Clean Water Act discharge permit · NPDES VAR10U084
UNITY TUNSTALL 230 KV LINES PHASE 2, Mecklenburg, VA: NPDES VAR10U084 discharge permit, effluent exceedances, inspections, penalties
- EffectivePermit status
- MinorDischarger class
- 0Pollutants under a numeric limit
- 0Pollutants with an effluent exceedance
- 1Inspections on file
- 0Formal enforcement actions
UNITY TUNSTALL 230 KV LINES PHASE 2, held by Virginia Electric and Power Co dba Dominion Energy, holds NPDES permit VAR10U084, which discharges to Meherrin River-Taylors Creek. EPA’s file records it issued July 1, 2024 and expiring June 30, 2029. The status and dates are as EPA’s permit file stood when Velarion loaded it (September 15, 2026); EPA’s free Detailed Facility Report on ECHO carries the permit’s current standing.
What stands out
- Its term runs 4 years and 364 days, July 1, 2024 to June 30, 2029.
- Its newest dated event on file is an inspection on June 16, 2026, 91 days before EPA's file was loaded.
- In the 365 days to September 15, 2026, it was dated 1 inspection.
- EPA's file dates 1 event for it, all in 2026.
- It is one of 13,137 discharge permits on the register in Virginia; 6,257 of them (48%) are in its program, Construction stormwater, and it is a minor discharger.
Identity
| Facility as filed | UNITY TUNSTALL 230 KV LINES PHASE 2 |
|---|---|
| Permittee as filed | Virginia Electric and Power Co dba Dominion Energy |
| NPDES ID | VAR10U084 |
| Permit status | Effective |
| Permit type | Coverage under a general permit |
| Discharger class | Minor discharger |
| Facility type | Not a publicly owned treatment works |
| Program | Construction stormwater |
| Issued | July 1, 2024 |
| Expiration date | June 30, 2029 |
| Issuing agency | VA DEQ |
| Address | Mecklenburg, VA 23915 |
| Receiving water | Meherrin River-Taylors Creek |
| Subwatershed | Stony Creek-Meherrin River (HUC 030102040401) |
Cited to the EPA ICIS-NPDES permit file (ECHO download).
Effluent limits and exceedances
- 0Pollutants on file
- 0Under a numeric limit
- 0With a violation of any kind
- 0With an effluent exceedance
EPA’s limits and effluent violation files hold no pollutant row for NPDES VAR10U084.
Cited to the EPA ICIS-NPDES limits and effluent violations files (ECHO download); up to 60 rows shown, most exceedances first.
Inspections, violations and enforcement
- 0Single-event violations
EPA’s single-event violation file, as loaded, holds no violation for NPDES VAR10U084.
Inspections
| Date | What EPA recorded | Agency |
|---|---|---|
| June 16, 2026 | Evaluation | S |
Formal enforcement and penalties
0 formal actions, 0 of them with a penalty assessed. Federal and state penalties are separate figures from separate authorities and are shown as each was filed, never added together.
Informal enforcement
EPA’s informal enforcement file holds no action for NPDES VAR10U084.
Cited to the EPA ICIS-NPDES violation, inspection and enforcement files (ECHO download); up to 50 rows of each shown, newest first.
Watch this permit
One permit holder, $99/month. Watch the register for one permit holder and the places and receiving waters tied to its permits. Choose “One permit holder” and enter this permit’s NPDES ID, VAR10U084.
Start the watch
- One permit holder — $99/month
- One watershed — $2,990/year
- One state — $4,990/year
- The whole register — $18,000/year
How we handle your data → Privacy
EPA publishes a free Detailed Facility Report for every permit on ECHO: its compliance status quarter by quarter, its inspections, and its enforcement actions and penalties. EPA also sends free notices of new inspections and enforcement actions through ECHO Notify; enter NPDES ID VAR10U084 there.
UNITY TUNSTALL 230 KV LINES PHASE 2, Mecklenburg, Virginia: Coverage under a general permit VAR10U084, held by Virginia Electric and Power Co dba Dominion Energy; Construction stormwater; Effective; issued July 1, 2024, term to June 30, 2029, by VA DEQ; discharges to Meherrin River-Taylors Creek.
- June 16, 2026: Evaluation (S).
Virginia holds 6,257 Construction stormwater coverages of this permit type in EPA’s file; 3,403 were issued before VAR10U084. Virginia Electric and Power Co dba Dominion Energy holds 26 permits in Virginia.
Other permits held by Virginia Electric and Power Co dba Dominion Energy
- MAIN POINT SUBSTATION FINAL SITE AND GRADING PLAN, Fort Lee: VAR10N325, issued 2019-07-01
- FORT POWHATAN SOLAR PHASE I AND PHASE II, Disputanta: VAR10N521, issued 2019-07-01
- MOUNT STORM TO VALLEY 500 KV ELECTRICAL TRANSMISSI, Harrisonburg: VAR10N687, issued 2019-07-01
- POSSUM POINT POWER STATION PONDS ABC AND E CLOSURE, Dumfries: VAR10O106, issued 2019-07-01
- DINWIDDIE CAMPUS MOBILE SUBSTATION AND LAB, N. Dinwiddie: VAR10O898, issued 2019-07-01
- TYSONS SUBSTATION UPGRADE, Vienna: VAR10O956, issued 2019-07-01
- BOOKERS MILL SOLAR PART 1, Farnham: VAR10P897, issued 2019-07-01
- RENAISSANCE TECH PARK BRIDGING, Herndon: VAR10S394, issued 2019-07-01
- BLUE RIDGE SOLAR PART 1, Tight Squeeze: VAR10S443, issued 2019-07-01
- HARPERS SWITCHING STATION, Virginia Beach: VAR10S806, issued 2019-07-01
Coverages issued nearest VAR10U084
- 2024-07-01: FOXCROFT SCHOOL-STEAM BUILDING & SITE IMPROVEMENTS, Middleburg: VAR10U066, held by Coakley & Williams Construction of MD, LLC
- 2024-07-01: GARY BAUSERMAN DUPLEX - 305 & 307 WILLOW OAKS DRIV, Elkton: VAR10U068, held by Gary Bauserman
- 2024-07-01: WAWA ENTRANCE PLAN, Ruckersville: VAR10U069, held by Route 33 Holdings LLC
- 2024-07-01: LIBERTY UNIVERSITY GREEN HALL PARKING IMPROVEMENTS, Lynchburg: VAR10U077, held by Liberty University, Inc.
- 2024-07-01: DULLES 28 TECHNOLOGY PARK, Sterling: VAR10U081, held by Long Drive Land Company LLC
- 2024-07-01: HARPERS MILL SOUTHEAST, SECTION 10, Chesterfield: VAR10U085, held by U.S. Home, LLC
- 2024-07-01: MCCAULEY PARK CARRIAGE HOMES, Aylett: VAR10U096, held by Rogers-Chenault, Inc.
- 2024-07-01: KIRA HEIGHTS, Waynesboro: VAR10U103, held by D.R. Horton, Inc.
- 2024-07-01: GRETNA 2 SOLAR PROJECT, Gretna: VAR10U112, held by Gretna II Solar LLC
- 2024-07-01: GATORADE BLUE RIDGE ADDITION, Wytheville: VAR10U123, held by CHA Tech Services LLC dba CTS Builders
UNITY TUNSTALL 230 KV LINES PHASE 2 among its neighbors
3 discharge permits are in the Stony Creek-Meherrin River subwatershed (HUC 030102040401); VAR10U084 is one.
Other permits in the Stony Creek-Meherrin River subwatershed (HUC 030102040401)
- RACETRAC SOUTH HILL PROJECT #1730, South Hill: VAR10W016, minor, term to 2029-06-30
- VSU HEALTH COMMUNITY MEMORIAL HOSPITAL, South Hill: VAR10W237, minor, term to 2029-06-30
Nearby on the register
- Discharge permits in Mecklenburg
- Every permit record in Mecklenburg, A to Z
- Discharge permits in Virginia
- Every permit record in Virginia, A to Z
Figures from EPA’s ICIS-NPDES download, loaded September 15, 2026.
What this page shows
UNITY TUNSTALL 230 KV LINES PHASE 2 is linked to 3 NPDES permits in the Stony Creek-Meherrin River subwatershed, including this permit. Permits issued earlier than this permit make up 37.5% of the 16 storm water construction permits in Mecklenburg.