EPA Air · inspections by county and year
Air-emissions inspections in St. Clair County, Michigan, 2022
- 30Inspections
A compliance evaluation is the on-site or file review a state, local or federal air agency records against a permitted source. Each row below is one inspection recorded against a source in St. Clair County, Michigan during 2022. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the St. Clair County facility page.
St. Clair County, Michigan, 2022
Air-emissions inspections in St. Clair County, other years
Air-emissions inspections recorded in St. Clair County, Michigan, 2022
| Date | Facility | Kind | Agency |
|---|---|---|---|
| 2022-11-10 | MUELLER BRASS COMPANY | PCE On-Site | State |
| 2022-11-09 | MOD INTERIORS, INCORPORATED — high-priority violation on file | FCE On-Site | State |
| 2022-11-09 | MOD INTERIORS, INCORPORATED — high-priority violation on file | PCE On-Site | State |
| 2022-09-30 | ANR PIPELINE COMPANY - CAPAC COMPRESSOR STATION | FCE On-Site | State |
| 2022-09-28 | SMITHS CREEK LANDFILL | FCE On-Site | State |
| 2022-09-20 | DTE ELECTRIC COMPANY - GREENWOOD ENERGY CENTER | FCE On-Site | State |
| 2022-09-20 | SEMCO ENERGY GAS COMPANY - COLLIN FIELD | FCE On-Site | State |
| 2022-09-16 | DTE ST. CLAIR / BELLE RIVER POWER PLANT — high-priority violation on file | FCE On-Site | State |
| 2022-08-29 | BLUEWATER GAS STORAGE FACILITY - COLUMBUS | FCE On-Site | State |
| 2022-08-25 | TI FLUID SYSTEMS | FCE On-Site | State |
| 2022-08-18 | INTERNATIONAL AUTOMOTIVE COMPONENTS | PCE On-Site | State |
| 2022-08-18 | INTERNATIONAL AUTOMOTIVE COMPONENTS | FCE On-Site | State |
| 2022-08-11 | DTE ST. CLAIR / BELLE RIVER POWER PLANT — high-priority violation on file | PCE On-Site | State |
| 2022-08-02 | SUNOCO PIPELINE L.P. - MARYSVILLE PUMP STATION | PCE On-Site | State |
| 2022-08-02 | BLUEWATER GAS STORAGE FACILITY - COLUMBUS | PCE On-Site | State |
| 2022-08-01 | ANR PIPELINE COMPANY - CAPAC COMPRESSOR STATION | PCE On-Site | State |
| 2022-07-29 | PREGIS | FCE On-Site | State |
| 2022-07-27 | SEMCO ENERGY GAS COMPANY - COLLIN FIELD | PCE Off-Site | State |
| 2022-07-20 | DTE ELECTRIC COMPANY - GREENWOOD ENERGY CENTER | PCE On-Site | State |
| 2022-06-22 | SMITHS CREEK LANDFILL | PCE On-Site | State |
| 2022-06-15 | SEMCO ENERGY GAS COMPANY - MORTON WELLS FACILITY | FCE On-Site | State |
| 2022-06-03 | TI FLUID SYSTEMS | PCE On-Site | State |
| 2022-05-26 | SEMCO ENERGY GAS COMPANY - MORTON WELLS FACILITY | PCE On-Site | State |
| 2022-05-17 | PREGIS | PCE On-Site | State |
| 2022-04-27 | MICHIGAN METAL COATINGS | FCE On-Site | State |
| 2022-03-17 | DTE GAS COMPANY - COLUMBUS COMPRESSOR STATION — high-priority violation on file | FCE On-Site | State |
| 2022-03-10 | MICHIGAN METAL COATINGS | PCE On-Site | State |
| 2022-03-01 | SHAWMUT CORPORATION | FCE On-Site | State |
| 2022-02-08 | SHAWMUT CORPORATION | PCE On-Site | State |
| 2022-01-05 | DTE GAS COMPANY - COLUMBUS COMPRESSOR STATION — high-priority violation on file | PCE On-Site | State |
Dates as filed by the agency that recorded the inspection. Figures from EPA’s ICIS-AIR download.