EPA Air · inspections by county and year
Air-emissions inspections in Heard County, Georgia, 2018
- 29Inspections
A compliance evaluation is the on-site or file review a state, local or federal air agency records against a permitted source. Each row below is one inspection recorded against a source in Heard County, Georgia during 2018. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the Heard County facility page.
Heard County, Georgia, 2018
- Stack tests 10
Air-emissions inspections in Heard County, other years
Air-emissions inspections recorded in Heard County, Georgia, 2018
| Date | Facility | Kind | Agency |
|---|---|---|---|
| 2018-11-27 | SOUTHERN POWER - WANSLEY COMBINED CYCLE | PCE Off-Site | State |
| 2018-11-09 | HAWK ROAD ENERGY FACILITY | PCE Off-Site | State |
| 2018-11-08 | MUNICIPAL ELECTRIC AUTHORITY OF GA-WANSLEY | PCE Off-Site | State |
| 2018-11-05 | CHATTAHOOCHEE ENERGY FACILITY | PCE Off-Site | State |
| 2018-08-29 | SOUTHERN POWER - WANSLEY COMBINED CYCLE | PCE Off-Site | State |
| 2018-08-29 | SOUTHERN POWER - WANSLEY COMBINED CYCLE | PCE Off-Site | State |
| 2018-08-28 | PLASTI-PAINT INC. — high-priority violation on file | PCE Off-Site | State |
| 2018-08-16 | TENASKA GEORGIA GENERATING STATION | PCE Off-Site | State |
| 2018-08-10 | HAWK ROAD ENERGY FACILITY | PCE Off-Site | State |
| 2018-08-10 | HAWK ROAD ENERGY FACILITY | PCE Off-Site | State |
| 2018-08-09 | CHATTAHOOCHEE ENERGY FACILITY | PCE Off-Site | State |
| 2018-07-23 | MUNICIPAL ELECTRIC AUTHORITY OF GA-WANSLEY | PCE Off-Site | State |
| 2018-07-23 | PLASTI-PAINT INC. — high-priority violation on file | FCE On-Site | State |
| 2018-07-18 | PLASTI-PAINT INC. — high-priority violation on file | PCE On-Site Record/Report Review | State |
| 2018-06-06 | SOUTHERN POWER - WANSLEY COMBINED CYCLE | FCE On-Site | State |
| 2018-05-25 | SOUTHERN POWER - WANSLEY COMBINED CYCLE | PCE Off-Site | State |
| 2018-05-23 | SOUTHERN POWER - WANSLEY COMBINED CYCLE | PCE On-Site Record/Report Review | State |
| 2018-05-14 | HAWK ROAD ENERGY FACILITY | PCE Off-Site | State |
| 2018-05-14 | CHATTAHOOCHEE ENERGY FACILITY | PCE Off-Site | State |
| 2018-04-30 | MUNICIPAL ELECTRIC AUTHORITY OF GA-WANSLEY | PCE Off-Site | State |
| 2018-03-01 | HAWK ROAD ENERGY FACILITY | PCE Off-Site | State |
| 2018-03-01 | CHATTAHOOCHEE ENERGY FACILITY | PCE Off-Site | State |
| 2018-02-26 | CHATTAHOOCHEE ENERGY FACILITY | FCE On-Site | State |
| 2018-02-26 | PLASTI-PAINT INC. — high-priority violation on file | PCE Off-Site | State |
| 2018-02-22 | CHATTAHOOCHEE ENERGY FACILITY | PCE On-Site Record/Report Review | State |
| 2018-02-19 | TENASKA GEORGIA GENERATING STATION | PCE Off-Site | State |
| 2018-02-12 | SOUTHERN POWER - WANSLEY COMBINED CYCLE | PCE Off-Site | State |
| 2018-02-12 | SOUTHERN POWER - WANSLEY COMBINED CYCLE | PCE Off-Site | State |
| 2018-01-23 | MUNICIPAL ELECTRIC AUTHORITY OF GA-WANSLEY | PCE Off-Site | State |
Dates as filed by the agency that recorded the inspection. Figures from EPA’s ICIS-AIR download.