NPDES VAR10S911 · Clean Water Act
LOUDOUN WATER MILESTONE RESERVOIR SITE, Ashburn, VA: NPDES VAR10S911 discharge permit, effluent exceedances, inspections, penalties
LOUDOUN WATER MILESTONE RESERVOIR SITE, Ashburn, Virginia: General permit coverage VAR10S911, held by Clark Construction Group LLC; Construction stormwater; Administratively continued; issued July 1, 2019, term to June 30, 2024, by VA DEQ; discharges to Goose Creek-Cattail Branch.
Virginia holds 6,257 Construction stormwater coverages of this permit type in EPA’s file; 4 were issued before VAR10S911. Clark Construction Group LLC holds 9 permits in Virginia.
Other permits held by Clark Construction Group LLC
- SOLID PROCESSING REHABILITATION CONTRACT 3, Lorton: VAR10L283, issued 2019-07-01
- QUAIL RIDGE QR, Aldie: VAR10M141, issued 2019-07-01
- GMU ARLINGTON CAMPUS, Alrington: VAR10P215, issued 2019-07-01
- NOMAN COLE JR. PCP PRIMARY AND SECONDARY SUSTAININ, Lorton: VAR10Q789, issued 2019-07-01
- LOUDOUN WATER MILESTONE RESERVOIR PUMP STATION SIT, Ashburn: VAR10T156, issued 2019-07-01
- FOSTER DRIVE 230KV ELECTRICAL SUBSTATION, Manassas: VAR10U294, issued 2024-07-01
- JCM LOUISA - CAMPUS 1 - ROADWAY, Louisa County: VAR10W610, issued 2024-07-01
- ARLINGTON NATIONAL CEMETERY PHASE III CEMETERY EXP, Arlington: VAR10X096, issued 2024-07-01
Coverages issued nearest VAR10S911
- 2019-07-01: REHABILITATION OF COLONIAL PARKWAY PHASE 1, Williamsburg: VAR10S893, held by Wagman Heavy Civil Inc
- 2019-07-01: CEDAR POINT, Poquoson: VAR10S897, held by Engle Construction, Inc.
- 2019-07-01: THE ARBORS AT GREENE COUNTY, Barboursville: VAR10S901, held by Greene Senior, LP
- 2019-07-01: FALLING CREEK STATION STORAGE YARD, Chesterfield: VAR10S906, held by Rampart Real Estate Partners DBA 6101 Jefferson Da
- 2019-07-01: DELTA STAR FABRICATION SHOP ADDITION, Lynchburg: VAR10S907, held by Blair Construction Inc.
- 2019-07-01: RESTORATION WOODS, Mechanicsville: VAR10S913, held by Geoffrey M. Lawrence
- 2019-07-01: SPRING ROCK GREEN PHASE 1-PARCEL 3 PARKING DECK, Richmond: VAR10S914, held by Economic Development Authority of the County of Ch
- 2019-07-01: CHEROKEE HILLS SECTION 6, Salem: VAR10S916, held by RFC2017 Land LLC
- 2019-07-01: HAMPTON RIDGE, Moseley: VAR10S920, held by J&J Land Development, LLC
- 2019-07-01: RIVER EAST, Henrico: VAR10S922, held by The Maggie Walker Community Land Trust
LOUDOUN WATER MILESTONE RESERVOIR SITE among its neighbors
64 discharge permits are in the Cattail Branch-Goose Creek subwatershed (HUC 020700080704); VAR10S911 is one.
Other permits in the Cattail Branch-Goose Creek subwatershed (HUC 020700080704)
- 107 MORVEN PARK ROAD, Leesburg: VAR10S390, minor, term to 2024-06-30
- AIRPORT COMMERCE PARK - PHASE 2, Leesburg: VAR10E205, minor, term to 2024-06-30
- BAKER/BEAM DC YARD - LUCK PROPERTY, Ashburn: VAR10S457, minor, term to 2024-06-30
- BARNES DEBORAH RESIDENCE, Leesburg: VAG406244, minor, term to 2026-07-31
- BATTLEFIELD PKWY TO CROSSTRAIL BLVD, Leesburg: VAR10S371, minor, term to 2024-06-30
- BELMONT INNOVATION CAMPUS - BUILDINGS 3&4 SANITARY, Ashburn: VAR10X156, minor, term to 2029-06-30
- BELMONT INNOVATION CAMPUS BUILDINGS 3 & 4, Ashburn: VAR10U844, minor, term to 2029-06-30
- BELMONT INNOVATION CAMPUS SUBSTATIONS, Ashburn: VAR10U147, minor, term to 2029-06-30
- BRICKYARD, Leesburg: VAR10T900, minor, term to 2024-06-30
- BROWNS CAR STORES BUILDING A, Leesburg: VAR10N702, minor, term to 2024-06-30
What stands out
- Its term runs 4 years and 365 days, July 1, 2019 to June 30, 2024; the term ended 807 days before EPA's file was loaded on September 15, 2026, and the file lists the permit as administratively continued.
- No dated event in the 365 days to September 15, 2026.
- It is one of 13,137 discharge permits on the register in Virginia; 6,257 of them (48%) are in its program, Construction stormwater, and it is a minor discharger.
Identity
| Facility | LOUDOUN WATER MILESTONE RESERVOIR SITE |
|---|---|
| Permittee | Clark Construction Group LLC |
| NPDES ID | VAR10S911 |
| Status | Administratively continued |
| Type | General permit coverage |
| Class | Minor |
| Facility type | Non-POTW |
| Program | Construction stormwater |
| Issued | July 1, 2019 |
| Expires | June 30, 2024 |
| Agency | VA DEQ |
| Address | Ashburn, VA 20147 |
| Receiving water | Goose Creek-Cattail Branch |
| Subwatershed | Cattail Branch-Goose Creek (HUC 020700080704) |
NPDES VAR10S911: effluent limits and exceedances
LOUDOUN WATER MILESTONE RESERVOIR SITE (NPDES VAR10S911): 0 pollutants on file, 0 limited; 0 with a violation of any kind, 0 with an exceedance.
NPDES VAR10S911: no pollutant row on file.
NPDES VAR10S911: inspections, violations and enforcement
NPDES VAR10S911 (LOUDOUN WATER MILESTONE RESERVOIR SITE): no single-event violation, inspection, formal enforcement action and informal enforcement action on file.
Watch NPDES VAR10S911
NPDES VAR10S911: one email when its EPA record changes — $99/month.
Permits near NPDES VAR10S911
NPDES VAR10S911: 0 pollutant rows, 0 dated events; ICIS-NPDES download, loaded September 15, 2026.