EPA Air · inspections by county and year
Air-emissions inspections in Person County, North Carolina, 2023
- 92Inspections
A compliance evaluation is the on-site or file review a state, local or federal air agency records against a permitted source. Each row below is one inspection recorded against a source in Person County, North Carolina during 2023. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the Person County facility page.
Person County, North Carolina, 2023
Air-emissions inspections in Person County, other years
Air-emissions inspections recorded in Person County, North Carolina, 2023
| Date | Facility | Kind | Agency |
|---|---|---|---|
| 2023-11-13 | US FLUE CURED TOBACCO GROWERS, INC. | PCE Off-Site | State |
| 2023-11-07 | LOUISIANA-PACIFIC CORPORATION - ROXBORO — high-priority violation on file | PCE Off-Site | State |
| 2023-10-24 | US FLUE CURED TOBACCO GROWERS, INC. | FCE On-Site | State |
| 2023-09-26 | DUKE ENERGY PROGRESS, LLC - MAYO ELECTRIC GENERATING PLANT | PCE Off-Site | State |
| 2023-09-26 | DUKE ENERGY PROGRESS, LLC - MAYO ELECTRIC GENERATING PLANT | PCE Off-Site | State |
| 2023-09-26 | DUKE ENERGY PROGRESS, LLC - MAYO ELECTRIC GENERATING PLANT | PCE Off-Site | State |
| 2023-09-26 | DUKE ENERGY PROGRESS, LLC - MAYO ELECTRIC GENERATING PLANT | PCE Off-Site | State |
| 2023-09-20 | UPPER PIEDMONT ENVIRONMENTAL LANDFILL | FCE On-Site | State |
| 2023-09-13 | LOUISIANA-PACIFIC CORPORATION - ROXBORO — high-priority violation on file | FCE On-Site | State |
| 2023-08-24 | DUKE ENERGY PROGRESS, LLC - ROXBORO STEAM ELECTRIC PLANT | PCE Off-Site | State |
| 2023-08-24 | DUKE ENERGY PROGRESS, LLC - ROXBORO STEAM ELECTRIC PLANT | PCE Off-Site | State |
| 2023-08-24 | DUKE ENERGY PROGRESS, LLC - ROXBORO STEAM ELECTRIC PLANT | PCE Off-Site | State |
| 2023-08-24 | DUKE ENERGY PROGRESS, LLC - ROXBORO STEAM ELECTRIC PLANT | PCE Off-Site | State |
| 2023-08-24 | DUKE ENERGY PROGRESS, LLC - ROXBORO STEAM ELECTRIC PLANT | PCE Off-Site | State |
| 2023-08-24 | DUKE ENERGY PROGRESS, LLC - ROXBORO STEAM ELECTRIC PLANT | PCE Off-Site | State |
| 2023-08-24 | DUKE ENERGY PROGRESS, LLC - ROXBORO STEAM ELECTRIC PLANT | PCE Off-Site | State |
| 2023-08-24 | DUKE ENERGY PROGRESS, LLC - ROXBORO STEAM ELECTRIC PLANT | PCE Off-Site | State |
| 2023-08-24 | DUKE ENERGY PROGRESS, LLC - ROXBORO STEAM ELECTRIC PLANT | PCE Off-Site | State |
| 2023-08-24 | DUKE ENERGY PROGRESS, LLC - ROXBORO STEAM ELECTRIC PLANT | PCE Off-Site | State |
| 2023-08-24 | DUKE ENERGY PROGRESS, LLC - ROXBORO STEAM ELECTRIC PLANT | PCE Off-Site | State |
| 2023-08-24 | DUKE ENERGY PROGRESS, LLC - ROXBORO STEAM ELECTRIC PLANT | PCE Off-Site | State |
| 2023-08-24 | DUKE ENERGY PROGRESS, LLC - ROXBORO STEAM ELECTRIC PLANT | PCE Off-Site | State |
| 2023-08-24 | DUKE ENERGY PROGRESS, LLC - ROXBORO STEAM ELECTRIC PLANT | PCE Off-Site | State |
| 2023-08-24 | SUNROCK INDUSTRIES LLC - WOODSDALE | FCE On-Site | State |
| 2023-08-23 | UPPER PIEDMONT ENVIRONMENTAL LANDFILL | PCE Off-Site | State |
| 2023-08-22 | DUKE ENERGY PROGRESS, LLC - ROXBORO STEAM ELECTRIC PLANT | PCE Off-Site | State |
| 2023-08-22 | DUKE ENERGY PROGRESS, LLC - ROXBORO STEAM ELECTRIC PLANT | PCE Off-Site | State |
| 2023-08-22 | DUKE ENERGY PROGRESS, LLC - ROXBORO STEAM ELECTRIC PLANT | PCE Off-Site | State |
| 2023-08-22 | DUKE ENERGY PROGRESS, LLC - ROXBORO STEAM ELECTRIC PLANT | PCE Off-Site | State |
| 2023-08-22 | DUKE ENERGY PROGRESS, LLC - ROXBORO STEAM ELECTRIC PLANT | PCE Off-Site | State |
| 2023-08-22 | DUKE ENERGY PROGRESS, LLC - ROXBORO STEAM ELECTRIC PLANT | PCE Off-Site | State |
| 2023-08-09 | DUKE ENERGY PROGRESS, LLC - MAYO ELECTRIC GENERATING PLANT | FCE On-Site | State |
| 2023-08-02 | DUKE ENERGY PROGRESS, LLC - ROXBORO STEAM ELECTRIC PLANT | PCE Off-Site | State |
| 2023-08-02 | DUKE ENERGY PROGRESS, LLC - ROXBORO STEAM ELECTRIC PLANT | PCE Off-Site | State |
| 2023-08-02 | DUKE ENERGY PROGRESS, LLC - MAYO ELECTRIC GENERATING PLANT | PCE Off-Site | State |
| 2023-08-02 | DUKE ENERGY PROGRESS, LLC - MAYO ELECTRIC GENERATING PLANT | PCE Off-Site | State |
| 2023-08-02 | LOUISIANA-PACIFIC CORPORATION - ROXBORO — high-priority violation on file | PCE Off-Site | State |
| 2023-08-02 | LOUISIANA-PACIFIC CORPORATION - ROXBORO — high-priority violation on file | PCE Off-Site | State |
| 2023-08-01 | US FLUE CURED TOBACCO GROWERS, INC. | PCE Off-Site | State |
| 2023-07-26 | LOUISIANA-PACIFIC CORPORATION - ROXBORO — high-priority violation on file | PCE Off-Site | State |
| 2023-07-26 | LOUISIANA-PACIFIC CORPORATION - ROXBORO — high-priority violation on file | PCE Off-Site | State |
| 2023-07-26 | LOUISIANA-PACIFIC CORPORATION - ROXBORO — high-priority violation on file | PCE Off-Site | State |
| 2023-07-26 | CERTAINTEED ROXBORO WALLBOARD FACILITY | PCE Off-Site | State |
| 2023-07-26 | CERTAINTEED ROXBORO WALLBOARD FACILITY | PCE Off-Site | State |
| 2023-07-13 | DUKE ENERGY PROGRESS, LLC - MAYO ELECTRIC GENERATING PLANT | PCE Off-Site | State |
| 2023-07-13 | DUKE ENERGY PROGRESS, LLC - MAYO ELECTRIC GENERATING PLANT | PCE Off-Site | State |
| 2023-07-13 | DUKE ENERGY PROGRESS, LLC - MAYO ELECTRIC GENERATING PLANT | PCE Off-Site | State |
| 2023-06-27 | US FLUE CURED TOBACCO GROWERS, INC. | FCE On-Site | State |
| 2023-06-20 | CERTAINTEED ROXBORO WALLBOARD FACILITY | FCE On-Site | State |
| 2023-06-13 | MARTIN MARIETTA MATERIALS, INC. - PERSON QUARRY | PCE On-Site | State |
| 2023-06-08 | LOUISIANA-PACIFIC CORPORATION - ROXBORO — high-priority violation on file | PCE Off-Site | State |
| 2023-06-07 | LOUISIANA-PACIFIC CORPORATION - ROXBORO — high-priority violation on file | PCE Off-Site | State |
| 2023-06-06 | DUKE ENERGY PROGRESS, LLC - ROXBORO STEAM ELECTRIC PLANT | PCE Off-Site | State |
| 2023-06-06 | DUKE ENERGY PROGRESS, LLC - ROXBORO STEAM ELECTRIC PLANT | PCE Off-Site | State |
| 2023-06-06 | DUKE ENERGY PROGRESS, LLC - ROXBORO STEAM ELECTRIC PLANT | PCE Off-Site | State |
| 2023-06-06 | DUKE ENERGY PROGRESS, LLC - ROXBORO STEAM ELECTRIC PLANT | PCE Off-Site | State |
| 2023-06-06 | DUKE ENERGY PROGRESS, LLC - ROXBORO STEAM ELECTRIC PLANT | PCE Off-Site | State |
| 2023-06-06 | DUKE ENERGY PROGRESS, LLC - ROXBORO STEAM ELECTRIC PLANT | PCE Off-Site | State |
| 2023-06-06 | DUKE ENERGY PROGRESS, LLC - ROXBORO STEAM ELECTRIC PLANT | PCE Off-Site | State |
| 2023-05-17 | DUKE ENERGY PROGRESS, LLC - ROXBORO STEAM ELECTRIC PLANT | FCE On-Site | State |
| 2023-05-15 | US FLUE CURED TOBACCO GROWERS, INC. | PCE Off-Site | State |
| 2023-05-01 | LOUISIANA-PACIFIC CORPORATION - ROXBORO — high-priority violation on file | PCE Off-Site | State |
| 2023-04-25 | DUKE ENERGY PROGRESS, LLC - MAYO ELECTRIC GENERATING PLANT | PCE Off-Site | State |
| 2023-04-25 | DUKE ENERGY PROGRESS, LLC - MAYO ELECTRIC GENERATING PLANT | PCE Off-Site | State |
| 2023-04-25 | DUKE ENERGY PROGRESS, LLC - MAYO ELECTRIC GENERATING PLANT | PCE Off-Site | State |
| 2023-04-25 | DUKE ENERGY PROGRESS, LLC - MAYO ELECTRIC GENERATING PLANT | PCE Off-Site | State |
| 2023-04-03 | UPPER PIEDMONT ENVIRONMENTAL LANDFILL | PCE Off-Site | State |
| 2023-03-27 | LOUISIANA-PACIFIC CORPORATION - ROXBORO — high-priority violation on file | PCE Off-Site | State |
| 2023-03-13 | DUKE ENERGY PROGRESS, LLC - ROXBORO STEAM ELECTRIC PLANT | PCE Off-Site | State |
| 2023-03-13 | DUKE ENERGY PROGRESS, LLC - MAYO ELECTRIC GENERATING PLANT | PCE Off-Site | State |
| 2023-03-06 | DUKE ENERGY PROGRESS, LLC - MAYO ELECTRIC GENERATING PLANT | PCE Off-Site | State |
| 2023-03-06 | DUKE ENERGY PROGRESS, LLC - MAYO ELECTRIC GENERATING PLANT | PCE Off-Site | State |
| 2023-03-06 | DUKE ENERGY PROGRESS, LLC - MAYO ELECTRIC GENERATING PLANT | PCE Off-Site | State |
| 2023-03-01 | DUKE ENERGY PROGRESS, LLC - MAYO ELECTRIC GENERATING PLANT | PCE Off-Site | State |
| 2023-03-01 | DUKE ENERGY PROGRESS, LLC - MAYO ELECTRIC GENERATING PLANT | PCE Off-Site | State |
| 2023-03-01 | LOUISIANA-PACIFIC CORPORATION - ROXBORO — high-priority violation on file | PCE Off-Site | State |
| 2023-03-01 | LOUISIANA-PACIFIC CORPORATION - ROXBORO — high-priority violation on file | PCE Off-Site | State |
| 2023-03-01 | LOUISIANA-PACIFIC CORPORATION - ROXBORO — high-priority violation on file | PCE Off-Site | State |
| 2023-03-01 | LOUISIANA-PACIFIC CORPORATION - ROXBORO — high-priority violation on file | PCE Off-Site | State |
| 2023-03-01 | LOUISIANA-PACIFIC CORPORATION - ROXBORO — high-priority violation on file | PCE Off-Site | State |
| 2023-02-28 | DUKE ENERGY PROGRESS, LLC - ROXBORO STEAM ELECTRIC PLANT | PCE Off-Site | State |
| 2023-02-28 | DUKE ENERGY PROGRESS, LLC - ROXBORO STEAM ELECTRIC PLANT | PCE Off-Site | State |
| 2023-02-24 | CERTAINTEED ROXBORO WALLBOARD FACILITY | PCE Off-Site | State |
| 2023-02-24 | CERTAINTEED ROXBORO WALLBOARD FACILITY | PCE Off-Site | State |
| 2023-02-07 | US FLUE CURED TOBACCO GROWERS, INC. | PCE Off-Site | State |
| 2023-01-23 | SUNROCK INDUSTRIES LLC - WOODSDALE | PCE Off-Site | State |
| 2023-01-09 | DUKE ENERGY PROGRESS, LLC - ROXBORO STEAM ELECTRIC PLANT | PCE Off-Site | State |
| 2023-01-09 | DUKE ENERGY PROGRESS, LLC - ROXBORO STEAM ELECTRIC PLANT | PCE Off-Site | State |
| 2023-01-09 | DUKE ENERGY PROGRESS, LLC - ROXBORO STEAM ELECTRIC PLANT | PCE Off-Site | State |
| 2023-01-09 | DUKE ENERGY PROGRESS, LLC - ROXBORO STEAM ELECTRIC PLANT | PCE Off-Site | State |
| 2023-01-09 | DUKE ENERGY PROGRESS, LLC - ROXBORO STEAM ELECTRIC PLANT | PCE Off-Site | State |
| 2023-01-09 | DUKE ENERGY PROGRESS, LLC - ROXBORO STEAM ELECTRIC PLANT | PCE Off-Site | State |
Dates as filed by the agency that recorded the inspection. Figures from EPA’s ICIS-AIR download.