EPA Air · inspections by county and year
Air-emissions inspections in Wake County, North Carolina, 2017
- 62Inspections
A compliance evaluation is the on-site or file review a state, local or federal air agency records against a permitted source. Each row below is one inspection recorded against a source in Wake County, North Carolina during 2017. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the Wake County facility page.
Wake County, North Carolina, 2017
- Stack tests 11
Air-emissions inspections in Wake County, other years
Air-emissions inspections recorded in Wake County, North Carolina, 2017
| Date | Facility | Kind | Agency |
|---|---|---|---|
| 2017-12-19 | ENTERPRISE PROPANE TERMINALS AND STORAGE, LLC -APEX TERMINAL | FCE On-Site | State |
| 2017-11-30 | S. T. WOOTEN PLANT 5 - BANKS RD | PCE On-Site | State |
| 2017-11-28 | THOMAS CONCRETE OF CAROLINA INC-WEST STREET PLANT | PCE On-Site | State |
| 2017-11-20 | HEIDELBERG MATERIALS SOUTHEAST AGG LLC- HOLLY SPRINGS QUARRY | PCE Off-Site | State |
| 2017-09-28 | DUKE ENERGY PROGRESS, LLC - HARRIS NUCLEAR PLANT | FCE On-Site | State |
| 2017-09-27 | THOMAS CONCRETE OF CAROLINA INC | PCE On-Site | State |
| 2017-09-26 | BARNHILL CONTRACTING COMPANY - RALEIGH PLANT | FCE On-Site | State |
| 2017-09-26 | WAKE STONE CORPORATION - TRIANGLE QUARRY | PCE On-Site | State |
| 2017-09-26 | T. R. VERNAL PAVING, INC. | FCE On-Site | State |
| 2017-09-25 | ACCU-FAB, INC. | PCE On-Site | State |
| 2017-09-21 | FSC II, LLC - KNIGHTDALE ASPHALT PLANT | FCE On-Site | State |
| 2017-09-19 | WAKEMED | FCE On-Site | State |
| 2017-09-19 | FSC II, LLC - HOLLY SPRINGS ASPHALT PLANT | PCE On-Site | State |
| 2017-09-19 | CAPITAL READY MIX CONCRETE - KNIGHTDALE PLANT | PCE On-Site | State |
| 2017-09-19 | TT&E IRON & METAL | FCE On-Site | State |
| 2017-09-18 | EAGLE ROCK CONCRETE - MOUNT HERMAN ROAD | PCE On-Site | State |
| 2017-09-17 | HEIDELBERG MATERIALS SOUTHEAST AGG LLC- HOLLY SPRINGS QUARRY | PCE Off-Site | State |
| 2017-09-15 | SOUTHERN EQUIPMENT CO. - RALEIGH PLANT #4 | PCE On-Site | State |
| 2017-09-15 | READY MIXED CONCRETE COMPANY, PLANT #3, WESTGATE RD | PCE On-Site | State |
| 2017-09-14 | SOUTHERN EQUIP CO. - RALEIGH PLT #2 | PCE On-Site | State |
| 2017-09-14 | FIDELITY REAL ESTATE CO.- FIDELITY MORRISVILLE DATA CENTER | FCE On-Site | State |
| 2017-09-13 | UNILIN FLOORING - GARNER FLOORING FACILITY | FCE On-Site | State |
| 2017-09-07 | FSC II, LLC - WESTGATE ASPHALT PLANT | FCE On-Site | State |
| 2017-09-07 | BLYTHE CONSTRUCTION, INC. GARNER PLANT | FCE On-Site | State |
| 2017-09-07 | BLYTHE CONSTRUCTION, INC. GRESHAM LAKE PLANT | FCE On-Site | State |
| 2017-09-07 | FSC II, LLC - NORTH RALEIGH ASPHALT PLANT | FCE On-Site | State |
| 2017-09-06 | BLYTHE CONSTRUCTION, INC. WEST RALEIGH PLANT | FCE On-Site | State |
| 2017-09-06 | FSC II, LLC - HOLLY SPRINGS ASPHALT PLANT | FCE On-Site | State |
| 2017-08-31 | NC DAC - CENTRAL PRISON | FCE On-Site | State |
| 2017-08-30 | RALEIGH-DURHAM AIRPORT AUTHORITY | FCE On-Site | State |
| 2017-08-25 | AUSTIN QUALITY FOODS, INC. | FCE On-Site | State |
| 2017-08-15 | SPECGX LLC - MALLINCKRODT PHARMACEUTICALS | FCE On-Site | State |
| 2017-08-10 | REX HEALTHCARE | FCE On-Site | State |
| 2017-08-09 | WAKEMED CARY HOSPITAL | FCE On-Site | State |
| 2017-08-07 | NORTH CAROLINA STATE UNIVERSITY | FCE On-Site | State |
| 2017-07-27 | SOUTHERN EQUIPMENT CO (DBA RMCC) - APEX - PLANT #6 | PCE On-Site | State |
| 2017-07-18 | NOMACO INC. - ZEBULON | FCE On-Site | State |
| 2017-07-11 | SOUTH WAKE LANDFILL | FCE On-Site | State |
| 2017-06-30 | NC DOA CENTRAL HEATING PLANT | FCE On-Site | State |
| 2017-06-29 | NORTH WAKE COUNTY LANDFILL | FCE On-Site | State |
| 2017-06-14 | BIOGEN | FCE On-Site | State |
| 2017-06-09 | GLOBAL COMPANIES - APEX TERMINAL | FCE On-Site | State |
| 2017-06-09 | WESTERN WAKE REGIONAL WATER RECLAMATION FACILITY | FCE On-Site | State |
| 2017-06-07 | AJINOMOTO HEALTH & NUTRITION NORTH AMERICA, INC. | PCE On-Site | State |
| 2017-06-07 | RUSSELL CARROLL MANUFACTURING INC. | PCE On-Site | State |
| 2017-06-02 | SEQIRUS INC. | FCE On-Site | State |
| 2017-05-24 | CHARLES RIVER LABORATORIES | PCE On-Site | State |
| 2017-05-17 | GSK, INC. | PCE On-Site | State |
| 2017-05-04 | MEREDITH COLLEGE | PCE On-Site | State |
| 2017-04-05 | TOWN OF CARY - SOUTH CARY WATER RECLAMATION FACILITY | PCE On-Site | State |
| 2017-03-07 | T. R. VERNAL PAVING, INC. | PCE Off-Site | State |
| 2017-02-28 | CITY OF RALEIGH WILDERS GROVE LANDFILL | FCE On-Site | State |
| 2017-02-28 | T. R. VERNAL PAVING, INC. | PCE Off-Site | State |
| 2017-02-21 | FUJIFILM DIOSYNTH BIOTECHNOLOGIES U.S.A., INC. | PCE On-Site | State |
| 2017-02-17 | SOUTHERN EQUIPMENT CO (DBA RMCC) - KNIGHTDALE - PLANT #1 | PCE On-Site | State |
| 2017-02-16 | SUNROCK INDUSTRIES LLC - RDU DISTRIBUTION CENTER | FCE On-Site | State |
| 2017-02-16 | SOUTHERN EQUIPMENT CO (DBA RMCC) - KNIGHTDALE - PLANT #1 | PCE On-Site | State |
| 2017-02-14 | MARTIN MARIETTA MATERIALS, INC. - RALEIGH DURHAM QUARRY | PCE On-Site | State |
| 2017-01-26 | POTTERS INDUSTRIES, LLC | FCE On-Site | State |
| 2017-01-04 | FSC II, LLC - GARNER ASPHALT PLANT | FCE On-Site | State |
| 2017-01-04 | RALEIGH TRANSFLO TERMINAL | FCE On-Site | State |
| 2017-01-03 | WAKE COUNTY JUSTICE CENTER AND COMPLEX | PCE Off-Site | State |
Dates as filed by the agency that recorded the inspection. Figures from EPA’s ICIS-AIR download.