Utilities (NAICS 2211): stack tests in Missouri, 2019
- 131Stack tests
A stack test measures what a source actually emits, at the stack, against the limit in its permit. Each row is one stack test recorded during 2019 at a Missouri source whose primary industry code is NAICS 2211. A facility filing more than one industry code is counted under the first one on its record.
Utilities (NAICS 2211) in Missouri, other years
Other industries in Missouri, 2019
- Nonmetallic mineral product manufacturing (NAICS 3273) 47
- Mining and quarrying (NAICS 2123) 37
- Primary metal manufacturing (NAICS 3314) 29
- Nonmetallic mineral product manufacturing (NAICS 3279) 20
- Primary metal manufacturing (NAICS 3313) 18
- Food manufacturing (NAICS 3112) 15
- Chemical manufacturing (NAICS 3253) 15
- Utilities (NAICS 2213) 15
- Nonmetallic mineral product manufacturing (NAICS 3274) 11
- Pipeline transportation (NAICS 4862) 10
- Chemical manufacturing (NAICS 3251) 8
- Nonmetallic mineral product manufacturing (NAICS 3272) 7
- Primary metal manufacturing (NAICS 3315) 6
- Paper manufacturing (NAICS 3222) 6
- Transportation equipment manufacturing (NAICS 3361) 5
- Plastics and rubber products manufacturing (NAICS 3261) 5
- Merchant wholesalers, nondurable goods (NAICS 4247) 4
- Beverage and tobacco manufacturing (NAICS 3121) 3
- Petroleum and coal products manufacturing (NAICS 3241) 3
- Educational services (NAICS 6113) 3
- Printing and related support (NAICS 3231) 3
Air-emissions stack tests recorded in Missouri, 2019
| Date | Facility | Where | Kind | Agency |
|---|---|---|---|---|
| 2019-05-20 | THOMAS HILL ENERGY CENTER - POWER DIVISION | CLIFTON HILL, Randolph, MO | Pending | State |
| 2019-05-18 | EVERGY-HAWTHORN GENERATING STATION | KANSAS CITY, Jackson, MO | Pending | State |
| 2019-05-08 | NEW MADRID POWER PLANT-ASSOC ELEC COOP | MARSTON, New Madrid, MO | Pending | State |
| 2019-05-07 | NEW MADRID POWER PLANT-ASSOC ELEC COOP | MARSTON, New Madrid, MO | Pending | State |
| 2019-04-16 | EVERGY INC -IATAN GENERATING STATION | WESTON, Platte, MO | Pass | State |
| 2019-04-15 | BLACK OAK POWER PRODUCERS LLC | HARTVILLE, Wright, MO | Pending | State |
| 2019-04-15 | BLACK OAK POWER PRODUCERS LLC | HARTVILLE, Wright, MO | Pending | State |
| 2019-04-11 | AMERESCO JEFFERSON CITY LLC | JEFFERSON CITY, Cole, MO | Pending | State |
| 2019-04-10 | AMERESCO JEFFERSON CITY LLC | JEFFERSON CITY, Cole, MO | Pending | State |
| 2019-04-10 | AMERESCO JEFFERSON CITY LLC | JEFFERSON CITY, Cole, MO | Pending | State |
| 2019-03-14 | SIKESTON POWER STATION | SIKESTON, Scott, MO | Pending | State |
| 2019-03-12 | THOMAS HILL ENERGY CENTER - POWER DIVISION | CLIFTON HILL, Randolph, MO | Pending | State |
| 2019-03-07 | THOMAS HILL ENERGY CENTER - POWER DIVISION | CLIFTON HILL, Randolph, MO | Pending | State |
| 2019-03-06 | THOMAS HILL ENERGY CENTER - POWER DIVISION | CLIFTON HILL, Randolph, MO | Pending | State |
| 2019-03-01 | EVERGY INC -IATAN GENERATING STATION | WESTON, Platte, MO | Pending | State |
| 2019-02-05 | EVERGY-HAWTHORN GENERATING STATION | KANSAS CITY, Jackson, MO | Pending | State |
| 2019-02-01 | CITY UTILITIES OF SPRINGFIELD MISSOURI JOHN TWITTY ENERGY CENTER — high-priority violation on file | SPRINGFIELD, Greene, MO | Pending | State |
| 2019-01-31 | CITY UTILITIES OF SPRINGFIELD MISSOURI JOHN TWITTY ENERGY CENTER — high-priority violation on file | SPRINGFIELD, Greene, MO | Fail | State |
| 2019-01-31 | CITY UTILITIES OF SPRINGFIELD MISSOURI JOHN TWITTY ENERGY CENTER — high-priority violation on file | SPRINGFIELD, Greene, MO | Pending | State |
| 2019-01-29 | CITY UTILITIES OF SPRINGFIELD MISSOURI JOHN TWITTY ENERGY CENTER — high-priority violation on file | SPRINGFIELD, Greene, MO | Pending | State |
| 2019-01-24 | EVERGY INC -IATAN GENERATING STATION | WESTON, Platte, MO | Fail | State |
| 2019-01-24 | EVERGY INC -IATAN GENERATING STATION | WESTON, Platte, MO | Pending | State |
| 2019-01-23 | COLUMBIA ENERGY CENTER | COLUMBIA, Boone, MO | Pass | State |
| 2019-01-23 | COLUMBIA ENERGY CENTER | COLUMBIA, Boone, MO | Pass | State |
| 2019-01-23 | COLUMBIA ENERGY CENTER | COLUMBIA, Boone, MO | Pass | State |
| 2019-01-23 | EVERGY INC -IATAN GENERATING STATION | WESTON, Platte, MO | Pending | State |
| 2019-01-23 | EVERGY INC -IATAN GENERATING STATION | WESTON, Platte, MO | Pending | State |
| 2019-01-16 | EVERGY INC -IATAN GENERATING STATION | WESTON, Platte, MO | Pending | State |
| 2019-01-15 | EVERGY INC -IATAN GENERATING STATION | WESTON, Platte, MO | Pending | State |
| 2019-01-09 | NEW MADRID POWER PLANT-ASSOC ELEC COOP | MARSTON, New Madrid, MO | Pending | State |
| 2019-01-08 | NEW MADRID POWER PLANT-ASSOC ELEC COOP | MARSTON, New Madrid, MO | Pending | State |