NPDES WYR104063 · Clean Water Act
FORMER DUBOIS SAWMILL SITE REFUSE PILE CLEANUP, WY: NPDES WYR104063 discharge permit, effluent exceedances, inspections, penalties
FORMER DUBOIS SAWMILL SITE REFUSE PILE CLEANUP, Wyoming: General permit coverage WYR104063, held by Town of Dubois; Construction stormwater; Administratively continued; issued April 22, 2016, term to February 1, 2020.
- November 3, 2025: WW Storm Water Construction - Failure to Maintain Records (ST6).
- November 3, 2025: WW Storm Water Construction - Failure to Conduct Inspections (ST6).
- November 3, 2025: WW Storm Water Construction - Failure to Implement SWPPP/SWMP (ST6).
Wyoming holds 323 Construction stormwater coverages of this permit type in EPA’s file; 1 were issued before WYR104063. Town of Dubois holds 2 permits in Wyoming.
Other permits held by Town of Dubois
- RODEO GROUNDS BRIDGE REPAIR, Dubois: WYTW10021, issued 2026-01-23
Coverages issued nearest WYR104063
- 2016-04-22: CHURCH BUTTES OIL & GAS PRODUCTION AND GATHERING SYSTEM: WYR103325, held by Wexpro Company
- 2016-04-22: BRUFF/MOXA ARCH OIL & GAS PRODUCTION AND GATHERING SYSTEM: WYR103326, held by Wexpro Company
- 2016-04-22: CASPER/DOUGLAS FIELD (FIELD PERMIT): WYR103591, held by EOG Resources, Inc.
- 2016-04-22: MONELL FIELD (FIELD PERMIT): WYR103648, held by FDL Operating, LLC
- 2016-04-22: WASHAKIE BASIN NATURAL GAS DEVELOPMENT AREA (FIELD PERMIT): WYR103809, held by Crowheart Energy, LLC
- 2016-04-22: SMITH RANCH-HIGHLAND OPERATION: WYR104157, held by Power Resources Inc. d/b/a Cameco Resources
- 2016-04-22: DJ BASIN-NIOBRARA (FIELD PERMIT): WYR104193, held by Anadarko E&P Onshore LLC
- 2016-04-22: NORTH BUTTE URANIUM ISR MINE PROJECT: WYR104286, held by Power Resources Inc. d/b/a Cameco Resources
- 2016-04-22: CHEROKEE RIDGE (FIELD PERMIT): WYR104323, held by Petro-Hunt LLC
- 2016-04-22: NICHOLS RANCH ISR PROJECT (LCGP): WYR104331, held by Uranerz Energy Corporation
What stands out
- Its term runs 3 years and 285 days, April 22, 2016 to February 1, 2020; the term ended 2,418 days before EPA's file was loaded on September 15, 2026, and the file lists the permit as administratively continued.
- Its newest dated event on file is a single-event violation on November 3, 2025, 316 days before EPA's file was loaded.
- In the 365 days to September 15, 2026, it was dated 3 single-event violations.
- EPA's file dates 3 events for it, all in 2025.
- It is one of 1,686 discharge permits on the register in Wyoming; 323 of them (19%) are in its program, Construction stormwater, and it is a minor discharger.
Identity
| Facility | FORMER DUBOIS SAWMILL SITE REFUSE PILE CLEANUP |
|---|---|
| Permittee | Town of Dubois |
| NPDES ID | WYR104063 |
| Status | Administratively continued |
| Type | General permit coverage |
| Class | Minor |
| Facility type | Non-POTW |
| Program | Construction stormwater |
| Issued | April 22, 2016 |
| Expires | February 1, 2020 |
| Address | WY |
NPDES WYR104063: effluent limits and exceedances
FORMER DUBOIS SAWMILL SITE REFUSE PILE CLEANUP (NPDES WYR104063): 0 pollutants on file, 0 limited; 0 with a violation of any kind, 0 with an exceedance.
NPDES WYR104063: no pollutant row on file.
NPDES WYR104063: inspections, violations and enforcement
NPDES WYR104063: 3 single-event violations
| Date | What EPA recorded | Agency |
|---|---|---|
| November 3, 2025 | WW Storm Water Construction - Failure to Maintain Records | ST6 |
| November 3, 2025 | WW Storm Water Construction - Failure to Conduct Inspections | ST6 |
| November 3, 2025 | WW Storm Water Construction - Failure to Implement SWPPP/SWMP | ST6 |
NPDES WYR104063 (FORMER DUBOIS SAWMILL SITE REFUSE PILE CLEANUP): no inspection, formal enforcement action and informal enforcement action on file.
Watch NPDES WYR104063
NPDES WYR104063: one email when its EPA record changes — $99/month.
Permits near NPDES WYR104063
NPDES WYR104063: 0 pollutant rows, 3 dated events; ICIS-NPDES download, loaded September 15, 2026.