NPDES VAR10O094 · Clean Water Act
BLUE POINT AT RIVERFRON FUTURE PARCEL 1, Suffolk, VA: NPDES VAR10O094 discharge permit, effluent exceedances, inspections, penalties
BLUE POINT AT RIVERFRON FUTURE PARCEL 1, Suffolk, Virginia: General permit coverage VAR10O094, held by The Miller Group Companies Inc; Construction stormwater; Administratively continued; issued July 1, 2019, term to June 30, 2024, by VA DEQ; discharges to Nansemond River-Bennett Creek.
Virginia holds 6,257 Construction stormwater coverages of this permit type in EPA’s file; 4 were issued before VAR10O094. The Miller Group Companies Inc holds 2 permits in Virginia.
Other permits held by The Miller Group Companies Inc
- CORPORATE LANDING INDUSTRIAL, Virginia Beach: VAR10W854, issued 2024-07-01
Coverages issued nearest VAR10O094
- 2019-07-01: IWO JIMA MEMORIAL PARK, Williamsburg: VAR10O054, held by Iwo Jima Memorial Park Society
- 2019-07-01: WARSAW ACE, Warsaw: VAR10O057, held by Graylend Horn
- 2019-07-01: HOBBY LOBBY SITE PLAN BERMUDA SQUARE, Chester: VAR10O059, held by Southern Construction Utilities Inc
- 2019-07-01: VDOT ABINGDON - 0058-095-108 - UPC 16382, Washington County: VAR10O062, held by Virginia Dept of Transportation
- 2019-07-01: MONTGOMERY COUNTY PARKS AND RECREATION CREED FIELD, Elliston: VAR10O089, held by Montgomery County Board of Supervisors
- 2019-07-01: OPAL ROAD LOT 55-R, Warrenton: VAR10O095, held by Full House Investments LLC
- 2019-07-01: GREENWOOD SOLAR I LLC, Culpeper: VAR10O096, held by Greenwood Solar I LLC
- 2019-07-01: JSG CONTRACTORS OFFICE, Williamsburg: VAR10O099, held by JSG Corp
- 2019-07-01: TUSCARORA CROSSING LB 3, Leesburg: VAR10O105, held by DMM Tuscarora LLC
- 2019-07-01: POSSUM POINT POWER STATION PONDS ABC AND E CLOSURE, Dumfries: VAR10O106, held by Virginia Electric and Power Co dba Dominion Energy
BLUE POINT AT RIVERFRON FUTURE PARCEL 1 among its neighbors
46 discharge permits are in the Bennett Creek-Nansemond River subwatershed (HUC 020802080106); VAR10O094 is one.
Other permits in the Bennett Creek-Nansemond River subwatershed (HUC 020802080106)
- AMAZON COM SERVICES LLC - ORF 3, Suffolk: VAR052518, minor, term to 2024-06-30
- BCI EXPANSION, Suffolk: VAR10X476, minor, term to 2029-06-30
- BECO MEDICAL CENTER, Suffolk: VAR10R451, minor, term to 2024-06-30
- BENNETTS CREEK QUARTER PHASE I, Suffolk: VAR10M860, minor, term to 2024-06-30
- BENNETTS CREEK RECREATION CENTER RENOVATIONS, Suffolk: VAR10O444, minor, term to 2024-06-30
- BENNETTS PASTURE RD & NANSEMOND PKWY INTERSECTION, Suffolk: VAR10T761, minor, term to 2024-06-30
- BOB WHITE POINT, Suffolk: VAR10V744, minor, term to 2029-06-30
- BRIDGE 17 APARTMENTS, Suffolk: VAR10U082, minor, term to 2024-06-30
- BRIDGE ROAD AND SHOULDERS HILL ROAD INTERSECTION I, Suffolk: VAR10T590, minor, term to 2024-06-30
- CEDAR POINT COUNTRY CLUB, Suffolk: VAR10M723, minor, term to 2024-06-30
What stands out
- Its term runs 4 years and 365 days, July 1, 2019 to June 30, 2024; the term ended 807 days before EPA's file was loaded on September 15, 2026, and the file lists the permit as administratively continued.
- No dated event in the 365 days to September 15, 2026.
- It is one of 13,137 discharge permits on the register in Virginia; 6,257 of them (48%) are in its program, Construction stormwater, and it is a minor discharger.
Identity
| Facility | BLUE POINT AT RIVERFRON FUTURE PARCEL 1 |
|---|---|
| Permittee | The Miller Group Companies Inc |
| NPDES ID | VAR10O094 |
| Status | Administratively continued |
| Type | General permit coverage |
| Class | Minor |
| Facility type | Non-POTW |
| Program | Construction stormwater |
| Issued | July 1, 2019 |
| Expires | June 30, 2024 |
| Agency | VA DEQ |
| Address | Suffolk, VA 23435 |
| Receiving water | Nansemond River-Bennett Creek |
| Subwatershed | Bennett Creek-Nansemond River (HUC 020802080106) |
NPDES VAR10O094: effluent limits and exceedances
BLUE POINT AT RIVERFRON FUTURE PARCEL 1 (NPDES VAR10O094): 0 pollutants on file, 0 limited; 0 with a violation of any kind, 0 with an exceedance.
NPDES VAR10O094: no pollutant row on file.
NPDES VAR10O094: inspections, violations and enforcement
NPDES VAR10O094 (BLUE POINT AT RIVERFRON FUTURE PARCEL 1): no single-event violation, inspection, formal enforcement action and informal enforcement action on file.
Watch NPDES VAR10O094
NPDES VAR10O094: one email when its EPA record changes — $99/month.
Permits near NPDES VAR10O094
NPDES VAR10O094: 0 pollutant rows, 0 dated events; ICIS-NPDES download, loaded September 15, 2026.