HILCORP ALASKA, LLC / CRUDE OIL TOPPING UNIT (COTU), North Slope Borough, AK: Clean Air Act compliance record, inspections, violations, penalties

HILCORP ALASKA, LLC / CRUDE OIL TOPPING UNIT (COTU) is on EPA’s ICIS-AIR register at EAST DOCK ROAD 1, North Slope Borough in North Slope County, Alaska: operating status operating, emissions classification major source, current violation status “No Violation Identified”.

What stands out

  • The newest of the 55 events on file is a compliance evaluation dated September 18, 2026.
  • Its events on file run from April 12, 2017 through September 18, 2026.
  • Of its 45 compliance evaluations on file, 6 are a full compliance evaluation.
  • The register holds 76 air-emissions sources in North Slope County, Alaska.

Every line is computed by formula from the record’s stored figures; nothing is estimated.

Identity

Facility as filedHILCORP ALASKA, LLC / CRUDE OIL TOPPING UNIT (COTU)
ICIS-AIR IDAK0000000218500086
EPA facility registry ID110067216079
Operating statusOperating
Emissions classificationMajor source
Current violation status (HPV field)No Violation Identified
AddressEAST DOCK ROAD 1, North Slope Borough, AK 99734
CountyNorth Slope County
In a nonattainment countyNo (EPA Green Book)
Industry (NAICS)Oil and gas extraction (NAICS 2111)
EPA region10

Programs and pollutants

The program, pollutant and Title V files are not loaded: what this page covers.

Compliance evaluations

DateWhat EPA recordedAgencyPrograms
September 18, 2026PCE Off-SiteStateTitle V Permits
September 16, 2026FCE On-SiteStateTitle V Permits
May 21, 2026PCE Off-SiteStateTitle V Permits
February 27, 2026PCE Off-SiteStateTitle V Permits
December 13, 2025PCE Off-SiteStateTitle V Permits
August 19, 2025PCE Off-SiteStateTitle V Permits
August 1, 2025PCE Off-SiteStateTitle V Permits
August 1, 2025PCE Off-SiteStateTitle V Permits
January 14, 2025PCE Off-SiteStateTitle V Permits
January 14, 2025PCE Off-SiteStateTitle V Permits
September 30, 2024FCE On-SiteStateTitle V Permits
August 13, 2024PCE Off-SiteStateTitle V Permits
August 13, 2024PCE Off-SiteStateTitle V Permits
June 28, 2024PCE Off-SiteStateTitle V Permits
November 22, 2023PCE Off-SiteStateTitle V Permits
July 11, 2023PCE Off-SiteStateTitle V Permits
May 5, 2023PCE Off-SiteStateTitle V Permits
January 3, 2023PCE Off-SiteStateTitle V Permits
September 20, 2022FCE On-SiteStateTitle V Permits
August 25, 2022PCE Off-SiteStateTitle V Permits
June 8, 2022PCE Off-SiteStateTitle V Permits
May 11, 2022PCE Off-SiteStateTitle V Permits
January 26, 2022PCE Off-SiteStateTitle V Permits
November 16, 2021PCE Off-SiteStateTitle V Permits
June 17, 2021PCE Off-SiteStateTitle V Permits
April 2, 2021PCE Off-SiteStateTitle V Permits
December 3, 2020FCE On-SiteStateTitle V Permits
December 1, 2020PCE Off-SiteStateTitle V Permits
October 22, 2020PCE Off-SiteStateTitle V Permits
June 12, 2020PCE Off-SiteStateTitle V Permits
May 18, 2020PCE Off-SiteStateTitle V Permits
December 23, 2019PCE Off-SiteStateTitle V Permits
November 19, 2019PCE Off-SiteStateTitle V Permits
July 24, 2019PCE Off-SiteStateTitle V Permits
March 13, 2019FCE On-SiteStateTitle V Permits
March 11, 2019PCE Off-SiteStateTitle V Permits
December 7, 2018PCE Off-SiteStateTitle V Permits
September 18, 2018PCE Off-SiteStateTitle V Permits
July 6, 2018PCE Off-SiteStateTitle V Permits
March 20, 2018PCE Off-SiteStateTitle V Permits
December 15, 2017PCE Off-SiteStateTitle V Permits
November 9, 2017PCE Off-SiteStateTitle V Permits
August 3, 2017PCE Off-SiteStateTitle V Permits
May 15, 2017FCE On-SiteStateTitle V Permits
April 12, 2017PCE Off-SiteStateTitle V Permits

Violations

What high-priority and federally reportable violations mean.

DateWhat EPA recordedAgencyPrograms
September 30, 2025Earliest FRV determinationStateTitle V Permits
October 16, 2024Earliest FRV determinationStateTitle V Permits
March 11, 2022Earliest FRV determinationStateTitle V Permits
April 22, 2019Earliest FRV determinationStateTitle V Permits

Enforcement and penalties

0 of the formal enforcement actions carry a penalty filed above zero. How a penalty is shown.

Informal enforcement

DateWhat EPA recordedAgency
November 25, 2024Warning LetterState
September 30, 2024Warning LetterState
September 20, 2022Warning LetterState
December 3, 2020Warning LetterState
March 12, 2019Warning LetterState
May 17, 2017Warning LetterState

Stack tests

EPA’s stack test file holds no test at ICIS-AIR AK0000000218500086 since January 1, 2017.

Watch HILCORP ALASKA, LLC / CRUDE OIL TOPPING UNIT (COTU)

One source — $99/month

Billing

Privacy

Free from EPA: Detailed Facility Report, ECHO Notify (registry ID 110067216079).

Other air sources in Alaska beside HILCORP ALASKA, LLC / CRUDE OIL TOPPING UNIT (COTU)

EPA ICIS-AIR download, loaded September 14, 2026.