MILLER CREEK STREAM RESTORATION PROJECT, Burien And Seatac, WA: NPDES WAR312312 discharge permit, effluent exceedances, inspections, penalties
MILLER CREEK STREAM RESTORATION PROJECT, Burien And Seatac, Washington: General permit coverage WAR312312, held by Olson Brothers Excavating, Inc.; Construction stormwater; Administratively continued; issued November 18, 2020, term to December 31, 2025, by State.
- pH: 2 limits, 14 violations of any kind.
- Turbidity: 1 limit, 7 violations of any kind.
- Transparency: 1 limit, 7 violations of any kind.
- August 10, 2026: Reconnaissance without Sampling (S).
Washington holds 4,744 Construction stormwater coverages of this permit type in EPA’s file; 1,658 were issued before WAR312312. Olson Brothers Excavating, Inc. holds 3 permits in Washington.
Other permits held by Olson Brothers Excavating, Inc.
- PRAIRIE LINE TRAIL - PHASE 2, Tacoma: WAR313202, issued 2020-11-18
- FORT DENT PARK, Tukwila: WAR315705, issued 2025-11-19
Coverages issued nearest WAR312312
- 2020-11-18: NACHES RV RESORT, Selah: WAR312288, held by PLSA Engineering & Survey
- 2020-11-18: THE PRESERVE WASHOUGAL, Washougal: WAR312289, held by Preserve QOZB, LLC
- 2020-11-18: FALL CITY II, Fall City: WAR312290, held by Slalom 13 Investments, LLC
- 2020-11-18: EVERGREEN HIGH SCHOOL, Seattle: WAR312298, held by Cornerstone GC
- 2020-11-18: I90 NB VIC TO SNOQUALMIE PASS VIC DECK AND DRAINAGE, North Bend: WAR312299, held by MidMountain Contractors
- 2020-11-18: CARBON TRAILS, Auburn: WAR312313, held by Stowe Investments, LLC
- 2020-11-18: HARMONY VILLAGE AT LYNNWOOD, Lynnwood: WAR312318, held by Cornerstone Homes NW, LLC
- 2020-11-18: ROEDER LIFT STATION, Bellingham: WAR312319, held by IMCO Construction
- 2020-11-18: MINTER CREEK FISH HATCHERY, Gig Harbor: WAR312329, held by Rodarte Construction, Inc.
- 2020-11-18: SENDEROS TOWNHOMES, Kirkland: WAR312331, held by Taylor Morrison Northwest, LLC
MILLER CREEK STREAM RESTORATION PROJECT among its neighbors
107 discharge permits are in the Miller Creek-Frontal East Passage subwatershed (HUC 171100190204); WAR312312 is one.
Other permits in the Miller Creek-Frontal East Passage subwatershed (HUC 171100190204)
- 45TH AVE SW CULVERT REPLACEMENT, Seattle: WAR315511, minor, term to 2030-12-31
- AIRPORT STATION AREA PEDESTRIAN IMPROVEMENT PROJECT, Seatac: WAR315472, minor, term to 2030-12-31
- AMAZON.COM SERVICES LLC BFI8, Seatac: WAR309403, minor, term to 2024-12-31
- ARROW LAKE - LAKE TREATMENT, Unspecified: WAG994391, minor, term to 2026-03-21
- BARNES CREEK TRAIL, Des Moines: WAR315080, minor, term to 2025-12-31
- BOEING SPARES DISTRIBUTION CENTER, Seatac: WAR000225, minor, term to 2024-12-31
- BRACE POINT RECONDUCTOR 2021, Seattle: WAR310800, minor, term to 2025-12-31
- BURIEN CITY, Burien: WAR045509, minor, term to 2024-07-31
- BURIEN MERRILL GARDENS, Burien: WAR302237, minor, term to 2015-12-31
- BURIEN METRO LANDING, Burien: WAR314903, minor, term to 2025-12-31
What stands out
- Its term runs 5 years and 43 days, November 18, 2020 to December 31, 2025; the term ended 287 days before EPA's file was loaded on October 14, 2026, and the file lists the permit as administratively continued.
- Its newest dated event on file is an inspection on August 10, 2026, 65 days before EPA's file was loaded.
- In the 365 days to October 14, 2026, it was dated 1 inspection.
- EPA's file dates 1 event for it, all in 2026.
- It is one of 8,573 discharge permits on the register in Washington; 4,744 of them (55%) are in its program, Construction stormwater, and it is a minor discharger.
Identity
| Facility | MILLER CREEK STREAM RESTORATION PROJECT |
|---|---|
| Permittee | Olson Brothers Excavating, Inc. |
| NPDES ID | WAR312312 |
| Status | Administratively continued |
| Type | General permit coverage |
| Class | Minor |
| Facility type | Non-POTW |
| Program | Construction stormwater |
| Issued | November 18, 2020 |
| Expires | December 31, 2025 |
| Agency | State |
| Address | Burien And Seatac, WA 98168 |
| Subwatershed | Miller Creek-Frontal East Passage (HUC 171100190204) |
| SIC | 1794 – Excavation Work |
NPDES WAR312312: effluent limits and exceedances
MILLER CREEK STREAM RESTORATION PROJECT (NPDES WAR312312): 3 pollutants on file, 3 limited; 3 with a violation of any kind, 0 with an exceedance.
| Pollutant | Limits | Violations | Exceedances | Latest | Largest, as filed |
|---|---|---|---|---|---|
| pH | 2 | 14 | 0 | ||
| Turbidity | 1 | 7 | 0 | ||
| Transparency | 1 | 7 | 0 |
NPDES WAR312312: inspections, violations and enforcement
NPDES WAR312312: 1 inspection
| Date | What EPA recorded | Agency |
|---|---|---|
| August 10, 2026 | Reconnaissance without Sampling | S |
NPDES WAR312312 (MILLER CREEK STREAM RESTORATION PROJECT): no single-event violation, formal enforcement action and informal enforcement action on file.
Watch NPDES WAR312312
NPDES WAR312312: one email when its EPA record changes — $99/month.
Permits near NPDES WAR312312
NPDES WAR312312: 3 pollutant rows, 1 dated events; ICIS-NPDES download, loaded October 14, 2026.