EPA Air · inspections by county and year
Air-emissions inspections in Dallas County, Texas, 2025
- 14Inspections
A compliance evaluation is the on-site or file review a state, local or federal air agency records against a permitted source. Each row below is one inspection recorded against a source in Dallas County, Texas during 2025. A facility can appear several times: this is the year’s record of what happened, not a list of places. The sources themselves are on the Dallas County facility page.
Dallas County, Texas, 2025
Air-emissions inspections in Dallas County, other years
Air-emissions inspections recorded in Dallas County, Texas, 2025
| Date | Facility | Kind | Agency |
|---|---|---|---|
| 2025-12-17 | SOLAR TURBINES DLS OVERHAUL CENTER | FCE On-Site | State |
| 2025-08-26 | CABINETWORKS GROUP DUNCANVILLE | FCE On-Site | State |
| 2025-08-25 | LAKE HUBBARD STEAM ELECTRIC STATION | FCE On-Site | State |
| 2025-08-18 | DAL-TILE SUNNYVALE MANUFACTURING PLANT | FCE On-Site | State |
| 2025-07-22 | EXXON MOBIL IRVING TERMINAL | FCE On-Site | State |
| 2025-07-08 | FRITO LAY | FCE On-Site | State |
| 2025-07-07 | PRINTPACK | FCE On-Site | State |
| 2025-06-11 | WESTROCK CONVERTING DALLAS MILL | FCE On-Site | State |
| 2025-05-22 | MAGELLAN DISTRIBUTION FACILITY - DALLAS TERMINAL | FCE On-Site | State |
| 2025-04-30 | MCCOMMAS BLUFF LFG PROCESSING FACILITY | FCE On-Site | State |
| 2025-03-20 | TEXAS INSTRUMENTS NORTH CAMPUS | FCE On-Site | State |
| 2025-02-19 | MOUNTAIN CREEK STEAM ELECTRIC STATION | FCE On-Site | State |
| 2025-01-13 | AMERESCO BIOGAS ENERGY FACILITY | FCE On-Site | State |
| 2025-01-08 | REPKON USA DEFENSE GARLAND | FCE On-Site | State |
Dates as filed by the agency that recorded the inspection. Figures from EPA’s ICIS-AIR download.