GOLD BOND BUILDING PRODUCTS LLC, at 9720 US HWY 50, East Shoals in Martin County, Indiana, is an operating synthetic minor source of air pollution on EPA’s ICIS-AIR register. EPA’s file records its current violation status (ICIS-AIR’s high-priority violation field) as “Unaddressed-State”. The status and classification are as EPA’s facility file stood when Velarion loaded it (September 14, 2026); EPA’s free Detailed Facility Report on ECHO carries the source’s current standing, quarter by quarter.

Identity

Facility as filedGOLD BOND BUILDING PRODUCTS LLC
ICIS-AIR IDIN0000001810100003
EPA facility registry ID110040897269
Operating statusOperating
Emissions classificationSynthetic minor source
Current violation status (ICIS-AIR high-priority violation field)Unaddressed-State
Address9720 US HWY 50, East Shoals, IN 47581-7260
CountyMartin County
In a nonattainment countyNo (EPA Green Book)
Industry (NAICS)Nonmetallic mineral product manufacturing (NAICS 3274)
SIC code3275
EPA region05

Cited to the EPA ICIS-AIR facility file (ECHO download).

Programs and pollutants

Velarion’s copy of EPA’s ICIS-AIR download does not yet include its program, pollutant and Title V certification files, so this page does not list the Clean Air Act programs GOLD BOND BUILDING PRODUCTS LLC is under or the pollutants it is permitted for. The programs each evaluation and violation below was recorded under are shown with it. EPA’s free Detailed Facility Report lists both.

Compliance evaluations

DateWhat EPA recordedAgencyPrograms
June 25, 2026FCE On-SiteStateFederally-Enforceable State Operating Permit - Non Title V
March 11, 2025FCE On-SiteStateFederally-Enforceable State Operating Permit - Non Title V
December 9, 2021FCE On-SiteStateFederally-Enforceable State Operating Permit - Non Title V
June 8, 2018FCE On-SiteStateFederally-Enforceable State Operating Permit - Non Title V

Violations

A high-priority violation (HPV) is the most serious class of Clean Air Act non-compliance an agency records; a federally reportable violation (FRV) is the next step down. Each row is one determination as EPA’s violation history files it.

DateWhat EPA recordedAgencyPrograms
November 1, 2024Earliest FRV determinationStateFederally-Enforceable State Operating Permit - Non Title V
July 31, 2024Earliest FRV determinationStateFederally-Enforceable State Operating Permit - Non Title V
February 1, 2024Earliest FRV determinationStateFederally-Enforceable State Operating Permit - Non Title V
February 2, 2023HPV day-zero determinationStateFederally-Enforceable State Operating Permit - Non Title V
March 9, 2022HPV day-zero determinationStateFederally-Enforceable State Operating Permit - Non Title V
January 19, 2022Earliest FRV determinationStateFederally-Enforceable State Operating Permit - Non Title V
December 9, 2021Earliest FRV determinationStateFederally-Enforceable State Operating Permit - Non Title V
September 4, 2017HPV day-zero determinationStateFederally-Enforceable State Operating Permit - Non Title V

Enforcement and penalties

1 formal enforcement actions since January 1, 2017, 1 of them with a penalty filed above zero. Each penalty is shown as EPA’s formal action file states it; “Not stated” means the file gives no figure, and $0 is a disclosed zero.

DateWhat EPA recordedAgencyPenalty, as filed
January 23, 2025Administrative OrderState$2,400

Informal enforcement

DateWhat EPA recordedAgency
March 27, 2025Notice of ViolationState
February 17, 2025Notice of ViolationState
January 9, 2025Notice of ViolationState

Stack tests

DateWhat EPA recordedAgency
December 15, 2022PassState
December 14, 2022FailState
July 21, 2022FailState
July 21, 2022PassState
July 21, 2022FailState
July 21, 2022FailState
July 20, 2022FailState
July 19, 2022PassState
January 19, 2022PassState
January 19, 2022FailState
January 19, 2022PassState
January 19, 2022FailState
January 19, 2022FailState
January 19, 2022PassState
June 6, 2017FailState

Cited to the EPA ICIS-AIR evaluation, violation, stack test and enforcement files (ECHO download), events dated January 1, 2017 or later as loaded; up to 50 rows of each shown, newest first.

Watch this source

One source, $99/month. A source: the register entry for a plant, refinery, kiln, generating station, or other fixed installation the agency tracks under the Clean Air Act. Choose “One source” and enter this source’s ICIS-AIR ID, IN0000001810100003.

Start the watch

How often?
  • One source — $99/month
  • One county — $2,990/year
  • One state — $4,990/year
  • The whole register — $18,000/year

How we handle your data → Privacy

EPA publishes a free Detailed Facility Report for every source on ECHO: its compliance status quarter by quarter, its evaluations, and its violations, enforcement actions and penalties. EPA also sends free notices of new inspections and enforcement actions through ECHO Notify; enter EPA facility registry ID 110040897269 there.

Nearby on the register

Figures from EPA’s ICIS-AIR download, loaded September 14, 2026.