NPDES VAR10T168 · Clean Water Act
CHRISTENDOM COLLEGE - MADONNA HALL EXPANSION, Front Royal, VA: NPDES VAR10T168 discharge permit, effluent exceedances, inspections, penalties
CHRISTENDOM COLLEGE - MADONNA HALL EXPANSION, Front Royal, Virginia: General permit coverage VAR10T168, held by Christendom College LLC; Construction stormwater; Administratively continued; issued July 1, 2019, term to June 30, 2024, by VA DEQ; discharges to Shenandoah River-Manassas Run.
- October 28, 2026: Evaluation (S).
- October 26, 2026: Evaluation (S).
Virginia holds 6,257 Construction stormwater coverages of this permit type in EPA’s file; 4 were issued before VAR10T168.
Coverages issued nearest VAR10T168
- 2019-07-01: LEFT TURN LANE, Doswell: VAR10T157, held by Martin Marietta Materials, Inc
- 2019-07-01: KIRBY ROAD WALKWAY, Mclean: VAR10T159, held by FAIRFAX COUNTY DPWES
- 2019-07-01: SEEKFORD POULTRY HOUSES, Timberville: VAR10T162, held by Wade A. & Jacqueline K. Seekford
- 2019-07-01: AVC17 DATA CENTER, Clarksville: VAR10T165, held by Ames Construction Inc
- 2019-07-01: HUNTING RUN LANDING, Spotsylvania: VAR10T167, held by DRB Group
- 2019-07-01: SPRINGFIELD TOWN CENTER BUILDING R4, Springfield: VAR10T170, held by HANOVER R.S. CONSTRUCTION LLC
- 2019-07-01: FALLS FARM II, Great Falls: VAR10T172, held by AB LAND LLC
- 2019-07-01: ROYAL FARMS STORE #253, Port Royal: VAR10T173, held by Two Farms Inc
- 2019-07-01: CALDWELL MTN ESTATES, Troutville: VAR10T176, held by Building Consultants LLC
- 2019-07-01: CERULEAN SOLAR, Farnham: VAR10T177, held by Virginia Electric and Power Company (VEPCO) dba Do
CHRISTENDOM COLLEGE - MADONNA HALL EXPANSION among its neighbors
18 discharge permits are in the Manassas Run-Shenandoah River subwatershed (HUC 020700070102); VAR10T168 is one. Its county: 22, 1 major; VAR10T168 is minor permit.
Other permits in the Manassas Run-Shenandoah River subwatershed (HUC 020700070102)
- APPLE MOUNTAIN EXXON STP, Linden: VA0089958, minor, term to 2023-09-30
- BENNYS BEACH VPDES, Front Royal: VAG408582, minor, term to 2026-07-31
- BOAK MICHAEL E AND MICHELE M RESIDENCE, Linden: VAG401673, minor, term to 2026-07-31
- BUDWASH TERRY AND CATHERINE RESIDENCE, Linden: VAG401880, minor, term to 2026-07-31
- CHRISTENDOM COLLEGE STP, Front Royal: VA0067067, minor, term to 2023-12-31
- CHRISTENDOM COLLEGE STP, Front Royal: VAN010131, minor, term to 2021-12-31
- FRONT ROYAL WWTP, Front Royal: VA0062812, major, term to 2023-10-31
- FRONT ROYAL WWTP, Front Royal: VAN010010, minor, term to 2021-12-31
- LINDEN BUSINESS CENTER, Warrenton: VAG401578, minor, term to 2026-07-31
- MCCAFFERTY SHAWN RESIDENCE, Linden: VAG401754, minor, term to 2026-07-31
What stands out
- Its term runs 4 years and 365 days, July 1, 2019 to June 30, 2024; the term ended 807 days before EPA's file was loaded on September 15, 2026, and the file lists the permit as administratively continued.
- Its newest dated event on file is an inspection on October 28, 2026.
- No dated event in the 365 days to September 15, 2026.
- EPA's file dates 2 events for it, all in 2026.
- It is one of 13,137 discharge permits on the register in Virginia; 6,257 of them (48%) are in its program, Construction stormwater, and it is a minor discharger.
Identity
| Facility | CHRISTENDOM COLLEGE - MADONNA HALL EXPANSION |
|---|---|
| Permittee | Christendom College LLC |
| NPDES ID | VAR10T168 |
| Status | Administratively continued |
| Type | General permit coverage |
| Class | Minor |
| Facility type | Non-POTW |
| Program | Construction stormwater |
| Issued | July 1, 2019 |
| Expires | June 30, 2024 |
| Agency | VA DEQ |
| Address | Front Royal, VA 22630 |
| Receiving water | Shenandoah River-Manassas Run |
| Subwatershed | Manassas Run-Shenandoah River (HUC 020700070102) |
NPDES VAR10T168: effluent limits and exceedances
CHRISTENDOM COLLEGE - MADONNA HALL EXPANSION (NPDES VAR10T168): 0 pollutants on file, 0 limited; 0 with a violation of any kind, 0 with an exceedance.
NPDES VAR10T168: no pollutant row on file.
NPDES VAR10T168: inspections, violations and enforcement
NPDES VAR10T168: 2 inspections
| Date | What EPA recorded | Agency |
|---|---|---|
| October 28, 2026 | Evaluation | S |
| October 26, 2026 | Evaluation | S |
NPDES VAR10T168 (CHRISTENDOM COLLEGE - MADONNA HALL EXPANSION): no single-event violation, formal enforcement action and informal enforcement action on file.
Watch NPDES VAR10T168
NPDES VAR10T168: one email when its EPA record changes — $99/month.
Permits near NPDES VAR10T168
NPDES VAR10T168: 0 pollutant rows, 2 dated events; ICIS-NPDES download, loaded September 15, 2026.