Clean Water Act discharge permit · NPDES UTRC05334
NIBLEY MEADOWS PHASE 3, Nibley, UT: NPDES UTRC05334 discharge permit, effluent exceedances, inspections, penalties
- Administratively continuedPermit status
- MinorDischarger class
- 0Pollutants under a numeric limit
- 0Pollutants with an effluent exceedance
- 0Inspections on file
- 0Formal enforcement actions
NIBLEY MEADOWS PHASE 3, held by Westates Construction LLC, holds NPDES permit UTRC05334. EPA’s file records it issued June 22, 2022 and expiring June 21, 2023. The status and dates are as EPA’s permit file stood when Velarion loaded it (September 15, 2026); EPA’s free Detailed Facility Report on ECHO carries the permit’s current standing.
What the register holds for NIBLEY MEADOWS PHASE 3: its NPDES ID, its permit type and status, its dates, its address in Nibley, Utah. EPA’s effluent violation file and its single-event violation file hold no violation for NPDES UTRC05334.
What stands out
- Its term runs 364 days, June 22, 2022 to June 21, 2023; the term ended 1,182 days before EPA's file was loaded on September 15, 2026, and the file lists the permit as administratively continued.
- No dated event in the 365 days to September 15, 2026.
- It is one of 17,184 discharge permits on the register in Utah; 14,166 of them (82%) are in its program, Construction stormwater, and it is a minor discharger.
Identity
| Facility as filed | NIBLEY MEADOWS PHASE 3 |
|---|---|
| Permittee as filed | Westates Construction LLC |
| NPDES ID | UTRC05334 |
| Permit status | Administratively continued (past its expiration date and still in force until reissued) |
| Permit type | Coverage under a general permit |
| Discharger class | Minor discharger |
| Facility type | Not a publicly owned treatment works |
| Program | Construction stormwater |
| Issued | June 22, 2022 |
| Expiration date | June 21, 2023 |
| Issuing agency | UTDEQ |
| Address | Nibley, UT 84321 |
| Receiving water impaired | 303(D) Listed |
| Subwatershed | Spring Creek (HUC 160102030402) |
Cited to the EPA ICIS-NPDES permit file (ECHO download).
Effluent limits and exceedances
- 0Pollutants on file
- 0Under a numeric limit
- 0With a violation of any kind
- 0With an effluent exceedance
EPA’s limits and effluent violation files hold no pollutant row for NPDES UTRC05334.
Cited to the EPA ICIS-NPDES limits and effluent violations files (ECHO download); up to 60 rows shown, most exceedances first.
Inspections, violations and enforcement
- 0Single-event violations
EPA’s single-event violation file, as loaded, holds no violation for NPDES UTRC05334.
Inspections
EPA’s inspection file holds no inspection for NPDES UTRC05334.
Formal enforcement and penalties
0 formal actions, 0 of them with a penalty assessed. Federal and state penalties are separate figures from separate authorities and are shown as each was filed, never added together.
Informal enforcement
EPA’s informal enforcement file holds no action for NPDES UTRC05334.
Cited to the EPA ICIS-NPDES violation, inspection and enforcement files (ECHO download); up to 50 rows of each shown, newest first.
Watch this permit
One permit holder, $99/month. Watch the register for one permit holder and the places and receiving waters tied to its permits. Choose “One permit holder” and enter this permit’s NPDES ID, UTRC05334.
Start the watch
- One permit holder — $99/month
- One watershed — $2,990/year
- One state — $4,990/year
- The whole register — $18,000/year
How we handle your data → Privacy
EPA publishes a free Detailed Facility Report for every permit on ECHO: its compliance status quarter by quarter, its inspections, and its enforcement actions and penalties. EPA also sends free notices of new inspections and enforcement actions through ECHO Notify; enter NPDES ID UTRC05334 there.
NIBLEY MEADOWS PHASE 3, Nibley, Utah: Coverage under a general permit UTRC05334, held by Westates Construction LLC; Construction stormwater; Administratively continued (past its expiration date and still in force until reissued); issued June 22, 2022, term to June 21, 2023, by UTDEQ.
Utah holds 14,146 Construction stormwater coverages of this permit type in EPA’s file; 4,200 were issued before UTRC05334. Westates Construction LLC holds 3 permits in Utah.
Other permits held by Westates Construction LLC
- NIBLEY MEADOWS PHASE 1, Nibley: UTRC05331, issued 2022-06-22
- NIBLEY MEADOWS PHASE 3, Nibley: UTRC07857, issued 2023-11-03
Coverages issued nearest UTRC05334
- 2022-06-22: JACOBS RESIDENCE, Hideout: UTRC05327, held by Jason Gyllenskog
- 2022-06-22: LOT 3 MEADOWS AT TERAKEE FARMS, Ogden: UTRC05328, held by CHAD ZITO
- 2022-06-22: LOT 7 MEADOWS AT TERAKEE FARMS, Ogden: UTRC05329, held by CHAD ZITO
- 2022-06-22: MOUNTAIN RIDGE PARK, Highland: UTRC05330, held by Stratton & Bratt
- 2022-06-22: NIBLEY MEADOWS PHASE 1, Nibley: UTRC05331, held by Westates Construction LLC
- 2022-06-22: PINNACLE 20, Park City: UTRC05335, held by Greg Young Construction LLC
- 2022-06-22: SCHOENVOGEL RESIDENCE, Park City: UTRH05453, held by PureHaven Homes
- 2022-06-22: PARK SIDE #103, Toquerville: UTRH05454, held by Wall 2 Wall Construction
- 2022-06-22: CARSON DETACH, Coalville: UTRH05457, held by Jason Carson
- 2022-06-23: PINNACLE LOT 43, Park City: UTRH05093, held by Promontory Homes
NIBLEY MEADOWS PHASE 3 among its neighbors
58 discharge permits are in the Spring Creek subwatershed (HUC 160102030402); UTRC05334 is one.
Other permits in the Spring Creek subwatershed (HUC 160102030402)
- 10 HERITAGE CROSSING, Nibley: UTRH06917, minor, term to 2024-08-01
- 1015 WEST 2350 SOUTH, Logan: UTRH01426, minor, term to 2021-10-05
- 1309 S 3200 W ZAK - SFD, Logan: UTRH07487, minor, term to 2025-01-16
- 4400 SOUTH 1450 WEST NIBLEY SHOP/ OFFICE, Nibley: UTRC10116, minor, term to 2026-01-08
- ARELLANO RESIDENCE, Wellsville: UTRH11694, minor, term to 2027-07-12
- AUBURN HILL, Hyrum: UTR379597, minor, term to 2023-05-13
- BLACKSMITH FORK PARK, Hyrum: UTRC01225, minor, term to 2021-09-11
- BRIAN HANSEN RESIDENCE, Wellsville: UTRH01379, minor, term to 2021-09-25
- BURGESS RESIDENCE, Nibley: UTRH11255, minor, term to 2027-04-23
- CHRISTINE SHORT HOME, Nibley: UTRC12412, minor, term to 2027-03-05
Nearby on the register
- Discharge permits in Nibley
- Every permit record in Nibley, A to Z
- Discharge permits in Utah
- Every permit record in Utah, A to Z
Figures from EPA’s ICIS-NPDES download, loaded September 15, 2026.
What this page shows
NIBLEY MEADOWS PHASE 3 is one of 42 storm water construction permits on EPA's NPDES register in Nibley, and 0.0% of those 42 permits have a violation on file. Of those same 42 Nibley storm water construction permits, 19.0% were issued before this one, and the permit sits among 58 NPDES permits in the Spring Creek subwatershed. It has no pollutants under a numeric limit and no pollutants with an effluent exceedance, both recorded as 0.