NPDES VAR10V498 · Clean Water Act
COURTHOUSE WEST INFRASTRUCTURE PLAN, Stafford, VA: NPDES VAR10V498 discharge permit, effluent exceedances, inspections, penalties
COURTHOUSE WEST INFRASTRUCTURE PLAN, Stafford, Virginia: General permit coverage VAR10V498, held by Norton Scott LLC; Construction stormwater; Effective; issued July 1, 2024, term to June 30, 2029, by VA DEQ; discharges to Accokeek Creek.
- October 14, 2026: Evaluation (S).
- August 28, 2026: Evaluation (S).
- April 23, 2026: Evaluation (S).
- March 13, 2026: Evaluation (S).
Virginia holds 6,257 Construction stormwater coverages of this permit type in EPA’s file; 3,403 were issued before VAR10V498. Norton Scott LLC holds 2 permits in Virginia.
Other permits held by Norton Scott LLC
- COURTHOUSE WEST SITE PLAN, Stafford: VAR10X182, issued 2024-07-01
Coverages issued nearest VAR10V498
- 2024-07-01: JLMA-EAST WATERMAIN AND SANITARY SEWER, Leesburg: VAR10V492, held by DMM Tuscarora LLC
- 2024-07-01: VIRGINIA PHYSICIANS FOR WOMEN-CENTER POINTE OFFICE, Midlothian: VAR10V493, held by Loughridge & Company LLC
- 2024-07-01: ACCESSIBLE PLAYGROUNDS AT FORT BELVOIR SOUTH BLDG, Ft. Belvoir: VAR10V494, held by Lifecycle Construction Services LLC
- 2024-07-01: RIO SUAREZ FOODS, Hopewell: VAR10V496, held by Haley Builders
- 2024-07-01: WAWA #6636, South Hill: VAR10V497, held by Independence Construction Co of VA
- 2024-07-01: BUCHKO SUBDIVISION, Warrenton: VAR10V499, held by Maronda Homes of Virginia LLC
- 2024-07-01: MAPLEWOOD ACCESS ROAD, Chatham: VAR10V500, held by Virginia Electric and Power Co d/b/a Dominion Ener
- 2024-07-01: THE EDGE AT WESTCHESTER SECTIONS 2,3,4, Chesterfield: VAR10V503, held by Westchester Towns Development Company, LLC
- 2024-07-01: VIRGINIA VILLAGE RESIDENTIAL PLAN, Leesburg: VAR10V504, held by CATOCTIN WALK LLC
- 2024-07-01: PAGE AUDI CONNECTOR ROAD, Henrico: VAR10V505, held by Page Auto
COURTHOUSE WEST INFRASTRUCTURE PLAN among its neighbors
31 discharge permits are in the Accokeek Creek subwatershed (HUC 020700110204); VAR10V498 is one.
Other permits in the Accokeek Creek subwatershed (HUC 020700110204)
- AUSTIN RIDGE LOGISTICS CENTER, Stafford: VAR10T747, minor, term to 2024-06-30
- AYALA FRANCISCO RESIDENCE, Stafford: VAG406207, minor, term to 2026-07-31
- BIG SPRING ESTATES SECTION 1, Stafford: VAR10O135, minor, term to 2024-06-30
- BIG SPRING ESTATES SECTION 2, Stafford: VAR10Q154, minor, term to 2024-06-30
- BIG SPRING MANOR, Stafford: VAR10U530, minor, term to 2029-06-30
- BIG SPRING OFFICE BUILDING AKA ESKIMO HILL WAREHOU, Stafford: VAR10Q651, minor, term to 2024-06-30
- BIG SPRINGS BUILDING, Stafford: VAR10W993, minor, term to 2029-06-30
- BURNS CORNER MAJOR GRADING PLAN, Stafford: VAR10O556, minor, term to 2024-06-30
- BURNS CORNER WENDY'S, Stafford: VAR10S491, minor, term to 2024-06-30
- CENTRAL STAFFORD COMMERCE CENTER GDC CONTRACTORS S, Stafford: VAR10W535, minor, term to 2029-06-30
What stands out
- Its term runs 4 years and 364 days, July 1, 2024 to June 30, 2029.
- Its newest dated event on file is an inspection on October 14, 2026, 0 days before EPA's file was loaded.
- In the 365 days to October 14, 2026, it was dated 4 inspections.
- EPA's file dates 4 events for it, all in 2026.
- It is one of 13,137 discharge permits on the register in Virginia; 6,257 of them (48%) are in its program, Construction stormwater, and it is a minor discharger.
Identity
| Facility | COURTHOUSE WEST INFRASTRUCTURE PLAN |
|---|---|
| Permittee | Norton Scott LLC |
| NPDES ID | VAR10V498 |
| Status | Effective |
| Type | General permit coverage |
| Class | Minor |
| Facility type | Non-POTW |
| Program | Construction stormwater |
| Issued | July 1, 2024 |
| Expires | June 30, 2029 |
| Agency | VA DEQ |
| Address | Stafford, VA 22554 |
| Receiving water | Accokeek Creek |
| Subwatershed | Accokeek Creek (HUC 020700110204) |
NPDES VAR10V498: effluent limits and exceedances
COURTHOUSE WEST INFRASTRUCTURE PLAN (NPDES VAR10V498): 0 pollutants on file, 0 limited; 0 with a violation of any kind, 0 with an exceedance.
NPDES VAR10V498: no pollutant row on file.
NPDES VAR10V498: inspections, violations and enforcement
NPDES VAR10V498: 4 inspections
| Date | What EPA recorded | Agency |
|---|---|---|
| October 14, 2026 | Evaluation | S |
| August 28, 2026 | Evaluation | S |
| April 23, 2026 | Evaluation | S |
| March 13, 2026 | Evaluation | S |
NPDES VAR10V498 (COURTHOUSE WEST INFRASTRUCTURE PLAN): no single-event violation, formal enforcement action and informal enforcement action on file.
Watch NPDES VAR10V498
NPDES VAR10V498: one email when its EPA record changes — $99/month.
Permits near NPDES VAR10V498
NPDES VAR10V498: 0 pollutant rows, 4 dated events; ICIS-NPDES download, loaded October 14, 2026.