NPDES VAR10L571 · Clean Water Act
COLONIAL TRAIL WEST SOLAR PROJECT, Surry, VA: NPDES VAR10L571 discharge permit, effluent exceedances, inspections, penalties
COLONIAL TRAIL WEST SOLAR PROJECT, Surry, Virginia: General permit coverage VAR10L571, held by Virginia Electric and Power Co; Construction stormwater; Administratively continued; issued July 1, 2019, term to June 30, 2024, by VA DEQ; discharges to Cypress Swamp-Johnchecohunk Swamp.
- October 14, 2026: Evaluation (S).
- July 13, 2026: Evaluation (S).
- June 2, 2026: Evaluation (S).
Virginia holds 6,257 Construction stormwater coverages of this permit type in EPA’s file; 4 were issued before VAR10L571. Virginia Electric and Power Co holds 12 permits in Virginia.
Other permits held by Virginia Electric and Power Co
- DOMINION ASH HAUL ROAD AND BRIDGE OVER PROCTORS CR, Chester: VAR10G662, issued 2019-07-01
- BREMO POWER STATION, Bremo Bluff: VAR10H875, issued 2019-07-01
- BREMO BLUFF BORROW AREA, Fluvanna: VAR10I646, issued 2019-07-01
- GRASSHOPPER SOLAR, Mecklenburg: VAR10M798, issued 2019-07-01
- DOOMS REGIONAL LAYDOWN YARD, Augusta: VAR10M863, issued 2019-07-01
- BELCHER SOLAR, Louisa: VAR10N042, issued 2019-07-01
- BELCHER SOLAR PV AREA, Louisa: VAR10N574, issued 2019-07-01
- MAPLEWOOD SOLAR SUBSTATION AND SWITCHYARD, Chatham: VAR10N721, issued 2019-07-01
- MAPLEWOOD SOLAR MAIN PV AREA, Chatham: VAR10O122, issued 2019-07-01
- PUMPKINSEED SOLAR PROJECT PV ARRAY, Skippers: VAR10O882, issued 2019-07-01
Coverages issued nearest VAR10L571
- 2019-07-01: LORD RODNEY ESTATES LOT 7, Chesapeake: VAR10L485, held by Taylor Automotive Services Inc
- 2019-07-01: ROYAL SAIL AT BRIDGEPORT, Suffolk: VAR10L487, held by HBKC II LLC
- 2019-07-01: ASHBURN EAST PHASE 1 AND 2, Ashburn: VAR10L504, held by Equinix RP II LLC
- 2019-07-01: FIRST CHURCH OF COLUMBIA FURNACE, Edinburg: VAR10L543, held by Dennis George
- 2019-07-01: EWELL INDUSTRIAL PARK, Williamsburg: VAR10L570, held by Shaw Construction, Corp
- 2019-07-01: LIVING WATERS MINISTRY, Champbell: VAR10L572, held by Living Waters Ministry Inc
- 2019-07-01: HAYDEN VILLAGE CENTER, Franklin: VAR10L584, held by Luna Development Services LLC
- 2019-07-01: BREEZE HILL SECTION 4, Goochland: VAR10L610, held by Breeze Hill Inc.
- 2019-07-01: ROUTE 1 WIDENING FROM FEATHERSTONE TO MARYS WAY, Woodbridge: VAR10L683, held by Prince William County Dept of Transportation
- 2019-07-01: STERLING COMMUNITY CENTER, Sterling: VAR10L694, held by Forrester Construction Co
COLONIAL TRAIL WEST SOLAR PROJECT among its neighbors
4 discharge permits are in the Grays Creek subwatershed (HUC 020802060703); VAR10L571 is one.
Other permits in the Grays Creek subwatershed (HUC 020802060703)
- LOWER JAMES MITIGATION BANK PROJECT, Spring Grove: VAR10N394, minor, term to 2024-06-30
- SURRY COUNTY RESCUE SQUAD AND EMERGENCY OPERATION, Surry: VAR10L769, minor, term to 2024-06-30
- SURRY TOWN OF WWTF, Surry: VA0061646, minor, term to 2021-11-30
What stands out
- Its term runs 4 years and 365 days, July 1, 2019 to June 30, 2024; the term ended 807 days before EPA's file was loaded on September 15, 2026, and the file lists the permit as administratively continued.
- Its newest dated event on file is an inspection on October 14, 2026.
- In the 365 days to September 15, 2026, it was dated 2 inspections.
- EPA's file dates 3 events for it, all in 2026.
- It is one of 13,137 discharge permits on the register in Virginia; 6,257 of them (48%) are in its program, Construction stormwater, and it is a minor discharger.
Identity
| Facility | COLONIAL TRAIL WEST SOLAR PROJECT |
|---|---|
| Permittee | Virginia Electric and Power Co |
| NPDES ID | VAR10L571 |
| Status | Administratively continued |
| Type | General permit coverage |
| Class | Minor |
| Facility type | Non-POTW |
| Program | Construction stormwater |
| Issued | July 1, 2019 |
| Expires | June 30, 2024 |
| Agency | VA DEQ |
| Address | Surry, VA 23881 |
| Receiving water | Cypress Swamp-Johnchecohunk Swamp |
| Subwatershed | Grays Creek (HUC 020802060703) |
NPDES VAR10L571: effluent limits and exceedances
COLONIAL TRAIL WEST SOLAR PROJECT (NPDES VAR10L571): 0 pollutants on file, 0 limited; 0 with a violation of any kind, 0 with an exceedance.
NPDES VAR10L571: no pollutant row on file.
NPDES VAR10L571: inspections, violations and enforcement
NPDES VAR10L571: 3 inspections
| Date | What EPA recorded | Agency |
|---|---|---|
| October 14, 2026 | Evaluation | S |
| July 13, 2026 | Evaluation | S |
| June 2, 2026 | Evaluation | S |
NPDES VAR10L571 (COLONIAL TRAIL WEST SOLAR PROJECT): no single-event violation, formal enforcement action and informal enforcement action on file.
Watch NPDES VAR10L571
NPDES VAR10L571: one email when its EPA record changes — $99/month.
Permits near NPDES VAR10L571
NPDES VAR10L571: 0 pollutant rows, 3 dated events; ICIS-NPDES download, loaded September 15, 2026.