Air-emissions inspections in St. Clair County, Michigan, 2021
- 36Inspections
A compliance evaluation is the on-site or file review a state, local or federal air agency records against a permitted source. Each row below is one inspection recorded against a source in St. Clair County, Michigan during 2021. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the St. Clair County facility page.
St. Clair County, Michigan, 2021
- Stack tests 26
Air-emissions inspections in St. Clair County, other years
Air-emissions inspections recorded in St. Clair County, Michigan, 2021
| Date | Facility | Kind | Agency |
|---|---|---|---|
| 2021-10-14 | INTERTAPE POLYMER GROUP | PCE On-Site | State |
| 2021-09-29 | MUELLER BRASS COMPANY | FCE On-Site | State |
| 2021-09-29 | DTE ELECTRIC COMPANY - GREENWOOD ENERGY CENTER | FCE On-Site | State |
| 2021-09-28 | CONSUMERS ENERGY - ST. CLAIR COMPRESSOR STATION | FCE On-Site | State |
| 2021-09-27 | DTE ST. CLAIR / BELLE RIVER POWER PLANT — high-priority violation on file | FCE On-Site | State |
| 2021-09-15 | MARYSVILLE HYDROCARBONS, LLC | PCE On-Site | State |
| 2021-09-14 | DUNN PAPER, INC. | FCE On-Site | State |
| 2021-08-26 | DTE ELECTRIC COMPANY - GREENWOOD ENERGY CENTER | PCE On-Site | State |
| 2021-08-24 | MICHIGAN METAL COATINGS | FCE On-Site | State |
| 2021-08-18 | ZF AXLE DRIVES MARYSVILLE | FCE On-Site | State |
| 2021-08-17 | ZF AXLE DRIVES MARYSVILLE | PCE Off-Site | State |
| 2021-08-16 | DUNN PAPER, INC. | PCE On-Site | State |
| 2021-08-11 | MARYSVILLE HYDROCARBONS, LLC | FCE On-Site | State |
| 2021-08-10 | DTE ST. CLAIR / BELLE RIVER POWER PLANT — high-priority violation on file | PCE On-Site | State |
| 2021-08-06 | GREAT LAKES WATER AUTHORITY - LAKE HURON PLANT | PCE On-Site | State |
| 2021-07-30 | DTE GAS COMPANY - BELLE RIVER MILLS COMPRESSOR STATION | FCE On-Site | State |
| 2021-07-23 | HEARTLAND STEEL PRODUCTS, LLC | FCE On-Site | State |
| 2021-07-22 | INTERTAPE POLYMER GROUP | PCE On-Site | State |
| 2021-07-22 | INTERTAPE POLYMER GROUP | FCE On-Site | State |
| 2021-07-22 | SUNSET ENTERPRISES HOLDINGS, LLC | FCE On-Site | State |
| 2021-06-15 | MUELLER BRASS COMPANY | PCE On-Site | State |
| 2021-06-15 | MARYSVILLE HYDROCARBONS, LLC | PCE On-Site | State |
| 2021-06-03 | SUNSET ENTERPRISES HOLDINGS, LLC | PCE On-Site | State |
| 2021-05-21 | SMR AUTOMOTIVE SYSTEMS USA, INC. | PCE On-Site | State |
| 2021-04-28 | CONFORMANCE COATING AND PROTOTYPE, INC | FCE On-Site | State |
| 2021-04-28 | MICHIGAN METAL COATINGS | FCE On-Site | State |
| 2021-04-14 | CONFORMANCE COATING AND PROTOTYPE, INC | PCE On-Site | State |
| 2021-03-31 | CONSUMERS ENERGY - ST. CLAIR COMPRESSOR STATION | PCE On-Site | State |
| 2021-03-18 | DTE ST. CLAIR / BELLE RIVER POWER PLANT — high-priority violation on file | PCE On-Site | State |
| 2021-03-10 | PREGIS | FCE On-Site | State |
| 2021-03-09 | HEARTLAND STEEL PRODUCTS, LLC | PCE On-Site | State |
| 2021-03-09 | MICHIGAN METAL COATINGS | PCE On-Site | State |
| 2021-02-10 | PREGIS | PCE On-Site | State |
| 2021-01-29 | DTE GAS COMPANY - BELLE RIVER MILLS COMPRESSOR STATION | PCE On-Site | State |
| 2021-01-06 | DTE GAS COMPANY - COLUMBUS COMPRESSOR STATION — high-priority violation on file | PCE Off-Site | State |
| 2021-01-06 | DTE GAS COMPANY - COLUMBUS COMPRESSOR STATION — high-priority violation on file | FCE On-Site | State |
Dates as filed by the agency that recorded the inspection. Figures from EPA’s ICIS-AIR download.