NPDES WAR003120 · Clean Water Act
GARY MERLINO CONSTRUCTION OFFICE BD, Seattle, WA: NPDES WAR003120 discharge permit, effluent exceedances, inspections, penalties
GARY MERLINO CONSTRUCTION OFFICE BD, Seattle, Washington: General permit coverage WAR003120, held by Gary Merlino Construction; Administratively continued; issued November 20, 2019, term to December 31, 2024, by State.
- Turbidity: 2 limits, 21 violations of any kind, 11 effluent exceedances, latest December 31, 2023.
- Zinc, total [as Zn]: 2 limits, 20 violations of any kind, 10 effluent exceedances, latest September 30, 2024, largest 71% over the limit.
- Solids, total suspended: 2 limits, 23 violations of any kind, 7 effluent exceedances, latest September 30, 2024, largest 190% over the limit.
- Copper, total [as Cu]: 2 limits, 14 violations of any kind, 4 effluent exceedances, latest September 30, 2016, largest 106% over the limit.
- pH: 4 limits, 20 violations of any kind.
- Oil and grease visual: 2 limits, 10 violations of any kind.
- April 28, 2026: Follow-Up (S).
GARY MERLINO CONSTRUCTION OFFICE BD among its neighbors
362 discharge permits are in the Green River subwatershed (HUC 171100130305); WAR003120 is one. Its county: 1,319, 8 major; WAR003120 is minor permit.
Other permits in the Green River subwatershed (HUC 171100130305)
- 116TH AVENUE SE AND SE 248TH STREET ROUNDABOUT, Kent: WAR316076, minor, term to 2030-12-31
- 37TH & 40TH AVE SIDEWALK PROJECT, Seatac: WAR303423, minor, term to 2015-12-31
- 5TH AVENUE TOWNHOMES, Kent: WAR303021, minor, term to 2015-12-31
- 7 ELEVEN WEST VALLEY HWY, Tukwila: WAR313558, minor, term to 2025-12-31
- 76TH AVE S ROAD RAISING, Kent: WAR309038, minor, term to 2025-12-31
- 8801 E MARGINAL WAY S, Tukwila: WAR008681, minor, term to 2014-12-31
- ABF FREIGHT SYSTEMS KENT, Kent: WAR313014, minor, term to 2024-12-31
- ABX AIR INC SEATTLE, Seattle: WAR004602, minor, term to 2014-12-31
- ACE GALVANIZING INC 96TH, Seattle: WAR000154, minor, term to 2024-12-31
- AIRGAS KENT, Kent: WAR312174, minor, term to 2025-12-31
What stands out
- Its term runs 5 years and 41 days, November 20, 2019 to December 31, 2024; the term ended 623 days before EPA's file was loaded on September 15, 2026, and the file lists the permit as administratively continued.
- Its newest dated event on file is an inspection on April 28, 2026, 140 days before EPA's file was loaded.
- In the 365 days to September 15, 2026, it was dated 1 inspection.
- EPA's file dates 1 event for it, all in 2026.
- 4 of its 6 pollutants on file have an effluent exceedance (67%); 6 are under a numeric limit; the largest exceedance is Solids, total suspended at 190% over its limit.
- It is one of 8,573 discharge permits on the register in Washington; the file names no program for it, and it is a minor discharger.
Identity
| Facility | GARY MERLINO CONSTRUCTION OFFICE BD |
|---|---|
| Permittee | Gary Merlino Construction |
| NPDES ID | WAR003120 |
| Status | Administratively continued |
| Type | General permit coverage |
| Class | Minor |
| Facility type | Non-POTW |
| Issued | November 20, 2019 |
| Expires | December 31, 2024 |
| Agency | State |
| Address | Seattle, WA 98108 |
| Receiving water impaired | 303(D) Listed |
| Subwatershed | Green River (HUC 171100130305) |
| Other EPA IDs (FRS) | RCRA handler WAD988499125 |
NPDES WAR003120: effluent limits and exceedances
GARY MERLINO CONSTRUCTION OFFICE BD (NPDES WAR003120): 6 pollutants on file, 6 limited; 6 with a violation of any kind, 4 with an exceedance.
| Pollutant | Limits | Violations | Exceedances | Latest | Largest, as filed |
|---|---|---|---|---|---|
| Turbidity | 2 | 21 | 11 | December 31, 2023 | |
| Zinc, total [as Zn] | 2 | 20 | 10 | September 30, 2024 | 71% over the limit |
| Solids, total suspended | 2 | 23 | 7 | September 30, 2024 | 190% over the limit |
| Copper, total [as Cu] | 2 | 14 | 4 | September 30, 2016 | 106% over the limit |
| pH | 4 | 20 | 0 | ||
| Oil and grease visual | 2 | 10 | 0 |
NPDES WAR003120: inspections, violations and enforcement
NPDES WAR003120: 1 inspection
| Date | What EPA recorded | Agency |
|---|---|---|
| April 28, 2026 | Follow-Up | S |
NPDES WAR003120 (GARY MERLINO CONSTRUCTION OFFICE BD): no single-event violation, formal enforcement action and informal enforcement action on file.
Watch NPDES WAR003120
NPDES WAR003120: one email when its EPA record changes — $99/month.
Permits near NPDES WAR003120
NPDES WAR003120: 6 pollutant rows, 1 dated events; ICIS-NPDES download, loaded September 15, 2026.