EPA Air · inspections by county and year
Air-emissions inspections in Dallas County, Texas, 2023
- 12Inspections
A compliance evaluation is the on-site or file review a state, local or federal air agency records against a permitted source. Each row below is one inspection recorded against a source in Dallas County, Texas during 2023. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the Dallas County facility page.
Dallas County, Texas, 2023
- Stack tests 14
Air-emissions inspections in Dallas County, other years
Air-emissions inspections recorded in Dallas County, Texas, 2023
| Date | Facility | Kind | Agency |
|---|---|---|---|
| 2023-11-29 | SOLAR TURBINES DLS OVERHAUL CENTER | FCE On-Site | State |
| 2023-08-31 | LAKE HUBBARD STEAM ELECTRIC STATION | FCE On-Site | State |
| 2023-08-28 | CABINETWORKS GROUP DUNCANVILLE | FCE On-Site | State |
| 2023-08-21 | VALSPAR GARLAND FACILITY | FCE On-Site | State |
| 2023-07-27 | EXXON MOBIL IRVING TERMINAL | FCE On-Site | State |
| 2023-07-24 | REPKON USA DEFENSE GARLAND | FCE On-Site | State |
| 2023-07-24 | PRINTPACK | FCE On-Site | State |
| 2023-06-08 | DAL-TILE SUNNYVALE MANUFACTURING PLANT | FCE On-Site | State |
| 2023-05-01 | WESTROCK CONVERTING DALLAS MILL | FCE On-Site | State |
| 2023-03-21 | TEXAS INSTRUMENTS NORTH CAMPUS | FCE On-Site | State |
| 2023-03-13 | MOUNTAIN CREEK STEAM ELECTRIC STATION | FCE On-Site | State |
| 2023-01-10 | MCCOMMAS BLUFF LFG PROCESSING FACILITY | FCE On-Site | State |
Dates as filed by the agency that recorded the inspection. Figures from EPA’s ICIS-AIR download.