EPA Air · inspections by county and year
Air-emissions inspections in Queens County, New York, 2017
- 206Inspections
A compliance evaluation is the on-site or file review a state, local or federal air agency records against a permitted source. Each row below is one inspection recorded against a source in Queens County, New York during 2017. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the Queens County facility page.
Queens County, New York, 2017
- Stack tests 17
Air-emissions inspections in Queens County, other years
Air-emissions inspections recorded in Queens County, New York, 2017
| Date | Facility | Kind | Agency |
|---|---|---|---|
| 2017-12-28 | RAVENSWOOD STEAM PLANT | PCE Off-Site | State |
| 2017-12-15 | RAVENSWOOD GENERATING STATION | PCE Off-Site | State |
| 2017-11-28 | RAVENSWOOD STEAM PLANT | PCE Off-Site | State |
| 2017-11-27 | RAVENSWOOD GENERATING STATION | PCE Off-Site | State |
| 2017-11-13 | ASTORIA GENERATING STATION | PCE Off-Site | State |
| 2017-11-02 | US POSTAL SERVICES-QUEENS GMF | FCE On-Site | U.S. EPA |
| 2017-11-01 | RAVENSWOOD GENERATING STATION | PCE Off-Site | State |
| 2017-11-01 | RAVENSWOOD GENERATING STATION | PCE Off-Site | State |
| 2017-11-01 | RAVENSWOOD GENERATING STATION | PCE Off-Site | State |
| 2017-11-01 | RAVENSWOOD GENERATING STATION | PCE Off-Site | State |
| 2017-11-01 | RAVENSWOOD GENERATING STATION | PCE Off-Site | State |
| 2017-10-30 | NYPA - ASTORIA CAMPUS | PCE Off-Site | State |
| 2017-10-30 | NYPA - VERNON BOULEVARD PLANT | PCE Off-Site | State |
| 2017-10-27 | CON ED - ASTORIA FACILITY | PCE Off-Site | State |
| 2017-10-27 | RAVENSWOOD STEAM PLANT | PCE Off-Site | State |
| 2017-10-27 | RAVENSWOOD STEAM PLANT | PCE Off-Site | State |
| 2017-10-26 | LONG ISLAND JEWISH MEDICAL CENTER | PCE Off-Site | State |
| 2017-10-26 | LONG ISLAND JEWISH MEDICAL CENTER | PCE Off-Site | State |
| 2017-10-26 | BAYSWATER / JAMAICA BAY PEAKING FACILITY | PCE Off-Site | State |
| 2017-10-26 | BAYSWATER / JAMAICA BAY PEAKING FACILITY | PCE Off-Site | State |
| 2017-10-24 | ASTORIA ENERGY LLC & ASTORIA ENERGY II LLC | PCE Off-Site | State |
| 2017-10-24 | ASTORIA ENERGY LLC & ASTORIA ENERGY II LLC | PCE Off-Site | State |
| 2017-10-24 | ASTORIA ENERGY LLC & ASTORIA ENERGY II LLC | PCE Off-Site | State |
| 2017-10-23 | STEINWAY & SONS - QUEENS FACILITY | PCE Off-Site | State |
| 2017-10-23 | STEINWAY & SONS - QUEENS FACILITY | PCE Off-Site | State |
| 2017-10-23 | ASTORIA GENERATING STATION | PCE Off-Site | State |
| 2017-10-23 | ASTORIA GENERATING STATION | PCE Off-Site | State |
| 2017-10-23 | RAVENSWOOD STEAM PLANT | PCE Off-Site | State |
| 2017-10-19 | CALPINE JFK ENERGY CENTER | PCE Off-Site | State |
| 2017-10-16 | ASTORIA GENERATING STATION | PCE Off-Site | State |
| 2017-10-13 | N SHORE TOWERS APT TOTAL ENERGY PLANT | PCE Off-Site | State |
| 2017-10-13 | N SHORE TOWERS APT TOTAL ENERGY PLANT | PCE Off-Site | State |
| 2017-10-02 | RAVENSWOOD GENERATING STATION | PCE Off-Site | State |
| 2017-09-28 | RAVENSWOOD STEAM PLANT | PCE Off-Site | State |
| 2017-09-27 | TALLMAN ISLAND WASTEWATER RESOURCE RECOVERY FACILITY | FCE On-Site | State |
| 2017-09-26 | BOWERY BAY WASTEWATER RESOURCE RECOVERY FACILITY | FCE On-Site | State |
| 2017-09-22 | TALLMAN ISLAND WASTEWATER RESOURCE RECOVERY FACILITY | PCE On-Site | State |
| 2017-09-19 | NYPA - ASTORIA CAMPUS | FCE On-Site | State |
| 2017-09-13 | ASTORIA GENERATING STATION | PCE Off-Site | State |
| 2017-09-12 | NYPA - ASTORIA CAMPUS | PCE On-Site | State |
| 2017-09-12 | EPIC PHARMA LLC | FCE On-Site | State |
| 2017-09-09 | EPIC PHARMA LLC | PCE Off-Site | State |
| 2017-09-01 | ASTORIA GENERATING STATION | FCE On-Site | State |
| 2017-08-31 | BOWERY BAY WASTEWATER RESOURCE RECOVERY FACILITY | PCE On-Site | State |
| 2017-08-30 | CON ED - ASTORIA FACILITY | FCE On-Site | State |
| 2017-08-29 | RAVENSWOOD STEAM PLANT | FCE On-Site | State |
| 2017-08-24 | RAVENSWOOD GENERATING STATION | FCE On-Site | State |
| 2017-08-23 | RAVENSWOOD GENERATING STATION | PCE Off-Site | State |
| 2017-08-22 | RAVENSWOOD STEAM PLANT | PCE Off-Site | State |
| 2017-08-16 | LAGUARDIA AIRPORT CENTRAL TERMINAL BUILDING REPLACEMENT | FCE On-Site | State |
| 2017-08-16 | BAYSWATER / JAMAICA BAY PEAKING FACILITY | FCE On-Site | State |
| 2017-08-14 | ASTORIA GENERATING STATION | PCE Off-Site | State |
| 2017-08-02 | RAVENSWOOD GENERATING STATION | PCE Off-Site | State |
| 2017-08-02 | RAVENSWOOD GENERATING STATION | PCE Off-Site | State |
| 2017-08-02 | RAVENSWOOD GENERATING STATION | PCE Off-Site | State |
| 2017-08-01 | CON ED - ASTORIA FACILITY | PCE Off-Site | State |
| 2017-08-01 | RAVENSWOOD STEAM PLANT | PCE Off-Site | State |
| 2017-08-01 | RAVENSWOOD STEAM PLANT | PCE Off-Site | State |
| 2017-07-31 | ASTORIA ENERGY LLC & ASTORIA ENERGY II LLC | PCE Off-Site | State |
| 2017-07-31 | NYPA - ASTORIA CAMPUS | PCE Off-Site | State |
| 2017-07-31 | NYPA - ASTORIA CAMPUS | PCE Off-Site | State |
| 2017-07-31 | SIMSMETAL EAST LLC-QUEENS PLANT | PCE Off-Site | State |
| 2017-07-31 | SIMSMETAL EAST LLC-QUEENS PLANT | PCE Off-Site | State |
| 2017-07-31 | BIG SIX TOWERS INC | PCE Off-Site | State |
| 2017-07-31 | NYPA - VERNON BOULEVARD PLANT | PCE Off-Site | State |
| 2017-07-31 | NYPA - VERNON BOULEVARD PLANT | PCE Off-Site | State |
| 2017-07-27 | CON ED - ASTORIA FACILITY | PCE Off-Site | State |
| 2017-07-27 | ASTORIA ENERGY LLC & ASTORIA ENERGY II LLC | FCE On-Site | State |
| 2017-07-27 | TALLMAN ISLAND WASTEWATER RESOURCE RECOVERY FACILITY | PCE Off-Site | State |
| 2017-07-27 | TALLMAN ISLAND WASTEWATER RESOURCE RECOVERY FACILITY | PCE Off-Site | State |
| 2017-07-27 | TALLMAN ISLAND WASTEWATER RESOURCE RECOVERY FACILITY | PCE Off-Site | State |
| 2017-07-27 | TALLMAN ISLAND WASTEWATER RESOURCE RECOVERY FACILITY | PCE Off-Site | State |
| 2017-07-27 | TALLMAN ISLAND WASTEWATER RESOURCE RECOVERY FACILITY | PCE Off-Site | State |
| 2017-07-27 | TALLMAN ISLAND WASTEWATER RESOURCE RECOVERY FACILITY | PCE Off-Site | State |
| 2017-07-27 | TALLMAN ISLAND WASTEWATER RESOURCE RECOVERY FACILITY | PCE Off-Site | State |
| 2017-07-27 | TALLMAN ISLAND WASTEWATER RESOURCE RECOVERY FACILITY | PCE Off-Site | State |
| 2017-07-27 | ST JOHNS UNIVERSITY | PCE Off-Site | State |
| 2017-07-27 | QUEENS FRESH MEADOWS FACILITY | PCE Off-Site | State |
| 2017-07-26 | NYPA - VERNON BOULEVARD PLANT | FCE On-Site | State |
| 2017-07-26 | N SHORE TOWERS APT TOTAL ENERGY PLANT | FCE On-Site | State |
| 2017-07-26 | BAYSWATER / JAMAICA BAY PEAKING FACILITY | PCE Off-Site | State |
| 2017-07-25 | ASTORIA GENERATING STATION | PCE Off-Site | State |
| 2017-07-25 | ASTORIA GENERATING STATION | PCE Off-Site | State |
| 2017-07-25 | ASTORIA GENERATING STATION | PCE Off-Site | State |
| 2017-07-25 | ASTORIA GENERATING STATION | PCE Off-Site | State |
| 2017-07-24 | ROCHDALE VILLAGE | PCE Off-Site | State |
| 2017-07-21 | ASTORIA GENERATING STATION | PCE On-Site | State |
| 2017-07-20 | BAYSWATER / JAMAICA BAY PEAKING FACILITY | PCE On-Site | State |
| 2017-07-19 | SIMSMETAL EAST LLC-QUEENS PLANT | FCE On-Site | State |
| 2017-07-19 | RAVENSWOOD STEAM PLANT | PCE Off-Site | State |
| 2017-07-17 | RAVENSWOOD STEAM PLANT | PCE Off-Site | State |
| 2017-07-17 | CALPINE JFK ENERGY CENTER | PCE Off-Site | State |
| 2017-07-17 | CALPINE JFK ENERGY CENTER | PCE Off-Site | State |
| 2017-07-14 | ASTORIA GENERATING STATION | PCE Off-Site | State |
| 2017-07-14 | LAGUARDIA AIRPORT CENTRAL TERMINAL BUILDING REPLACEMENT | PCE On-Site | State |
| 2017-07-14 | LAGUARDIA AIRPORT CENTRAL TERMINAL BUILDING REPLACEMENT | PCE Off-Site | State |
| 2017-07-13 | EPIC PHARMA LLC | PCE On-Site | State |
| 2017-06-30 | RAVENSWOOD GENERATING STATION | PCE On-Site | State |
| 2017-06-29 | CON ED - ASTORIA FACILITY | PCE On-Site | State |
| 2017-06-29 | CALPINE JFK ENERGY CENTER | FCE On-Site | State |
Page 1 of 3NextPage 2
Dates as filed by the agency that recorded the inspection. Figures from EPA’s ICIS-AIR download.