A compliance evaluation is the on-site or file review a state, local or federal air agency records against a permitted source. Each row below is one inspection recorded against a source in Heard County, Georgia during 2025. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the Heard County facility page.
Heard County, Georgia, 2025
- Stack tests 13
Air-emissions inspections in Heard County, other years
Air-emissions inspections recorded in Heard County, Georgia, 2025
| Date | Facility | Kind | Agency |
|---|---|---|---|
| 2025-12-30 | MUNICIPAL ELECTRIC AUTHORITY OF GA-WANSLEY | PCE On-Site Record/Report Review | State |
| 2025-12-30 | SOUTHERN POWER - WANSLEY COMBINED CYCLE | PCE On-Site Record/Report Review | State |
| 2025-11-25 | TENASKA GEORGIA GENERATING STATION | PCE Off-Site | State |
| 2025-11-17 | HAWK ROAD ENERGY FACILITY | PCE Off-Site | State |
| 2025-11-17 | CHATTAHOOCHEE ENERGY FACILITY | PCE Off-Site | State |
| 2025-11-12 | SOUTHERN POWER - WANSLEY COMBINED CYCLE | PCE Off-Site | State |
| 2025-10-30 | MUNICIPAL ELECTRIC AUTHORITY OF GA-WANSLEY | PCE Off-Site | State |
| 2025-09-17 | MUNICIPAL ELECTRIC AUTHORITY OF GA-WANSLEY | PCE Off-Site | State |
| 2025-08-15 | SOUTHERN POWER - WANSLEY COMBINED CYCLE | PCE Off-Site | State |
| 2025-08-11 | HAWK ROAD ENERGY FACILITY | PCE Off-Site | State |
| 2025-08-11 | HAWK ROAD ENERGY FACILITY | PCE Off-Site | State |
| 2025-08-11 | CHATTAHOOCHEE ENERGY FACILITY | PCE Off-Site | State |
| 2025-08-11 | CHATTAHOOCHEE ENERGY FACILITY | PCE Off-Site | State |
| 2025-08-06 | TENASKA GEORGIA GENERATING STATION | PCE Off-Site | State |
| 2025-07-29 | SOUTHERN POWER - WANSLEY COMBINED CYCLE | FCE On-Site | State |
| 2025-07-14 | PLASTI-PAINT INC. — high-priority violation on file | PCE Off-Site | State |
| 2025-07-02 | MUNICIPAL ELECTRIC AUTHORITY OF GA-WANSLEY | FCE On-Site | State |
| 2025-05-28 | MUNICIPAL ELECTRIC AUTHORITY OF GA-WANSLEY | PCE On-Site Record/Report Review | State |
| 2025-05-28 | SOUTHERN POWER - WANSLEY COMBINED CYCLE | PCE Off-Site | State |
| 2025-05-28 | SOUTHERN POWER - WANSLEY COMBINED CYCLE | PCE On-Site Record/Report Review | State |
| 2025-05-27 | HAWK ROAD ENERGY FACILITY | PCE Off-Site | State |
| 2025-05-27 | CHATTAHOOCHEE ENERGY FACILITY | PCE Off-Site | State |
| 2025-05-15 | TENASKA GEORGIA GENERATING STATION | PCE Off-Site | State |
| 2025-05-05 | MUNICIPAL ELECTRIC AUTHORITY OF GA-WANSLEY | PCE Off-Site | State |
| 2025-03-10 | TENASKA GEORGIA GENERATING STATION | FCE On-Site | State |
| 2025-02-27 | CHATTAHOOCHEE ENERGY FACILITY | PCE Off-Site | State |
| 2025-02-26 | HAWK ROAD ENERGY FACILITY | PCE Off-Site | State |
| 2025-02-26 | HAWK ROAD ENERGY FACILITY | PCE Off-Site | State |
| 2025-02-26 | CHATTAHOOCHEE ENERGY FACILITY | PCE Off-Site | State |
| 2025-02-21 | TENASKA GEORGIA GENERATING STATION | PCE Off-Site | State |
| 2025-02-20 | TENASKA GEORGIA GENERATING STATION | PCE On-Site Record/Report Review | State |
| 2025-02-06 | SOUTHERN POWER - WANSLEY COMBINED CYCLE | PCE Off-Site | State |
| 2025-02-03 | MUNICIPAL ELECTRIC AUTHORITY OF GA-WANSLEY | PCE Off-Site | State |
| 2025-01-30 | PLASTI-PAINT INC. — high-priority violation on file | PCE Off-Site | State |