COEUR ALASKA INC. / KENSINGTON MINE PROJECT, Juneau, AK: Clean Air Act compliance record, inspections, violations, penalties

COEUR ALASKA INC. / KENSINGTON MINE PROJECT is on EPA’s ICIS-AIR register at 45 MILES N OF JUNEAU, Juneau in Juneau City and Borough County, Alaska: operating status operating, emissions classification synthetic minor source, current violation status “No Violation Identified”. Juneau City and Borough County is on EPA’s Green Book list of areas that do not meet a national air quality standard.

What stands out

  • The newest of the 35 events on file is a compliance evaluation dated July 16, 2026.
  • Its events on file run from February 28, 2017 through July 16, 2026.
  • Of its 26 compliance evaluations on file, 2 are a full compliance evaluation.
  • The register holds 17 air-emissions sources in Juneau City and Borough County, Alaska.

Every line is computed by formula from the record’s stored figures; nothing is estimated.

Identity

Facility as filedCOEUR ALASKA INC. / KENSINGTON MINE PROJECT
ICIS-AIR IDAK0000000211000010
EPA facility registry ID110055091699
Operating statusOperating
Emissions classificationSynthetic minor source
Current violation status (HPV field)No Violation Identified
Address45 MILES N OF JUNEAU, Juneau, AK 99801
CountyJuneau City and Borough County
In a nonattainment countyYes (EPA Green Book)
Industry (NAICS)Mining and quarrying (NAICS 2122)
EPA region10

Programs and pollutants

The program, pollutant and Title V files are not loaded: what this page covers.

Compliance evaluations

DateWhat EPA recordedAgencyPrograms
July 16, 2026PCE Off-SiteStateTitle V Permits
February 11, 2026PCE Off-SiteStateTitle V Permits
July 28, 2025PCE Off-SiteStateTitle V Permits
February 18, 2025PCE Off-SiteStateTitle V Permits
August 22, 2024PCE Off-SiteStateTitle V Permits
March 29, 2024FCE On-SiteStateNew Source Review Permit Requirements; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards
March 29, 2024PCE Off-SiteStateTitle V Permits
October 23, 2023PCE Off-SiteStateTitle V Permits
September 14, 2023PCE Off-SiteStateTitle V Permits
February 28, 2023PCE Off-SiteStateTitle V Permits
August 2, 2022PCE Off-SiteU.S. EPA40 CFR Part 63 Area Sources; MACT Standards (40 CFR Part 63); New Source Performance Standards; Operating Permits
January 28, 2022PCE Off-SiteStateTitle V Permits
August 25, 2021PCE Off-SiteStateTitle V Permits
May 10, 2021PCE Off-SiteStateTitle V Permits
September 8, 2020PCE Off-SiteStateTitle V Permits
June 16, 2020PCE Off-SiteStateTitle V Permits
June 16, 2020PCE Off-SiteStateTitle V Permits
June 16, 2020PCE Off-SiteStateTitle V Permits
May 20, 2019PCE Off-SiteStateTitle V Permits
January 15, 2019FCE On-SiteStateNew Source Review Permit Requirements; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards
November 19, 2018PCE Off-SiteStateTitle V Permits
November 16, 2018PCE Off-SiteStateTitle V Permits
November 16, 2018PCE Off-SiteStateTitle V Permits
October 19, 2017PCE Off-SiteStateTitle V Permits
October 19, 2017PCE Off-SiteStateTitle V Permits
February 28, 2017PCE Off-SiteStateTitle V Permits

Violations

What high-priority and federally reportable violations mean.

DateWhat EPA recordedAgencyPrograms
August 21, 2020Earliest FRV determinationStateFederally-Enforceable State Operating Permit - Non Title V
October 5, 2019Earliest FRV determinationStateFederally-Enforceable State Operating Permit - Non Title V

Enforcement and penalties

0 of the formal enforcement actions carry a penalty filed above zero. How a penalty is shown.

Informal enforcement

DateWhat EPA recordedAgency
April 1, 2024Warning LetterState
September 8, 2020Warning LetterState
December 22, 2017Warning LetterState

Stack tests

DateWhat EPA recordedAgency
November 14, 2018PassState
November 14, 2018PassState
August 26, 2018N/AState
August 26, 2018N/AState

Watch COEUR ALASKA INC. / KENSINGTON MINE PROJECT

One source — $99/month

Billing

Privacy

Free from EPA: Detailed Facility Report, ECHO Notify (registry ID 110055091699).

Other air sources in Alaska beside COEUR ALASKA INC. / KENSINGTON MINE PROJECT

EPA ICIS-AIR download, loaded September 14, 2026.