NPDES WAR314162 · Clean Water Act
WOODLAND PUMP STATION AND TEMPORARY FORCE MAIN, Puyallup, WA: NPDES WAR314162 discharge permit, effluent exceedances, inspections, penalties
WOODLAND PUMP STATION AND TEMPORARY FORCE MAIN, Puyallup, Washington: General permit coverage WAR314162, held by Rodarte Construction, Inc.; Construction stormwater; Administratively continued; issued November 18, 2020, term to December 31, 2025, by State.
- pH: 2 limits, 34 violations of any kind.
- Turbidity: 1 limit, 17 violations of any kind.
- Transparency: 1 limit, 11 violations of any kind.
- January 30, 2026: Evaluation (S).
Washington holds 4,744 Construction stormwater coverages of this permit type in EPA’s file; 1,658 were issued before WAR314162. Rodarte Construction, Inc. holds 4 permits in Washington.
Other permits held by Rodarte Construction, Inc.
- MINTER CREEK FISH HATCHERY, Gig Harbor: WAR312329, issued 2020-11-18
- 74TH & WARNER, Tacoma: WAR314274, issued 2020-11-18
- THOMAS EDDY FLOODPLAIN RESTORATION, Snohomish: WAR315197, issued 2025-11-19
Coverages issued nearest WAR314162
- 2020-11-18: LYNDEN ICE PRODUCTION PLANT, Lynden: WAR314157, held by Faber Construction Corporation
- 2020-11-18: MIDWAY MARKET COLBERT, Colbert: WAR314158, held by Kilgore Construction
- 2020-11-18: GRAHAM RANCH PLAT, Gig Harbor: WAR314159, held by Allen Family Trust
- 2020-11-18: VOA-NORTH MULTI-FAMILY, Burlington: WAR314160, held by Dawson Construction LLC
- 2020-11-18: MM RHOTON RD, Yelm: WAR314161, held by MM Rhoton Rd LLC
- 2020-11-18: WARDS LAKE PARK, Lakewood: WAR314163, held by Redside Construction LLC
- 2020-11-18: PORT OF SHELTON SANDERSON FIELD BUILDING REPLACEMENT, Shelton: WAR314164, held by Port of Shelton
- 2020-11-18: TEHALEH PHASES 3 AND 4, Bonney Lake: WAR314166, held by Holt Holdings, WA LLC
- 2020-11-18: US 101 SR 116 NORTH OLYMPIC PENINSULA REMOVE FISH BARRIER ENNIS CREEK, Port Angeles: WAR314172, held by Kiewit Infrastructure West Co.
- 2020-11-18: LITTLE WINGS CHILDCARE CENTER, Everett: WAR314173, held by Aeronautical Machinist, Inc
WOODLAND PUMP STATION AND TEMPORARY FORCE MAIN among its neighbors
130 discharge permits are in the Puyallup River subwatershed (HUC 171100140502); WAR314162 is one.
Other permits in the Puyallup River subwatershed (HUC 171100140502)
- 112TH STREET LOT, Tacoma: WAR314653, minor, term to 2025-12-31
- 137TH STREET EAST, Puyallup: WAR313641, minor, term to 2025-12-31
- 2412 INTER AVE, Puyallup: WAR314989, minor, term to 2025-12-31
- 4TH ST NW STORM SYSTEM UPGRADE PHASE N-2A, Puyallup: WAR315377, minor, term to 2030-12-31
- 5TH AVE NW IMPROVEMENTS PROJECT, Puyallup: WAR314351, minor, term to 2025-12-31
- 7TH AVE SE SIDEWALKS, Puyallup: WAR314001, minor, term to 2025-12-31
- 95TH AVENUE, Puyallup: WAR311081, minor, term to 2025-12-31
- 9TH AVE SW FAIR BOULEVARD, Puyallup: WAR314075, minor, term to 2025-12-31
- AIR PRODUCTS AND CHEMICALS INC, Puyallup: WAR001182, minor, term to 2024-12-31
- AMAZON.COM SERVICES LLC - RNT9, Fife: WAR310667, minor, term to 2024-12-31
What stands out
- Its term runs 5 years and 43 days, November 18, 2020 to December 31, 2025; the term ended 258 days before EPA's file was loaded on September 15, 2026, and the file lists the permit as administratively continued.
- Its newest dated event on file is an inspection on January 30, 2026, 228 days before EPA's file was loaded.
- In the 365 days to September 15, 2026, it was dated 1 inspection.
- EPA's file dates 1 event for it, all in 2026.
- It is one of 8,573 discharge permits on the register in Washington; 4,744 of them (55%) are in its program, Construction stormwater, and it is a minor discharger.
Identity
| Facility | WOODLAND PUMP STATION AND TEMPORARY FORCE MAIN |
|---|---|
| Permittee | Rodarte Construction, Inc. |
| NPDES ID | WAR314162 |
| Status | Administratively continued |
| Type | General permit coverage |
| Class | Minor |
| Facility type | Non-POTW |
| Program | Construction stormwater |
| Issued | November 18, 2020 |
| Expires | December 31, 2025 |
| Agency | State |
| Address | Puyallup, WA 98373 |
| Receiving water impaired | 303(D) Listed |
| Subwatershed | Puyallup River (HUC 171100140502) |
NPDES WAR314162: effluent limits and exceedances
WOODLAND PUMP STATION AND TEMPORARY FORCE MAIN (NPDES WAR314162): 3 pollutants on file, 3 limited; 3 with a violation of any kind, 0 with an exceedance.
| Pollutant | Limits | Violations | Exceedances | Latest | Largest, as filed |
|---|---|---|---|---|---|
| pH | 2 | 34 | 0 | ||
| Turbidity | 1 | 17 | 0 | ||
| Transparency | 1 | 11 | 0 |
NPDES WAR314162: inspections, violations and enforcement
NPDES WAR314162: 1 inspection
| Date | What EPA recorded | Agency |
|---|---|---|
| January 30, 2026 | Evaluation | S |
NPDES WAR314162 (WOODLAND PUMP STATION AND TEMPORARY FORCE MAIN): no single-event violation, formal enforcement action and informal enforcement action on file.
Watch NPDES WAR314162
NPDES WAR314162: one email when its EPA record changes — $99/month.
Permits near NPDES WAR314162
NPDES WAR314162: 3 pollutant rows, 1 dated events; ICIS-NPDES download, loaded September 15, 2026.