ALASKA ELECTRIC AND ENERGY COOPERATIVE / SOLDOTNA COMBUSTION TURBINE PLANT, Kenai, AK: Clean Air Act compliance record, inspections, violations, penalties

ALASKA ELECTRIC AND ENERGY COOPERATIVE / SOLDOTNA COMBUSTION TURBINE PLANT is on EPA’s ICIS-AIR register at MILE 21.5 SPUR HIGHWAY, Kenai in Kenai Peninsula County, Alaska: operating status operating, emissions classification major source, current violation status “No Violation Identified”.

What stands out

  • The newest of the 35 events on file is a compliance evaluation dated August 10, 2026.
  • Its events on file run from April 6, 2017 through August 10, 2026.
  • Of its 26 compliance evaluations on file, 5 are a full compliance evaluation.
  • The register holds 53 air-emissions sources in Kenai Peninsula County, Alaska.

Every line is computed by formula from the record’s stored figures; nothing is estimated.

Identity

Facility as filedALASKA ELECTRIC AND ENERGY COOPERATIVE / SOLDOTNA COMBUSTION TURBINE PLANT
ICIS-AIR IDAK0000000212200111
EPA facility registry ID110063697227
Operating statusOperating
Emissions classificationMajor source
Current violation status (HPV field)No Violation Identified
AddressMILE 21.5 SPUR HIGHWAY, Kenai, AK 99611
CountyKenai Peninsula County
In a nonattainment countyNo (EPA Green Book)
Industry (NAICS)Utilities (NAICS 2211)
EPA region10

Programs and pollutants

The program, pollutant and Title V files are not loaded: what this page covers.

Compliance evaluations

DateWhat EPA recordedAgencyPrograms
August 10, 2026PCE Off-SiteStateTitle V Permits
April 7, 2026PCE Off-SiteStateTitle V Permits
July 25, 2025FCE Off-SiteStateTitle V Permits
July 25, 2025PCE Off-SiteStateTitle V Permits
January 22, 2025PCE Off-SiteStateTitle V Permits
August 26, 2024PCE Off-SiteStateTitle V Permits
March 13, 2024PCE Off-SiteStateTitle V Permits
September 11, 2023FCE On-SiteStateTitle V Permits
August 2, 2023PCE Off-SiteStateTitle V Permits
February 8, 2023PCE Off-SiteStateTitle V Permits
November 10, 2022PCE Off-SiteStateTitle V Permits
February 7, 2022PCE Off-SiteStateTitle V Permits
February 4, 2022PCE Off-SiteStateTitle V Permits
August 24, 2021FCE Off-SiteStateTitle V Permits
August 20, 2021PCE Off-SiteStateTitle V Permits
July 27, 2021PCE Off-SiteStateTitle V Permits
October 29, 2020PCE Off-SiteStateTitle V Permits
May 4, 2020PCE Off-SiteStateTitle V Permits
December 16, 2019FCE On-SiteStateTitle V Permits
August 29, 2019PCE Off-SiteStateTitle V Permits
April 12, 2019PCE Off-SiteStateTitle V Permits
August 23, 2018PCE Off-SiteStateTitle V Permits
May 29, 2018PCE Off-SiteStateTitle V Permits
March 20, 2018FCE Off-SiteStateTitle V Permits
November 16, 2017PCE Off-SiteStateTitle V Permits
April 6, 2017PCE Off-SiteStateTitle V Permits

Violations

What high-priority and federally reportable violations mean.

DateWhat EPA recordedAgencyPrograms
September 12, 2023Earliest FRV determinationStateTitle V Permits
June 14, 2022Earliest FRV determinationStateTitle V Permits

Enforcement and penalties

0 of the formal enforcement actions carry a penalty filed above zero. How a penalty is shown.

Informal enforcement

DateWhat EPA recordedAgency
August 10, 2026Warning LetterState
September 19, 2023Warning LetterState
June 15, 2022Warning LetterState

Stack tests

DateWhat EPA recordedAgency
October 22, 2024PassState
November 3, 2022PassState
August 5, 2020PassState
August 14, 2018PassState

Watch ALASKA ELECTRIC AND ENERGY COOPERATIVE / SOLDOTNA COMBUSTION TURBINE PLANT

One source — $99/month

Billing

Privacy

Free from EPA: Detailed Facility Report, ECHO Notify (registry ID 110063697227).

Other air sources in Alaska beside ALASKA ELECTRIC AND ENERGY COOPERATIVE / SOLDOTNA COMBUSTION TURBINE PLANT

EPA ICIS-AIR download, loaded September 14, 2026.