COPPER VALLEY ELECTRIC ASSOCIATION / VALDEZ DIESEL POWER PLANT, Valdez, AK: Clean Air Act compliance record, inspections, violations, penalties

COPPER VALLEY ELECTRIC ASSOCIATION / VALDEZ DIESEL POWER PLANT is on EPA’s ICIS-AIR register at WEST EGAN DR, Valdez in Valdez-Cordova (CA) County, Alaska: operating status operating, emissions classification major source, current violation status “No Violation Identified”.

What stands out

  • The newest of the 30 events on file is a compliance evaluation dated October 7, 2026.
  • Its events on file run from February 7, 2017 through October 7, 2026.
  • Of its 26 compliance evaluations on file, 5 are a full compliance evaluation.
  • The register holds 15 air-emissions sources in Valdez-Cordova (CA) County, Alaska.

Every line is computed by formula from the record’s stored figures; nothing is estimated.

Identity

Facility as filedCOPPER VALLEY ELECTRIC ASSOCIATION / VALDEZ DIESEL POWER PLANT
ICIS-AIR IDAK0000000226100032
EPA facility registry ID110021283911
Operating statusOperating
Emissions classificationMajor source
Current violation status (HPV field)No Violation Identified
AddressWEST EGAN DR, Valdez, AK 99686
CountyValdez-Cordova (CA) County
In a nonattainment countyNo (EPA Green Book)
Industry (NAICS)Utilities (NAICS 2211)
EPA region10

Programs and pollutants

The program, pollutant and Title V files are not loaded: what this page covers.

Compliance evaluations

DateWhat EPA recordedAgencyPrograms
October 7, 2026PCE Off-SiteStateTitle V Permits
March 13, 2026PCE Off-SiteStateTitle V Permits
September 22, 2025PCE Off-SiteStateTitle V Permits
September 19, 2025FCE Off-SiteStateTitle V Permits
May 13, 2025PCE Off-SiteStateTitle V Permits
October 11, 2024PCE Off-SiteStateTitle V Permits
September 18, 2024PCE Off-SiteStateTitle V Permits
October 26, 2023PCE Off-SiteStateTitle V Permits
August 15, 2023FCE On-SiteStateTitle V Permits
March 30, 2023PCE Off-SiteStateTitle V Permits
October 20, 2022PCE Off-SiteStateTitle V Permits
March 11, 2022PCE Off-SiteStateTitle V Permits
October 21, 2021PCE Off-SiteStateTitle V Permits
October 21, 2021PCE Off-SiteStateTitle V Permits
May 24, 2021FCE Off-SiteState40 CFR Part 63 Area Sources; MACT Standards (40 CFR Part 63); National Emission Standards for Hazardous Air Pollutants (40 CFR Part 61); Title V Permits
March 11, 2021PCE Off-SiteStateTitle V Permits
October 5, 2020PCE Off-SiteStateTitle V Permits
March 23, 2020PCE Off-SiteStateTitle V Permits
August 29, 2019FCE Off-SiteStateTitle V Permits
August 23, 2019PCE Off-SiteStateTitle V Permits
January 30, 2019PCE Off-SiteStateTitle V Permits
August 2, 2018PCE Off-SiteStateTitle V Permits
February 22, 2018PCE Off-SiteStateTitle V Permits
December 21, 2017FCE On-SiteStateTitle V Permits
August 30, 2017PCE Off-SiteStateTitle V Permits
February 7, 2017PCE Off-SiteStateTitle V Permits

Violations

What high-priority and federally reportable violations mean.

DateWhat EPA recordedAgencyPrograms
August 17, 2023Earliest FRV determinationStateTitle V Permits
January 9, 2018Earliest FRV determinationStateTitle V Permits

Enforcement and penalties

0 of the formal enforcement actions carry a penalty filed above zero. How a penalty is shown.

Informal enforcement

DateWhat EPA recordedAgency
September 1, 2025Warning LetterState
January 9, 2018Warning LetterState

Stack tests

EPA’s stack test file holds no test at ICIS-AIR AK0000000226100032 since January 1, 2017.

Watch COPPER VALLEY ELECTRIC ASSOCIATION / VALDEZ DIESEL POWER PLANT

One source — $99/month

Billing

Privacy

Free from EPA: Detailed Facility Report, ECHO Notify (registry ID 110021283911).

Other air sources in Alaska beside COPPER VALLEY ELECTRIC ASSOCIATION / VALDEZ DIESEL POWER PLANT

EPA ICIS-AIR download, loaded September 14, 2026.