NPDES VAR10V102 · Clean Water Act
LOVETT 64 COMMERCE CENTER PHASE 1 ON-SITE PLANS, Williamsburg, VA: NPDES VAR10V102 discharge permit, effluent exceedances, inspections, penalties
LOVETT 64 COMMERCE CENTER PHASE 1 ON-SITE PLANS, Williamsburg, Virginia: General permit coverage VAR10V102, held by Brinkmann Constructors; Construction stormwater; Effective; issued July 1, 2024, term to June 30, 2029, by VA DEQ; discharges to Diascund Creek-Mill Creek.
- June 29, 2026: Evaluation (S).
Virginia holds 6,257 Construction stormwater coverages of this permit type in EPA’s file; 3,403 were issued before VAR10V102.
Coverages issued nearest VAR10V102
- 2024-07-01: CITIZENS BANK PARKING EXPANSION, Glen Allen: VAR10V094, held by Fortune-Johnson LLC
- 2024-07-01: SAMPSON CREEK ROAD, Chesapeake: VAR10V095, held by MKS Land Development, LLC
- 2024-07-01: TRANQUILITY AT THE LAKES PHASE II, Virginia Beach: VAR10V096, held by Hoy Construction, Inc.
- 2024-07-01: MEADOW SPRINGS RUN SUBDIVISION, Henrico: VAR10V098, held by Meadow Development LLC
- 2024-07-01: ROUTE 9 / ROUTE 287 ROUNDABOUT, Purcellville: VAR10V101, held by General Excavation, Inc.
- 2024-07-01: MONTGOMERY RIDGE PHASE 4, Charlottesville: VAR10V104, held by Powell Ridge Partners LLC
- 2024-07-01: BALCONY FALLS BUENA VISTA 115KV REBUILD PROJECT LI, Rockbridge: VAR10V105, held by Virginia Electric and Power Co dba Dominion Energy
- 2024-07-01: CHUS PHAT SON BUDDHA MOUNTAIN CENTER, Roanoke: VAR10V106, held by Chua Phat Son Buddha Mountain Center
- 2024-07-01: HOOVER RIDGE PARK FINAL SITE PLAN, Madison: VAR10V108, held by William W. Walls Excavating Inc
- 2024-07-01: OLD GREENVILLE POULTRY HOUSES, Stuarts Draft: VAR10V109, held by Jacob Leonard
LOVETT 64 COMMERCE CENTER PHASE 1 ON-SITE PLANS among its neighbors
11 discharge permits are in the Mill Creek-Diascund Creek subwatershed (HUC 020802060603); VAR10V102 is one.
Other permits in the Mill Creek-Diascund Creek subwatershed (HUC 020802060603)
- 8189 RICHMOND ROAD WAREHOUSE, Toano: VAR10Q769, minor, term to 2024-06-30
- 8251 RICHMOND RD - HERTZLER & GEORGE, Williamsburg: VAR10Q851, minor, term to 2024-06-30
- CHRIST COMMUNITY CHURCH MULTI-PURPOSE BUILDING, Toano: VAR10P536, minor, term to 2024-06-30
- CROSSROAD CUSTOM BUILDERS, Lanexa: VAR10V218, minor, term to 2029-06-30
- JAMES CITY COUNTY RECYCLING, Toano: VAR051899, minor, term to 2024-06-30
- LANEXA SUBSTATION EXPANSION, New Kent: VAR10Q529, minor, term to 2024-06-30
- MCSHERRY AND FOX RESIDENCES, Lanexa: VAG403004, minor, term to 2026-07-31
- RACEFIELD SOLAR, Toano: VAR10V486, minor, term to 2029-06-30
- RICHMOND ROAD SOLAR PROJECT, Toano: VAR10X039, minor, term to 2029-06-30
- THACKER RESIDENCE, Lanexa: VAG403104, minor, term to 2026-07-31
What stands out
- Its term runs 4 years and 364 days, July 1, 2024 to June 30, 2029.
- Its newest dated event on file is an inspection on June 29, 2026, 78 days before EPA's file was loaded.
- In the 365 days to September 15, 2026, it was dated 1 inspection.
- EPA's file dates 1 event for it, all in 2026.
- It is one of 13,137 discharge permits on the register in Virginia; 6,257 of them (48%) are in its program, Construction stormwater, and it is a minor discharger.
Identity
| Facility | LOVETT 64 COMMERCE CENTER PHASE 1 ON-SITE PLANS |
|---|---|
| Permittee | Brinkmann Constructors |
| NPDES ID | VAR10V102 |
| Status | Effective |
| Type | General permit coverage |
| Class | Minor |
| Facility type | Non-POTW |
| Program | Construction stormwater |
| Issued | July 1, 2024 |
| Expires | June 30, 2029 |
| Agency | VA DEQ |
| Address | Williamsburg, VA 23185 |
| Receiving water | Diascund Creek-Mill Creek |
| Subwatershed | Mill Creek-Diascund Creek (HUC 020802060603) |
NPDES VAR10V102: effluent limits and exceedances
LOVETT 64 COMMERCE CENTER PHASE 1 ON-SITE PLANS (NPDES VAR10V102): 0 pollutants on file, 0 limited; 0 with a violation of any kind, 0 with an exceedance.
NPDES VAR10V102: no pollutant row on file.
NPDES VAR10V102: inspections, violations and enforcement
NPDES VAR10V102: 1 inspection
| Date | What EPA recorded | Agency |
|---|---|---|
| June 29, 2026 | Evaluation | S |
NPDES VAR10V102 (LOVETT 64 COMMERCE CENTER PHASE 1 ON-SITE PLANS): no single-event violation, formal enforcement action and informal enforcement action on file.
Watch NPDES VAR10V102
NPDES VAR10V102: one email when its EPA record changes — $99/month.
Permits near NPDES VAR10V102
NPDES VAR10V102: 0 pollutant rows, 1 dated events; ICIS-NPDES download, loaded September 15, 2026.