NPDES ALR10C4K2 · Clean Water Act
THE LAND, Saraland, AL: NPDES ALR10C4K2 discharge permit, effluent exceedances, inspections, penalties
THE LAND, Saraland, Alabama: General permit coverage ALR10C4K2, held by City of Saraland; Construction stormwater; Administratively continued; issued November 14, 2023, term to March 31, 2026, by State.
- January 8, 2026: State Administrative Order of Consent (State), $30,900 state or local penalty.
- May 7, 2025: Failure to properly operate or maintain construction stormwater controls (ST6).
Alabama holds 7,857 Construction stormwater coverages of this permit type in EPA’s file; 4,493 were issued before ALR10C4K2. City of Saraland holds 3 permits in Alabama.
Other permits held by City of Saraland
- CITY OF SARALAND MS4 PH II, Saraland: ALR040045, issued 2016-09-06
- CRAIG DRIVE, Saraland: ALR10C1N8, issued 2021-11-15
Coverages issued nearest ALR10C4K2
- 2023-11-13: WEST FRASER EWP HUGULEY, Lanett: ALR10C4JT, held by West Fraser
- 2023-11-13: TUCKER PRITCHETT JACKSONVILLE, Jacksonville: ALR10C4JY, held by Tucker Pritchett
- 2023-11-13: FLORENCE MULTI-PURPOSE FIELD, Florence: ALR10C4K0, held by Roberts Builders Inc.
- 2023-11-14: MARTINSON RANCH, Huntsville: ALR10C4JA, held by McKinley Homes US LLC
- 2023-11-14: WATERCRESS, Athens: ALR10C4K1, held by North Alabama Communities, LLC
- 2023-11-14: MALVERN HILL, Madison: ALR10C4K5, held by DSLD Homes Gulf Coast, LLC
- 2023-11-14: COMMUNICATION LINE INSTALL - AT&T PROJECT #A02MLOG, Seale: ALR10C4K7, held by BellSouth Telecommunications, LLC dba AT&T Alabama
- 2023-11-14: DIXIE DRIVE APARTMENTS, Enterprise: ALR10C4K8, held by Pecan Grove Development, LLC
- 2023-11-14: DR MARK TURK, OD - BOAZ, AL, Boaz: ALR10C4K9, held by Double Dragon Development, LLC
- 2023-11-15: TVA MUSCLE SHOALS COMPLEX D, Muscle Shoals: ALR10C4KF, held by Tennessee Valley Authority
THE LAND among its neighbors
49 discharge permits are in the Bayou Sara subwatershed (HUC 031602040402); ALR10C4K2 is one. Its county: 1,120, 18 major; ALR10C4K2 is minor permit.
Other permits in the Bayou Sara subwatershed (HUC 031602040402)
- 527 SARALAND DEVELOPMENT, Saraland: ALR10C3CK, minor, term to 2026-03-31
- 637 BAKER RD, Satsuma: ALR10C2PC, minor, term to 2026-03-31
- AARON OIL COMPANY LLC, Saraland: ALNE00255, minor, term to 2029-03-03
- AGAPE MINISTRIES, Saraland: ALR109229, minor, term to 2016-03-31
- ALLEN - ROLLING HILLS ESTATES, Saraland: ALR10C7DW, minor, term to 2026-03-31
- BEAR RUN NORTH, Saraland: ALR10C74B, minor, term to 2026-03-31
- BEAR RUN PHASE 2A, Saraland: ALR10C52C, minor, term to 2026-03-31
- BEAR RUN PHASE 2B BY LOG CONSTRUCTION, LLC, Saraland: ALR10C7XY, minor, term to 2031-03-31
- BEAR RUN SUBDIVISION, Saraland: ALR10C71K, minor, term to 2026-03-31
- BOUTWELL - ELYSIAN FIELDS PHASE 3, Saraland: ALR10C5UP, minor, term to 2026-03-31
What stands out
- Its term runs 2 years and 137 days, November 14, 2023 to March 31, 2026; the term ended 168 days before EPA's file was loaded on September 15, 2026, and the file lists the permit as administratively continued.
- Its newest dated event on file is a formal enforcement action on January 8, 2026, 250 days before EPA's file was loaded.
- In the 365 days to September 15, 2026, it was dated 1 formal enforcement action.
- EPA's file dates 2 events for it, from 2025 to 2026.
- It is one of 13,475 discharge permits on the register in Alabama; 7,857 of them (58%) are in its program, Construction stormwater, and it is a minor discharger.
Identity
| Facility | THE LAND |
|---|---|
| Permittee | City of Saraland |
| NPDES ID | ALR10C4K2 |
| Status | Administratively continued |
| Type | General permit coverage |
| Class | Minor |
| Facility type | Non-POTW |
| Program | Construction stormwater |
| Issued | November 14, 2023 |
| Expires | March 31, 2026 |
| Agency | State |
| Address | Saraland, AL 36571 |
| Subwatershed | Bayou Sara (HUC 031602040402) |
NPDES ALR10C4K2: effluent limits and exceedances
THE LAND (NPDES ALR10C4K2): 0 pollutants on file, 0 limited; 0 with a violation of any kind, 0 with an exceedance.
NPDES ALR10C4K2: no pollutant row on file.
NPDES ALR10C4K2: inspections, violations and enforcement
NPDES ALR10C4K2: 1 single-event violation
| Date | What EPA recorded | Agency |
|---|---|---|
| May 7, 2025 | Failure to properly operate or maintain construction stormwater controls | ST6 |
NPDES ALR10C4K2: 1 formal enforcement action
1 of them with a penalty assessed. How penalties are shown.
| Date | What EPA recorded | Agency | Federal penalty | State or local penalty |
|---|---|---|---|---|
| January 8, 2026 | State Administrative Order of Consent | State | $30,900 |
NPDES ALR10C4K2 (THE LAND): no inspection and informal enforcement action on file.
Watch NPDES ALR10C4K2
NPDES ALR10C4K2: one email when its EPA record changes — $99/month.
Permits near NPDES ALR10C4K2
NPDES ALR10C4K2: 0 pollutant rows, 2 dated events; ICIS-NPDES download, loaded September 15, 2026.