Clean Air Act stationary source · ICIS-AIR WI0000005507322704

WISCONSIN ELECTRIC POWER COMPANY (DBA WE ENERGIES) - ROTHSCHILD BIOMASS COGENERA, Rothschild, WI: Clean Air Act compliance record, inspections, violations, penalties

WISCONSIN ELECTRIC POWER COMPANY (DBA WE ENERGIES) - ROTHSCHILD BIOMASS COGENERA, at 210 S GRAND AVE, Rothschild in Marathon County, Wisconsin, is an operating major source of air pollution on EPA’s ICIS-AIR register. EPA’s file records its current violation status (ICIS-AIR’s high-priority violation field) as “Unaddressed-State”. Marathon County is on EPA’s Green Book list of areas that do not meet a national air quality standard. The status and classification are as EPA’s facility file stood when Velarion loaded it (September 14, 2026); EPA’s free Detailed Facility Report on ECHO carries the source’s current standing, quarter by quarter.

Identity

Facility as filedWISCONSIN ELECTRIC POWER COMPANY (DBA WE ENERGIES) - ROTHSCHILD BIOMASS COGENERA
ICIS-AIR IDWI0000005507322704
EPA facility registry ID110054628729
Operating statusOperating
Emissions classificationMajor source
Current violation status (ICIS-AIR high-priority violation field)Unaddressed-State
Address210 S GRAND AVE, Rothschild, WI 54474
CountyMarathon County
In a nonattainment countyYes (EPA Green Book)
Industry (NAICS)Utilities (NAICS 2211)
SIC code4911
EPA region05

Cited to the EPA ICIS-AIR facility file (ECHO download).

Programs and pollutants

Velarion’s copy of EPA’s ICIS-AIR download does not include its program, pollutant and Title V certification files, so this page does not list the Clean Air Act programs WISCONSIN ELECTRIC POWER COMPANY (DBA WE ENERGIES) - ROTHSCHILD BIOMASS COGENERA is under or the pollutants it is permitted for. The programs each evaluation and violation below was recorded under are shown with it. EPA’s free Detailed Facility Report lists both.

Compliance evaluations

DateWhat EPA recordedAgencyPrograms
August 3, 2026PCE Off-SiteStateTitle V Permits
August 3, 2026PCE Off-SiteStateTitle V Permits
March 31, 2026FCE On-SiteStateTitle V Permits
March 29, 2026PCE Off-SiteStateTitle V Permits
February 27, 2026PCE Off-SiteStateTitle V Permits
February 23, 2026PCE Off-SiteStateTitle V Permits
January 30, 2026PCE Off-SiteStateTitle V Permits
October 31, 2025PCE Off-SiteStateTitle V Permits
October 28, 2025PCE Off-SiteStateTitle V Permits
April 29, 2025PCE Off-SiteStateTitle V Permits
February 24, 2025PCE Off-SiteStateTitle V Permits
February 5, 2025PCE Off-SiteStateTitle V Permits
January 29, 2025PCE Off-SiteStateTitle V Permits
January 29, 2025PCE Off-SiteStateTitle V Permits
December 31, 2024PCE Off-SiteStatePrevention of Significant Deterioration of Air Quality
October 30, 2024PCE Off-SiteStateTitle V Permits
October 23, 2023FCE On-SiteStateTitle V Permits
August 4, 2022FCE On-SiteStateTitle V Permits
October 26, 2021PCE Off-SiteStatePrevention of Significant Deterioration of Air Quality; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards
January 21, 2020FCE On-SiteStateTitle V Permits
July 12, 2018PCE Off-SiteStateMACT Standards (40 CFR Part 63); Prevention of Significant Deterioration of Air Quality
January 18, 2018FCE On-SiteStateTitle V Permits
October 27, 2017PCE Off-SiteStatePrevention of Significant Deterioration of Air Quality

Violations

A high-priority violation (HPV) is the most serious class of Clean Air Act non-compliance an agency records; a federally reportable violation (FRV) is the next step down. Each row is one determination as EPA’s violation history files it.

DateWhat EPA recordedAgencyPrograms
January 14, 2025HPV day-zero determinationStatePrevention of Significant Deterioration of Air Quality
January 14, 2025HPV day-zero determinationStatePrevention of Significant Deterioration of Air Quality
September 19, 2023Earliest FRV determinationStatePrevention of Significant Deterioration of Air Quality; State Implementation Plan for National Primary and Secondary Ambient Air Quality Standards
September 19, 2023Earliest FRV determinationStatePrevention of Significant Deterioration of Air Quality
September 19, 2023Earliest FRV determinationStateState Implementation Plan for National Primary and Secondary Ambient Air Quality Standards
October 27, 2021Earliest FRV determinationStateState Implementation Plan for National Primary and Secondary Ambient Air Quality Standards
January 21, 2020HPV day-zero determinationStateMACT Standards (40 CFR Part 63)
January 21, 2020HPV day-zero determinationStateMACT Standards (40 CFR Part 63); Title V Permits
January 14, 2020Earliest FRV determinationStateMACT Standards (40 CFR Part 63)
December 10, 2019Earliest FRV determinationStateMACT Standards (40 CFR Part 63); Title V Permits
July 12, 2018Earliest FRV determinationStatePrevention of Significant Deterioration of Air Quality
October 27, 2017Earliest FRV determinationStatePrevention of Significant Deterioration of Air Quality

Enforcement and penalties

0 formal enforcement actions since January 1, 2017, 0 of them with a penalty filed above zero. Each penalty is shown as EPA’s formal action file states it; “Not stated” means the file gives no figure, and $0 is a disclosed zero.

Informal enforcement

DateWhat EPA recordedAgency
January 21, 2025Warning LetterState
December 1, 2023Warning LetterState
November 1, 2021Warning LetterState
March 5, 2020Notice of ViolationState
February 4, 2020Notice of ViolationState
July 25, 2018Warning LetterState
November 7, 2017Warning LetterState

Stack tests

DateWhat EPA recordedAgency
June 9, 2026PassState
September 30, 2025PassState
August 12, 2025PassState
October 28, 2024PassState
October 8, 2024PassState
August 13, 2024PassState
June 3, 2024PassState
September 19, 2023PassState
August 15, 2023PassState
June 6, 2023PassState
September 6, 2022PassState
August 18, 2022PassState
September 14, 2021PassState
August 17, 2021PassState
May 7, 2020PassState
October 29, 2019PassState
September 10, 2019PassState
August 8, 2019PassState
September 11, 2018PassState
July 31, 2018PassState
January 24, 2018PassState
August 14, 2017PassState
July 10, 2017PassState

Cited to the EPA ICIS-AIR evaluation, violation, stack test and enforcement files (ECHO download), events dated January 1, 2017 or later as loaded; up to 50 rows of each shown, newest first.

Watch this source

One source, $99/month. A source: the register entry for a plant, refinery, kiln, generating station, or other fixed installation the agency tracks under the Clean Air Act. Choose “One source” and enter this source’s ICIS-AIR ID, WI0000005507322704.

Start the watch

How often?
  • One source — $99/month
  • One county — $2,990/year
  • One state — $4,990/year
  • The whole register — $18,000/year

How we handle your data → Privacy

EPA publishes a free Detailed Facility Report for every source on ECHO: its compliance status quarter by quarter, its evaluations, and its violations, enforcement actions and penalties. EPA also sends free notices of new inspections and enforcement actions through ECHO Notify; enter EPA facility registry ID 110054628729 there.

Nearby on the register

Figures from EPA’s ICIS-AIR download, loaded September 14, 2026.