XCEL ENERGY - FRENCH ISLAND GENERATING PLANT, La Crosse, WI: Clean Air Act compliance record, inspections, violations, penalties

XCEL ENERGY - FRENCH ISLAND GENERATING PLANT is on EPA’s ICIS-AIR register at 200 BAINBRIDGE ST, La Crosse in La Crosse County, Wisconsin: operating status operating, emissions classification major source, current violation status “No Violation Identified”.

What stands out

  • The newest of the 65 events on file is a compliance evaluation dated October 23, 2026.
  • Its events on file run from February 21, 2017 through October 23, 2026.
  • Of its 15 compliance evaluations on file, 5 are a full compliance evaluation.
  • 6 of the 41 stack tests on file are recorded as failed.
  • 1 of the 6 violation determinations on file is high-priority.
  • The register holds 30 air-emissions sources in La Crosse County, Wisconsin.

Every line is computed by formula from the record’s stored figures; nothing is estimated.

Identity

Facility as filedXCEL ENERGY - FRENCH ISLAND GENERATING PLANT
ICIS-AIR IDWI0000005506300011
EPA facility registry ID110000422524
Operating statusOperating
Emissions classificationMajor source
Current violation status (HPV field)No Violation Identified
Address200 BAINBRIDGE ST, La Crosse, WI 546031564
CountyLa Crosse County
In a nonattainment countyNo (EPA Green Book)
Industry (NAICS)Utilities (NAICS 2211)
SIC code4911
EPA region05

Programs and pollutants

The program, pollutant and Title V files are not loaded: what this page covers.

Compliance evaluations

DateWhat EPA recordedAgencyPrograms
October 23, 2026PCE Off-SiteStateTitle V Permits
July 13, 2026PCE Off-SiteStateTitle V Permits
April 15, 2026PCE Off-SiteStateTitle V Permits
January 12, 2026PCE Off-SiteStateTitle V Permits
December 9, 2025PCE Off-SiteStateTitle V Permits
October 30, 2025PCE Off-SiteStateTitle V Permits
July 22, 2025FCE On-SiteStateTitle V Permits
July 9, 2025PCE Off-SiteStateTitle V Permits
April 28, 2025PCE Off-SiteStateTitle V Permits
February 4, 2025PCE Off-SiteStateTitle V Permits
October 21, 2024PCE Off-SiteStateTitle V Permits
November 10, 2022FCE On-SiteStateTitle V Permits
July 27, 2021FCE On-SiteStateTitle V Permits
June 2, 2019FCE On-SiteStateTitle V Permits
June 19, 2017FCE On-SiteStateTitle V Permits

Violations

What high-priority and federally reportable violations mean.

DateWhat EPA recordedAgencyPrograms
July 11, 2025Earliest FRV determinationStateTitle V Permits
July 11, 2025Earliest FRV determinationStateTitle V Permits
July 11, 2025Earliest FRV determinationStateTitle V Permits
July 7, 2023Earliest FRV determinationStateTitle V Permits
July 10, 2017HPV day-zero determinationStateTitle V Permits
April 26, 2017Earliest FRV determinationStateTitle V Permits

Enforcement and penalties

0 of the formal enforcement actions carry a penalty filed above zero. How a penalty is shown.

Informal enforcement

DateWhat EPA recordedAgency
October 30, 2025Notice of ViolationState
July 27, 2023Warning LetterState
August 30, 2017Notice of ViolationState

Stack tests

DateWhat EPA recordedAgency
April 7, 2026PassState
February 3, 2026PassState
November 11, 2025PassState
August 27, 2025PassState
June 3, 2025FailState
April 14, 2025FailState
March 12, 2025PassState
June 5, 2024PassState
April 15, 2024PassState
February 27, 2024PassState
August 24, 2023PassState
April 25, 2023PassState
April 18, 2023FailState
February 21, 2023PassState
April 12, 2022PassState
April 5, 2022PassState
February 16, 2022PassState
February 15, 2022PassState
April 12, 2021PassState
April 6, 2021PassState
February 16, 2021PassState
April 1, 2020PassState
March 31, 2020PassState
February 26, 2020PassState
February 25, 2020PassState
April 24, 2019PassState
April 23, 2019PassState
April 9, 2019PassState
February 20, 2019PassState
February 19, 2019PassState
April 26, 2018PassState
April 3, 2018PassState
March 7, 2018PassState
March 6, 2018PassState
November 22, 2017PassState
November 21, 2017PassState
July 6, 2017PassState
April 27, 2017FailState
April 24, 2017FailState
April 3, 2017FailState
February 21, 2017PassState

Watch XCEL ENERGY - FRENCH ISLAND GENERATING PLANT

One source — $99/month

Billing

Privacy

Free from EPA: Detailed Facility Report, ECHO Notify (registry ID 110000422524).

Other air sources in Wisconsin beside XCEL ENERGY - FRENCH ISLAND GENERATING PLANT

EPA ICIS-AIR download, loaded September 14, 2026.