ICIS-AIR AK0000000205000090

ALASKA VILLAGE ELECTRIC COOPERATIVE / UPPER KALSKAG POWER PLANT, Bethel, AK: Clean Air Act compliance record, inspections, violations, penalties

ALASKA VILLAGE ELECTRIC COOPERATIVE / UPPER KALSKAG POWER PLANT is on EPA’s ICIS-AIR register at 1 CITY OF KALSKAG, Bethel in Bethel (CA) County, Alaska: operating status operating, emissions classification synthetic minor source, current violation status “No Violation Identified”.

What stands out

  • The newest of the 12 events on file is a compliance evaluation dated February 3, 2026.
  • Its events on file run from February 8, 2017 through February 3, 2026.
  • Of its 12 compliance evaluations on file, 2 are a full compliance evaluation.
  • The register holds 21 air-emissions sources in Bethel (CA) County, Alaska.

Every line is computed by formula from the record’s stored figures; nothing is estimated.

Identity

Facility as filedALASKA VILLAGE ELECTRIC COOPERATIVE / UPPER KALSKAG POWER PLANT
ICIS-AIR IDAK0000000205000090
EPA facility registry ID110064072872
Operating statusOperating
Emissions classificationSynthetic minor source
Current violation status (HPV field)No Violation Identified
Address1 CITY OF KALSKAG, Bethel, AK 99607
CountyBethel (CA) County
In a nonattainment countyNo (EPA Green Book)
Industry (NAICS)Utilities (NAICS 2211)
EPA region10

Programs and pollutants

The program, pollutant and Title V files are not loaded: what this page covers.

Compliance evaluations

DateWhat EPA recordedAgencyPrograms
February 3, 2026PCE Off-SiteStateFederally-Enforceable State Operating Permit - Non Title V
February 3, 2025PCE Off-SiteStateFederally-Enforceable State Operating Permit - Non Title V
August 22, 2024FCE Off-SiteStateFederally-Enforceable State Operating Permit - Non Title V
March 14, 2024PCE Off-SiteStateFederally-Enforceable State Operating Permit - Non Title V
February 8, 2023PCE Off-SiteStateFederally-Enforceable State Operating Permit - Non Title V
February 16, 2022PCE Off-SiteStateFederally-Enforceable State Operating Permit - Non Title V
February 24, 2021PCE Off-SiteStateFederally-Enforceable State Operating Permit - Non Title V
April 27, 2020PCE Off-SiteStateFederally-Enforceable State Operating Permit - Non Title V
June 10, 2019FCE Off-SiteStateFederally-Enforceable State Operating Permit - Non Title V
February 12, 2019PCE Off-SiteStateFederally-Enforceable State Operating Permit - Non Title V
February 9, 2018PCE Off-SiteStateFederally-Enforceable State Operating Permit - Non Title V
February 8, 2017PCE Off-SiteStateFederally-Enforceable State Operating Permit - Non Title V

Violations

What high-priority and federally reportable violations mean.

EPA’s violation history file holds no violation for ICIS-AIR AK0000000205000090 since January 1, 2017.

Enforcement and penalties

0 of the formal enforcement actions carry a penalty filed above zero. How a penalty is shown.

Informal enforcement

EPA’s informal action file holds no notice or warning for ICIS-AIR AK0000000205000090 since January 1, 2017.

Stack tests

EPA’s stack test file holds no test at ICIS-AIR AK0000000205000090 since January 1, 2017.

Watch ALASKA VILLAGE ELECTRIC COOPERATIVE / UPPER KALSKAG POWER PLANT

One source — $99/month

Billing

Privacy

Free from EPA: Detailed Facility Report, ECHO Notify (registry ID 110064072872).

Other air sources in Alaska beside ALASKA VILLAGE ELECTRIC COOPERATIVE / UPPER KALSKAG POWER PLANT

EPA ICIS-AIR download, loaded September 14, 2026.