTR264017, held by PacifiCorp Energy - Blundell Geothermal Plant
- 2020-01-01: SALT LAKE CITY RLC 218, Salt Lake City: UTR265679, held by Propak Logistics Inc
- 2020-01-01: G.S. HARRIS COMPANY, INC., Ogden: UTR265931, held by G S HARRIS COMPANY INC.
- 2020-01-01: ALTIUM PACKAGING - CLEARFIELD, Clearfield: UTR266633, held by Consolidated Container Company L.P.
- 2020-01-01: DANIELS PIT, Heber City: UTR267607, held by Staker Parson Companies
- 2020-01-01: GENEVA ROCK PRODUCTS: HELPER, Helper: UTR267793, held by Geneva Rock Products, Inc
- 2020-01-01: GENEVA ROCK PRODUCTS: PAYSON, Payson: UTR268053, held by Geneva Rock Products-Payson
- 2020-01-01: HONEYWELL ELECTRONIC MATERIALS, Salt Lake City: UTR268135, held by Honeywell Electronic Chemicals
HUNTINGTON POWER PLANT among its neighbors
9 discharge permits are in the Huntington Lake-Huntington Creek subwatershed (HUC 140600090105); UTR266299 is one. Its county: 35, 1 major; UTR266299 is minor permit.
Other permits in the Huntington Lake-Huntington Creek subwatershed (HUC 140600090105)
- DEER CREEK MINE, Huntington: UTRC01404, minor, term to 2021-10-09
- HUNTINGTON ASPHALT PLANT, Huntington: UTR281661, minor, term to 2021-12-31
- HUNTINGTON EQUIPMENT YARD, Huntington: UTR000682, minor, term to 2010-12-31
- HUNTINGTON EQUIPMENT YARD, Huntington: UTR269007, minor, term to 2018-12-31
- HUNTINGTON SHOP, Huntington: UTR281631, minor, term to 2023-12-31
- ICM SOLUTIONS, Huntington: UTRI00467, minor, term to 2028-12-31
- NORTH EMERY WATER USERS SPECIAL SERVICE DISTRICT, Huntington: UTG640056, minor, term to 2028-06-30
- PACIFICORP - DEER CREEK MINE, Huntington: UT0023604, minor, term to 2020-01-31
Identity
| Facility | HUNTINGTON POWER PLANT |
|---|---|
| Permittee | Pacificorp Energy-Huntington Plant |
| NPDES ID | UTR266299 |
| Status | Administratively continued |
| Type | General permit coverage |
| Class | Minor |
| Facility type | Non-POTW |
| Program | Industrial stormwater |
| Issued | January 1, 2020 |
| Expires | December 31, 2023 |
| Agency | Utah Division of Water Quality |
| Address | Huntington, UT 84528 |
| Receiving water | Huntington Creek, Deer Creek |
| Receiving water impaired | 303(D) Listed |
| Subwatershed | Huntington Lake-Huntington Creek (HUC 140600090105) |
NPDES UTR266299: effluent limits and exceedances
HUNTINGTON POWER PLANT (NPDES UTR266299): 0 pollutants on file, 0 limited; 0 with a violation of any kind, 0 with an exceedance.
NPDES UTR266299: no pollutant row on file.
NPDES UTR266299: inspections, violations and enforcement
NPDES UTR266299 (HUNTINGTON POWER PLANT): no single-event violation, inspection, formal enforcement action and informal enforcement action on file.
Watch NPDES UTR266299