NPDES VAR10V670 · Clean Water Act
CLOVER – BUTLER 230 KV LINE PHASE 1, Charlotte And Halifax Counties, VA: NPDES VAR10V670 discharge permit, effluent exceedances, inspections, penalties
CLOVER – BUTLER 230 KV LINE PHASE 1, Charlotte And Halifax Counties, Virginia: General permit coverage VAR10V670, held by Virginia Electric and Power Company d/b/a Dominion; Construction stormwater; Effective; issued July 1, 2024, term to June 30, 2029, by VA DEQ; discharges to Roanoke River-John H Kerr Reservoir-Buffalo Creek.
- April 7, 2026: Evaluation (S).
Virginia holds 6,257 Construction stormwater coverages of this permit type in EPA’s file; 3,403 were issued before VAR10V670. Virginia Electric and Power Company d/b/a Dominion holds 33 permits in Virginia.
Other permits held by Virginia Electric and Power Company d/b/a Dominion
- BOOKERS MILL SOLAR - PART 2, Farnham: VAR10Q451, issued 2019-07-01
- SWEET SUE SOLAR, Aylett: VAR10Q543, issued 2019-07-01
- MOUNT STORM TO VALLEY 500 KV TRANSMISSION LINE 550, Fulks Run: VAR10R202, issued 2019-07-01
- FOUNTAIN CREEK SOLAR - PART I, Emporia: VAR10R239, issued 2019-07-01
- FOUNTAIN CREEK SOLAR - PART II, Emporia: VAR10R240, issued 2019-07-01
- NORGE SOLAR ELECTRIC POWER PLANT, Williamsburg: VAR10R411, issued 2019-07-01
- WISHING STAR SUBSTATION, Loudoun: VAR10S325, issued 2019-07-01
- NORTH RIDGE SOLAR, Powhatan: VAR10S945, issued 2019-07-01
- LINE 568 STRUCTURE RELOCATIONS, Prince William County: VAR10U377, issued 2024-07-01
- LINE #183 PARTIAL REBUILD BRISTERS TO JOPLIN ROAD, Bealeton: VAR10U435, issued 2024-07-01
Coverages issued nearest VAR10V670
- 2024-07-01: JARRATT ENERGY FACILITY, Jarratt: VAR10V664, held by Jarratt Energy Facility, LLC
- 2024-07-01: VPCC WORKFORCE DEVELOPMENT CENTER, Newport News: VAR10V666, held by W. M. Jordan Company, L.C.
- 2024-07-01: CWF NURSERY IMPROVEMENTS, Williamsburg: VAR10V667, held by Henderson, Inc.
- 2024-07-01: CHESTERBROOK RD WALKWAY, MADDUX LN TO 41ST, Mclean: VAR10V668, held by M&F CONCRETE INC
- 2024-07-01: THE FLATS AT MAYLAND, Henrico: VAR10V669, held by Bradyminster Properties, LLC
- 2024-07-01: GRADING AND ESC PLAN FOR PARCELS 80-(A)-44,80-(A)-, Christiansburg: VAR10V673, held by SHAH DEVELOPMENT LLC
- 2024-07-01: MOUNTAIN VIEW SECTION PART 3 SHENANDOAH FARMS, Warren: VAR10V675, held by Knowles Construction LLC
- 2024-07-01: EXTENDED STAY AMERICA - VINTON, Vinton: VAR10V676, held by KARA Roanoke, LLC
- 2024-07-01: VA MTR#2 TO VANTAGE (320 CIRCUIT), Dulles: VAR10V677, held by Virginia Electric and Power Company dba Dominion E
- 2024-07-01: SAM'S XPRESS CAR WASH, Virginia Beach: VAR10V678, held by Sam's Xpress Car Wash, LLC
CLOVER – BUTLER 230 KV LINE PHASE 1 among its neighbors
15 discharge permits are in the Sandy Creek-Roanoke River subwatershed (HUC 030101020601); VAR10V670 is one.
Other permits in the Sandy Creek-Roanoke River subwatershed (HUC 030101020601)
- CLOVER CREEK SOLAR, Scottsburg: VAR10U364, minor, term to 2029-06-30
- CLOVER POWER STATION-MUD MOUNTAIN STOCKPILE PROJEC, Clover: VAR10U709, minor, term to 2029-06-30
- CLOVER WWTP, Clover: VA0073733, minor, term to 2021-12-31
- CONSTRUCTION TRAILER PARKING AND ACCESS ROAD, Saxe: VAR10W063, minor, term to 2029-06-30
- COVINGTON MATTHEW AND ANNA MURRAY RESIDENCE, Wyliesburg: VAG407357, minor, term to 2026-07-31
- LINE #235 230 KV REBUILD FROM CLOVER SUBSTATION TO, Halifax: VAR10V241, minor, term to 2029-06-30
- MORGAN LUMBER COMPANY INC, Red Oak: VAR051165, minor, term to 2024-06-30
- MORGAN LUMBER FACILITY EXPANSION, Red Oak: VAR10S820, minor, term to 2024-06-30
- REGIONAL SOLAR OFF-SITE LAYDOWN SUPPORT, Scottsburg: VAR10W547, minor, term to 2029-06-30
- ROE PARENT RESIDENCE, Wylesburg: VAG407304, minor, term to 2026-07-31
What stands out
- Its term runs 4 years and 364 days, July 1, 2024 to June 30, 2029.
- Its newest dated event on file is an inspection on April 7, 2026, 161 days before EPA's file was loaded.
- In the 365 days to September 15, 2026, it was dated 1 inspection.
- EPA's file dates 1 event for it, all in 2026.
- It is one of 13,137 discharge permits on the register in Virginia; 6,257 of them (48%) are in its program, Construction stormwater, and it is a minor discharger.
Identity
| Facility | CLOVER – BUTLER 230 KV LINE PHASE 1 |
|---|---|
| Permittee | Virginia Electric and Power Company d/b/a Dominion |
| NPDES ID | VAR10V670 |
| Status | Effective |
| Type | General permit coverage |
| Class | Minor |
| Facility type | Non-POTW |
| Program | Construction stormwater |
| Issued | July 1, 2024 |
| Expires | June 30, 2029 |
| Agency | VA DEQ |
| Address | Charlotte And Halifax Counties, VA 23923 |
| Receiving water | Roanoke River-John H Kerr Reservoir-Buffalo Creek |
| Subwatershed | Sandy Creek-Roanoke River (HUC 030101020601) |
NPDES VAR10V670: effluent limits and exceedances
CLOVER – BUTLER 230 KV LINE PHASE 1 (NPDES VAR10V670): 0 pollutants on file, 0 limited; 0 with a violation of any kind, 0 with an exceedance.
NPDES VAR10V670: no pollutant row on file.
NPDES VAR10V670: inspections, violations and enforcement
NPDES VAR10V670: 1 inspection
| Date | What EPA recorded | Agency |
|---|---|---|
| April 7, 2026 | Evaluation | S |
NPDES VAR10V670 (CLOVER – BUTLER 230 KV LINE PHASE 1): no single-event violation, formal enforcement action and informal enforcement action on file.
Watch NPDES VAR10V670
NPDES VAR10V670: one email when its EPA record changes — $99/month.
Permits near NPDES VAR10V670
NPDES VAR10V670: 0 pollutant rows, 1 dated events; ICIS-NPDES download, loaded September 15, 2026.