NPDES AKR10H04F · Clean Water Act
NAVIGATION CENTER MOA, Anchorage, AK: NPDES AKR10H04F discharge permit, effluent exceedances, inspections, penalties
NAVIGATION CENTER MOA, Anchorage, Alaska: General permit coverage AKR10H04F, held by Shay Throop; Construction stormwater; Effective; issued July 6, 2023, term to January 31, 2026, by Alaska Department of Environmental Conservation.
Alaska holds 1,371 Construction stormwater coverages of this permit type in EPA’s file; 434 were issued before AKR10H04F. Shay Throop holds 3 permits in Alaska.
Other permits held by Shay Throop
- ZODIAK MANOR DRAINAGE IMPROVEMENT PROJECT, Anchorage: AKR10GN60, issued 2023-08-11
- CRAWFORD ST & TERRY ST DRAINAGE IMPROVEMENTS, Anchorage: AKR10H0XC, issued 2025-12-03
Coverages issued nearest AKR10H04F
- 2023-06-23: HN2325 2023-2025 MAINTENANCE DREDGING HOMER&NINILCHIK, Homer: AKR10H06M, held by James Sauceda
- 2023-06-23: COSTCO #10 - DIMOND, Anchorage: AKR10H0AM, held by Mostafa Ahanchi
- 2023-06-28: GLENN PARKS INTERCHANGE REPAIRS NOV 2018 EQ PR, Palmer: AKR10GO51, held by John Binder
- 2023-06-28: MULDOON ROAD - DEBARR RD TO E 36TH AVE PAVEMENT PRESERVATION, Anchorage: AKR10H04K, held by John Binder
- 2023-06-30: SELAWIK BARGE LANDING ACCESS ROAD & BOARDWALK IMPROVEMENTS, Selawik: AKR10H0AY, held by Joseph P. Kemp, P.E.
- 2023-07-06: FUNNY RIVER RD. & COHOE LOOP RD. PAVEMENT PRESERVATION, Soldotna: AKR10H089, held by Troy Gray
- 2023-07-06: BEACH ROAD REPAIRS, Haines: AKR10H0B1, held by Roger Schnabel
- 2023-07-07: KENAI LAKE WORK CENTER: WATER AND WASTEWATER SYSTEM IMPROVEMENTS, Seward: AKR10H0B6, held by Royce Drennon
- 2023-07-07: BEACH ROAD REPAIRS, Haines: AKR10H0B8, held by Ed Coffland
- 2023-07-07: AK NPS KATM 10(4) REHABILITATE VALLEY OF 10K SMOKES RD PHASE IV, King Salmon: AKR10H0BB, held by David Lax
NAVIGATION CENTER MOA among its neighbors
78 discharge permits are in the Chester Creek subwatershed (HUC 190204010806); AKR10H04F is one. Its county: 555, 4 major; AKR10H04F is minor permit.
Other permits in the Chester Creek subwatershed (HUC 190204010806)
- 2024 MERRILL FIELD AIRPORT IMPROVEMENTS, REHABILITATE R/W 07/25, Anchorage: AKR10H0TH, minor, term to 2026-01-31
- 2024 MERRILL FIELD AIRPORT IMPROVEMENTS, REHABILITATE R/W 07/25, Anchorage: AKR10H0U4, minor, term to 2026-01-31
- 42ND AVE UPGRADES - PHASE 1 LAKE OTIS PARKWAY TO PIPER STREET, Anchorage: AKG002370, minor, term to 2030-08-31
- 42ND AVE UPGRADES - PHASE 1 LAKE OTIS PARKWAY TO PIPER STREET, Anchorage: AKR10H0P4, minor, term to 2026-01-31
- 42ND AVE UPGRADES - PHASE 1 LAKE OTIS PARKWAY TO PIPER STREET, Anchorage: AKR10H0P5, minor, term to 2026-01-31
- 42ND AVE UPGRADES - PHASE 1 LAKE OTIS PARKWAY TO PIPER STREET, Anchorage: AKR10H10T, minor, term to 2031-01-31
- AIRPORT HEIGHTS PHASE 1, Anchorage: AKR10H13G, minor, term to 2031-01-31
- ALASKA DOT AND PUBLIC FACILITIES (ADOT & PF), Anchorage: AKR10C833
- ALASKA NATIVE MEDICAL CENTER, Anchorage: AKG250005, minor, term to 2025-08-31
- AMATS BOUNDARY AVENUE BONIFACE TO OKLAHOMA, Anchorage: AKR10GQ07, minor, term to 2026-01-31
What stands out
- Its term runs 2 years and 209 days, July 6, 2023 to January 31, 2026; the term ended 227 days before EPA's file was loaded on September 15, 2026, and the file lists the permit as effective.
- No dated event in the 365 days to September 15, 2026.
- It is one of 3,110 discharge permits on the register in Alaska; 1,373 of them (44%) are in its program, Construction stormwater, and it is a minor discharger.
Identity
| Facility | NAVIGATION CENTER MOA |
|---|---|
| Permittee | Shay Throop |
| NPDES ID | AKR10H04F |
| Status | Effective |
| Type | General permit coverage |
| Class | Minor |
| Facility type | Non-POTW |
| Program | Construction stormwater |
| Issued | July 6, 2023 |
| Expires | January 31, 2026 |
| Agency | Alaska Department of Environmental Conservation |
| Address | Anchorage, AK 99507 |
| Subwatershed | Chester Creek (HUC 190204010806) |
NPDES AKR10H04F: effluent limits and exceedances
NAVIGATION CENTER MOA (NPDES AKR10H04F): 0 pollutants on file, 0 limited; 0 with a violation of any kind, 0 with an exceedance.
NPDES AKR10H04F: no pollutant row on file.
NPDES AKR10H04F: inspections, violations and enforcement
NPDES AKR10H04F (NAVIGATION CENTER MOA): no single-event violation, inspection, formal enforcement action and informal enforcement action on file.
Watch NPDES AKR10H04F
NPDES AKR10H04F: one email when its EPA record changes — $99/month.
Permits near NPDES AKR10H04F
NPDES AKR10H04F: 0 pollutant rows, 0 dated events; ICIS-NPDES download, loaded September 15, 2026.