Clean Water Act discharge permit · NPDES FL0000132
DUKE ENERGY FLORIDA - BARTOW PLANT, St Petersburg, FL: NPDES FL0000132 discharge permit, effluent exceedances, inspections, penalties
- Administratively continuedPermit status
- MajorDischarger class
- 17Pollutants under a numeric limit
- 1Pollutants with an effluent exceedance
- 0Inspections on file
- 0Formal enforcement actions
DUKE ENERGY FLORIDA - BARTOW PLANT, held by Duke Energy Florida, LLC, holds NPDES permit FL0000132, which discharges to Tampa Bay Wbid 1656 Class Ii. EPA’s file records it issued January 5, 2016 and expiring February 3, 2021. The status and dates are as EPA’s permit file stood when Velarion loaded it (October 14, 2026); EPA’s free Detailed Facility Report on ECHO carries the permit’s current standing.
What stands out
- Its term runs 5 years and 29 days, January 5, 2016 to February 3, 2021; the term ended 2,079 days before EPA's file was loaded on October 14, 2026, and the file lists the permit as administratively continued.
- Its newest dated event on file is a single-event violation on July 1, 2026, 105 days before EPA's file was loaded.
- In the 365 days to October 14, 2026, it was dated 2 single-event violations.
- EPA's file dates 5 events for it, from 2022 to 2026; the busiest year is 2026 with 2.
- 1 of its 18 pollutants on file has an effluent exceedance (5.6%); 17 are under a numeric limit.
- It is one of 23,564 discharge permits on the register in Florida; the file names no program for it, and it is a major discharger.
Identity
| Facility as filed | DUKE ENERGY FLORIDA - BARTOW PLANT |
|---|---|
| Permittee as filed | Duke Energy Florida, LLC |
| NPDES ID | FL0000132 |
| Permit status | Administratively continued (past its expiration date and still in force until reissued) |
| Permit type | Individual permit |
| Discharger class | Major discharger |
| Facility type | Not a publicly owned treatment works |
| Issued | January 5, 2016 |
| Expiration date | February 3, 2021 |
| Issuing agency | Florida Department of Environmental Protection |
| Address | St Petersburg, FL 33702 |
| Receiving water | Tampa Bay WBID 1656 Class II |
| Subwatershed | Grand Bayou (HUC 031002060603) |
| NAICS | 221111 – Hydroelectric Power Generation |
| SIC | 4911 – Electric Services |
| Other EPA IDs (FRS) | RCRA handler FLD044014413; ICIS-AIR source FL0000001210300011 |
Cited to the EPA ICIS-NPDES permit file (ECHO download) and EPA’s NAICS/SIC and component files, the same download; cross-program IDs from EPA’s FRS facility-registry crosswalk.
Effluent limits and exceedances
- 18Pollutants on file
- 17Under a numeric limit
- 18With a violation of any kind
- 1With an effluent exceedance
An effluent exceedance is a discharge monitoring report value over the permit’s numeric limit (EPA’s violation code E90). A violation of any kind also counts a report not filed. Each row is EPA’s own count for that pollutant.
| Pollutant or measure | Limits | Violations, any kind | Effluent exceedances | Latest exceedance | Largest exceedance, as filed |
|---|---|---|---|---|---|
| pH | 5 | 11 | 1 | May 31, 2010 | |
| Temperature, water deg. fahrenheit | 4 | 10 | 0 | ||
| IC25 Static Renewal 7 Day Chronic Americamysis bahia (formerly Mysidopsis bahia) | 3 | 9 | 0 | ||
| IC25 Static Renewal 7 Day Chronic Menidia menidia | 3 | 9 | 0 | ||
| Turbidity | 8 | 8 | 0 | ||
| Nitrogen, total [as N] | 6 | 6 | 0 | ||
| Flow, in conduit or thru treatment plant | 4 | 5 | 0 | ||
| Temp. diff. between intake and discharge | 2 | 5 | 0 | ||
| Temperature, water deg. centigrade | 2 | 2 | 0 | ||
| Solids, total suspended | 2 | 2 | 0 | ||
| Oil & Grease | 2 | 2 | 0 | ||
| Nitrogen, ammonia total [as N] | 2 | 2 | 0 | ||
| Ammonia, unionized | 2 | 2 | 0 | ||
| Nitrogen, Kjeldahl, total [as N] | 2 | 2 | 0 | ||
| Nitrite + Nitrate total [as N] | 2 | 2 | 0 | ||
| Phosphate, ortho [as PO4] | 2 | 2 | 0 | ||
| Phosphorus, total [as P] | 2 | 2 | 0 | ||
| Iron, total recoverable | 0 | 1 | 0 |
Cited to the EPA ICIS-NPDES limits and effluent violations files (ECHO download); up to 60 rows shown, most exceedances first.
Inspections, violations and enforcement
- 5Single-event violations
| Date | What EPA recorded | Agency |
|---|---|---|
| July 1, 2026 | Effluent Violations - Industrial Spill | ST6 |
| March 9, 2026 | Effluent Violations - Industrial Spill | ST6 |
| April 17, 2024 | Effluent Violations - Industrial Spill | ST6 |
| March 28, 2023 | WW SSO - Overflow to Dry Land or Building Backup | ST6 |
| September 13, 2022 | WW SSO - Overflow to Dry Land or Building Backup | ST6 |
Inspections
EPA’s inspection file holds no inspection for NPDES FL0000132.
Formal enforcement and penalties
0 formal actions, 0 of them with a penalty assessed. Federal and state penalties are separate figures from separate authorities and are shown as each was filed, never added together.
Informal enforcement
EPA’s informal enforcement file holds no action for NPDES FL0000132.
Cited to the EPA ICIS-NPDES violation, inspection and enforcement files (ECHO download); up to 50 rows of each shown, newest first.
Watch this permit
One permit holder, $99/month. Watch the register for one permit holder and the places and receiving waters tied to its permits. Choose “One permit holder” and enter this permit’s NPDES ID, FL0000132.
Start the watch
- One permit holder — $99/month
- One watershed — $2,990/year
- One state — $4,990/year
- The whole register — $18,000/year
How we handle your data → Privacy
EPA publishes a free Detailed Facility Report for every permit on ECHO: its compliance status quarter by quarter, its inspections, and its enforcement actions and penalties. EPA also sends free notices of new inspections and enforcement actions through ECHO Notify; enter NPDES ID FL0000132 there.
DUKE ENERGY FLORIDA - BARTOW PLANT, St Petersburg, Florida: Individual permit FL0000132, held by Duke Energy Florida, LLC; Administratively continued (past its expiration date and still in force until reissued); issued January 5, 2016, term to February 3, 2021, by Florida Department of Environmental Protection; discharges to Tampa Bay WBID 1656 Class II; Hydroelectric Power Generation.
- pH: 5 limits, 11 violations of any kind, 1 effluent exceedance, latest May 31, 2010.
- Temperature, water deg. fahrenheit: 4 limits, 10 violations of any kind.
- IC25 Static Renewal 7 Day Chronic Americamysis bahia (formerly Mysidopsis bahia): 3 limits, 9 violations of any kind.
- IC25 Static Renewal 7 Day Chronic Menidia menidia: 3 limits, 9 violations of any kind.
- Turbidity: 8 limits, 8 violations of any kind.
- Nitrogen, total [as N]: 6 limits, 6 violations of any kind.
- Flow, in conduit or thru treatment plant: 4 limits, 5 violations of any kind.
- Temp. diff. between intake and discharge: 2 limits, 5 violations of any kind.
- Temperature, water deg. centigrade: 2 limits, 2 violations of any kind.
- Solids, total suspended: 2 limits, 2 violations of any kind.
- Oil & Grease: 2 limits, 2 violations of any kind.
- Nitrogen, ammonia total [as N]: 2 limits, 2 violations of any kind.
- Ammonia, unionized: 2 limits, 2 violations of any kind.
- Nitrogen, Kjeldahl, total [as N]: 2 limits, 2 violations of any kind.
- Nitrite + Nitrate total [as N]: 2 limits, 2 violations of any kind.
- Phosphate, ortho [as PO4]: 2 limits, 2 violations of any kind.
- Phosphorus, total [as P]: 2 limits, 2 violations of any kind.
- Iron, total recoverable: 0 limits, 1 violation of any kind.
- July 1, 2026: Effluent Violations - Industrial Spill (ST6).
- March 9, 2026: Effluent Violations - Industrial Spill (ST6).
- April 17, 2024: Effluent Violations - Industrial Spill (ST6).
- March 28, 2023: WW SSO - Overflow to Dry Land or Building Backup (ST6).
- September 13, 2022: WW SSO - Overflow to Dry Land or Building Backup (ST6).
Other permits held by Duke Energy Florida, LLC
- DUKE ENERGY FLORIDA - SUWANNEE RIVER POWER PLANT, Live Oak: FL0000183, issued 2016-10-06
- BARTOW POWER PLANT, St Petersburg: FLR05G904, issued 2019-08-08
- OSPREY ENERGY CENTER, Auburndale: FLR05I046, issued 2017-01-09
- NEWBERRY SUBSTATION, Trenton: FLR10YR36, issued 2026-08-15
- POWERLINE SUBSTATION, Crystal River: FLR20CC28, issued 2018-05-18
- 16TH STREET SUBSTATION, Saint Petersburg: FLR20CI50, issued 2018-09-14
- BAILEY MILL RENEWABLE ENERGY CENTER, Monticello: FLR20IP56, issued 2025-09-21
- DUKE ENERGY MAXIMO SUBSTATION, Saint Petersburg: FLR20JO57, issued 2026-09-07
- TIGER BAY COGENERATION PLANT, Fort Meade: FLRNEE394, issued 2020-06-12
DUKE ENERGY FLORIDA - BARTOW PLANT among its neighbors
60 discharge permits are in the Grand Bayou subwatershed (HUC 031002060603); FL0000132 is one. Its county: 724, 34 major; FL0000132 is major permit.
Other permits in the Grand Bayou subwatershed (HUC 031002060603)
- 4210 78TH AVENUE TOWNHOMES, Pinellas Park: FLR20HL33, minor, term to 2029-08-07
- AMARA BAY, Saint Petersburg: FLR10YG43, minor, term to 2031-02-13
- AMAZON.COM SERVICES LLC - DSR8, Saint Petersburg: FLR05I882, minor, term to 2027-06-30
- AMAZON.COM SERVICES LLC DMF8 PKG STPETERSBU3, Saint Petersburg: FLR05J088, minor, term to 2028-09-22
- APEC, Saint Petersburg: FLR20FN06, minor, term to 2027-06-18
- AUTONATION, Pinellas Park: FLG074303, minor, term to 2030-01-26
- AUTONATION PINELLAS PARK, Pinellas Park: FLR20GR64, minor, term to 2028-10-08
- AUTONATION TOYOTA PINELLAS PARK, Pinellas Park: FLG074771, minor, term to 2031-02-02
- AUTONATION TOYOTA PINELLAS PARK, Pinellas Park: FLR20HV83, minor, term to 2030-01-15
- BARTOW POWER PLANT, St Petersburg: FLR05G904, minor, term to 2024-08-07
Nearby on the register
- Discharge permits in St Petersburg
- Every permit record in St Petersburg, A to Z
- Discharge permits in Florida
- Every permit record in Florida, A to Z
Figures from EPA’s ICIS-NPDES download, loaded October 14, 2026.
What this page shows
This public-records page covers NPDES permit FL0000132, held by Duke Energy Florida, LLC for the DUKE ENERGY FLORIDA - BARTOW PLANT, which discharges to Tampa Bay (WBID 1656, Class II) and is administratively continued as a Major Discharger. The page lists 17 for discharger class, 1 pollutant under a numeric limit, and 1 pollutant with an effluent exceedance.