NPDES VAR10P556 · Clean Water Act
PROJECT MANGO PHASE I, Bristow, VA: NPDES VAR10P556 discharge permit, effluent exceedances, inspections, penalties
PROJECT MANGO PHASE I, Bristow, Virginia: General permit coverage VAR10P556, held by Holder Construction Group LLC; Construction stormwater; Administratively continued; issued July 1, 2019, term to June 30, 2024, by VA DEQ; discharges to Broad Run-Rocky Branch.
Virginia holds 6,257 Construction stormwater coverages of this permit type in EPA’s file; 4 were issued before VAR10P556. Holder Construction Group LLC holds 3 permits in Virginia.
Other permits held by Holder Construction Group LLC
- PROJECT MANGO PHASE 1 STAGING AREA, Bristow, Prince William County: VAR10Q706, issued 2019-07-01
- DULLES BERRY LC4 DATA CENTER, Ashburn: VAR10Q910, issued 2019-07-01
Coverages issued nearest VAR10P556
- 2019-07-01: SANDY HILL SUBDIVISION, Hopewell: VAR10P542, held by James R Jones Builder Inc
- 2019-07-01: BRICKHOUSE POINTE SUBDIVISION PHASE II, Prince George: VAR10P543, held by James R Jones Builder Inc
- 2019-07-01: JEFFERSON PARK II, Prince George: VAR10P544, held by James R Jones Builder Inc
- 2019-07-01: FIRST BAPTIST CHURCH PARKING LOT, Spring Grove: VAR10P545, held by Edward Harrison
- 2019-07-01: CROWNPOINT INDEPENDENT LIVING, Rockingham: VAR10P549, held by Crownpoint Harrisonburg LLC
- 2019-07-01: RIP 3 LLC, Opal: VAR10P559, held by Donovan Construction LLC
- 2019-07-01: STORELAND SELF STORAGE, Cupeper: VAR10P565, held by Storeland Self Storage LLC
- 2019-07-01: MICHAEL DRIVE INDUSTRIAL PARK, Chesapeake: VAR10P566, held by Baylor Corp
- 2019-07-01: BANNER CHRISTIAN SCHOOL RECREATION FIELD, Chesterfield: VAR10P567, held by Banner Christian School
- 2019-07-01: TEMPLE BAPTIST CHURCH, Ashburn: VAR10P568, held by Temple Baptist Church INC
PROJECT MANGO PHASE I among its neighbors
184 discharge permits are in the Rocky Branch-Broad Run subwatershed (HUC 020700100504); VAR10P556 is one.
Other permits in the Rocky Branch-Broad Run subwatershed (HUC 020700100504)
- 11300 BRADEN DRIVE DEVELOPMENT, Manassas: VAR10T623, minor, term to 2024-06-30
- 13TH HIGH SCHOOL, Gainesville: VAR10M056, minor, term to 2024-06-30
- 7490 BETHLEHAM ROAD - MOTOR REPAIR SERVICES, Manassas: VAR10E473, minor, term to 2024-06-30
- 8033 DEVLIN LLC RESIDENCE, Bristow: VAG406071, minor, term to 2026-07-31
- 8760 VIRGINIA MEADOWS DRIVE, Manassas: VAR10W111, minor, term to 2029-06-30
- ABERDEEN ASSEMBLAGE LIMITED LIABILITY COMPANY, Nokesville: VAG406225, minor, term to 2026-07-31
- ADAMS GAINESVILLE CENTER - PHASE 1, Nokesville: VAR10Q796, minor, term to 2024-06-30
- AMAZON COM SERVICES LLC - DDC9, Gainesville: VAR052500, minor, term to 2024-06-30
- AMERICAN DISPOSAL SERVICES, Manassas: VAR052467, minor, term to 2024-06-30
- AMERICAN DISPOSAL SERVICES NATURAL GAS, Manassas: VAR10K533, minor, term to 2024-06-30
What stands out
- Its term runs 4 years and 365 days, July 1, 2019 to June 30, 2024; the term ended 807 days before EPA's file was loaded on September 15, 2026, and the file lists the permit as administratively continued.
- No dated event in the 365 days to September 15, 2026.
- It is one of 13,137 discharge permits on the register in Virginia; 6,257 of them (48%) are in its program, Construction stormwater, and it is a minor discharger.
Identity
| Facility | PROJECT MANGO PHASE I |
|---|---|
| Permittee | Holder Construction Group LLC |
| NPDES ID | VAR10P556 |
| Status | Administratively continued |
| Type | General permit coverage |
| Class | Minor |
| Facility type | Non-POTW |
| Program | Construction stormwater |
| Issued | July 1, 2019 |
| Expires | June 30, 2024 |
| Agency | VA DEQ |
| Address | Bristow, VA 20136 |
| Receiving water | Broad Run-Rocky Branch |
| Subwatershed | Rocky Branch-Broad Run (HUC 020700100504) |
NPDES VAR10P556: effluent limits and exceedances
PROJECT MANGO PHASE I (NPDES VAR10P556): 0 pollutants on file, 0 limited; 0 with a violation of any kind, 0 with an exceedance.
NPDES VAR10P556: no pollutant row on file.
NPDES VAR10P556: inspections, violations and enforcement
NPDES VAR10P556 (PROJECT MANGO PHASE I): no single-event violation, inspection, formal enforcement action and informal enforcement action on file.
Watch NPDES VAR10P556
NPDES VAR10P556: one email when its EPA record changes — $99/month.
Permits near NPDES VAR10P556
NPDES VAR10P556: 0 pollutant rows, 0 dated events; ICIS-NPDES download, loaded September 15, 2026.