Clean Water Act discharge permit · NPDES WAR308607

I-405 RENTON TO BELLEVUE ETL PROJECT, Renton, WA: NPDES WAR308607 discharge permit, effluent exceedances, inspections, penalties

I-405 RENTON TO BELLEVUE ETL PROJECT, held by FlatironDragados-Lane a Join Venture, holds NPDES permit WAR308607. EPA’s file records it issued November 18, 2020 and expiring December 31, 2025. The status and dates are as EPA’s permit file stood when Velarion loaded it (September 15, 2026); EPA’s free Detailed Facility Report on ECHO carries the permit’s current standing.

What stands out

  • Its term runs 5 years and 43 days, November 18, 2020 to December 31, 2025; the term ended 258 days before EPA's file was loaded on September 15, 2026, and the file lists the permit as administratively continued.
  • Its newest dated event on file is an inspection on October 21, 2026.
  • In the 365 days to September 15, 2026, it was dated 1 inspection, 1 formal enforcement action, 1 informal enforcement action.
  • EPA's file dates 4 events for it, all in 2026.
  • 2 of its 41 pollutants on file have an effluent exceedance (4.9%); 41 are under a numeric limit.
  • It is one of 8,573 discharge permits on the register in Washington; 4,744 of them (55%) are in its program, Construction stormwater, and it is a minor discharger.

Identity

Facility as filedI-405 RENTON TO BELLEVUE ETL PROJECT
Permittee as filedFlatironDragados-Lane a Join Venture
NPDES IDWAR308607
Permit statusAdministratively continued (past its expiration date and still in force until reissued)
Permit typeCoverage under a general permit
Discharger classMinor discharger
Facility typeNot a publicly owned treatment works
ProgramConstruction stormwater
IssuedNovember 18, 2020
Expiration dateDecember 31, 2025
Issuing agencyState
AddressRenton, WA 98055
Receiving water impaired303(D) Listed
SubwatershedMadsen Creek-Cedar River (HUC 171100120106)

Cited to the EPA ICIS-NPDES permit file (ECHO download).

Effluent limits and exceedances

An effluent exceedance is a discharge monitoring report value over the permit’s numeric limit (EPA’s violation code E90). A violation of any kind also counts a report not filed. Each row is EPA’s own count for that pollutant.

Pollutant or measureLimitsViolations, any kindEffluent exceedancesLatest exceedanceLargest exceedance, as filed
Turbidity47151123June 30, 2026
pH94593January 31, 2024
Total Petroleum Hydrocarbons - Gasoline2170
Arsenic, total [as As]220
Cadmium, total [as Cd]220
Chromium, total [as Cr]220
Copper, total [as Cu]220
Lead, total [as Pb]220
Acenaphthylene220
Acenaphthene220
Anthracene220
Benzo[b]fluoranthene220
Benzo[k]fluoranthene220
Benzo[a]pyrene220
Chrysene220
Fluoranthene220
Fluorene220
Indeno[1,2,3-cd]pyrene220
Phenanthrene220
Pyrene220
Tetrachloroethylene220
1,1-Dichloroethane220
Benzo[ghi]perylene220
Benzo[a]anthracene220
Dibenz[a,h]anthracene220
Naphthalene220
Vinyl chloride220
Total Petroleum Hydrocarbons - Diesel220
Carbon disulfide220
1,2,4-Trimethylbenzene220
Isopropylbenzene220
n-Propylbenzene220
1,3,5-Trimethylbenzene220
n-Butylbenzene220
2-Methylnaphthalene220
1-Methylnaphthalene220
Benzo[j]fluoranthene220
Trichloroethene220
Acetone220
Methyl ethyl ketone220
cis-1,2-Dichloroethene220

Cited to the EPA ICIS-NPDES limits and effluent violations files (ECHO download); up to 60 rows shown, most exceedances first.

Inspections, violations and enforcement

EPA’s single-event violation file, as loaded, holds no violation for NPDES WAR308607.

Inspections

DateWhat EPA recordedAgency
October 21, 2026EvaluationS
March 6, 2026EvaluationS

Formal enforcement and penalties

1 formal actions, 0 of them with a penalty assessed. Federal and state penalties are separate figures from separate authorities and are shown as each was filed, never added together.

DateWhat EPA recordedAgencyFederal penaltyState or local penalty
March 11, 2026State CWA Non Penalty AOState

Informal enforcement

DateWhat EPA recordedAgency
April 16, 2026Notice of ViolationState

Cited to the EPA ICIS-NPDES violation, inspection and enforcement files (ECHO download); up to 50 rows of each shown, newest first.

Watch this permit

One permit holder, $99/month. Watch the register for one permit holder and the places and receiving waters tied to its permits. Choose “One permit holder” and enter this permit’s NPDES ID, WAR308607.

Start the watch

How often?
  • One permit holder — $99/month
  • One watershed — $2,990/year
  • One state — $4,990/year
  • The whole register — $18,000/year

How we handle your data → Privacy

EPA publishes a free Detailed Facility Report for every permit on ECHO: its compliance status quarter by quarter, its inspections, and its enforcement actions and penalties. EPA also sends free notices of new inspections and enforcement actions through ECHO Notify; enter NPDES ID WAR308607 there.

I-405 RENTON TO BELLEVUE ETL PROJECT, Renton, Washington: Coverage under a general permit WAR308607, held by FlatironDragados-Lane a Join Venture; Construction stormwater; Administratively continued (past its expiration date and still in force until reissued); issued November 18, 2020, term to December 31, 2025, by State.

  • Turbidity: 47 limits, 151 violations of any kind, 123 effluent exceedances, latest June 30, 2026.
  • pH: 94 limits, 59 violations of any kind, 3 effluent exceedances, latest January 31, 2024.
  • Total Petroleum Hydrocarbons - Gasoline: 2 limits, 17 violations of any kind.
  • Arsenic, total [as As]: 2 limits, 2 violations of any kind.
  • Cadmium, total [as Cd]: 2 limits, 2 violations of any kind.
  • Chromium, total [as Cr]: 2 limits, 2 violations of any kind.
  • Copper, total [as Cu]: 2 limits, 2 violations of any kind.
  • Lead, total [as Pb]: 2 limits, 2 violations of any kind.
  • Acenaphthylene: 2 limits, 2 violations of any kind.
  • Acenaphthene: 2 limits, 2 violations of any kind.
  • Anthracene: 2 limits, 2 violations of any kind.
  • Benzo[b]fluoranthene: 2 limits, 2 violations of any kind.
  • Benzo[k]fluoranthene: 2 limits, 2 violations of any kind.
  • Benzo[a]pyrene: 2 limits, 2 violations of any kind.
  • Chrysene: 2 limits, 2 violations of any kind.
  • Fluoranthene: 2 limits, 2 violations of any kind.
  • Fluorene: 2 limits, 2 violations of any kind.
  • Indeno[1,2,3-cd]pyrene: 2 limits, 2 violations of any kind.
  • Phenanthrene: 2 limits, 2 violations of any kind.
  • Pyrene: 2 limits, 2 violations of any kind.
  • Tetrachloroethylene: 2 limits, 2 violations of any kind.
  • 1,1-Dichloroethane: 2 limits, 2 violations of any kind.
  • Benzo[ghi]perylene: 2 limits, 2 violations of any kind.
  • Benzo[a]anthracene: 2 limits, 2 violations of any kind.
  • Dibenz[a,h]anthracene: 2 limits, 2 violations of any kind.
  • Naphthalene: 2 limits, 2 violations of any kind.
  • Vinyl chloride: 2 limits, 2 violations of any kind.
  • Total Petroleum Hydrocarbons - Diesel: 2 limits, 2 violations of any kind.
  • Carbon disulfide: 2 limits, 2 violations of any kind.
  • 1,2,4-Trimethylbenzene: 2 limits, 2 violations of any kind.
  • Isopropylbenzene: 2 limits, 2 violations of any kind.
  • n-Propylbenzene: 2 limits, 2 violations of any kind.
  • 1,3,5-Trimethylbenzene: 2 limits, 2 violations of any kind.
  • n-Butylbenzene: 2 limits, 2 violations of any kind.
  • 2-Methylnaphthalene: 2 limits, 2 violations of any kind.
  • 1-Methylnaphthalene: 2 limits, 2 violations of any kind.
  • Benzo[j]fluoranthene: 2 limits, 2 violations of any kind.
  • Trichloroethene: 2 limits, 2 violations of any kind.
  • Acetone: 2 limits, 2 violations of any kind.
  • Methyl ethyl ketone: 2 limits, 2 violations of any kind.
  • cis-1,2-Dichloroethene: 2 limits, 2 violations of any kind.
  • October 21, 2026: Evaluation (S).
  • April 16, 2026: Notice of Violation (State).
  • March 11, 2026: State CWA Non Penalty AO (State).
  • March 6, 2026: Evaluation (S).

Washington holds 4,744 Construction stormwater coverages of this permit type in EPA’s file; 1,658 were issued before WAR308607.

Coverages issued nearest WAR308607

I-405 RENTON TO BELLEVUE ETL PROJECT among its neighbors

45 discharge permits are in the Madsen Creek-Cedar River subwatershed (HUC 171100120106); WAR308607 is one.

Other permits in the Madsen Creek-Cedar River subwatershed (HUC 171100120106)

Nearby on the register

Figures from EPA’s ICIS-NPDES download, loaded September 15, 2026.

What this page shows

This public-records page covers Clean Water Act NPDES permit WAR308607 for the I-405 RENTON TO BELLEVUE ETL PROJECT in Renton, WA, held by FlatironDragados-Lane a Join Venture, which EPA's file shows as administratively continued after its December 31, 2025 expiration. The page lists a Minor Discharger class of 41, with 2 pollutants under a numeric limit and 2 pollutants with an effluent exceedance, as recorded when Velarion loaded the file on September 15, 2026.