NPDES FL0000159 · Clean Water Act
CITRUS COMBINED CYCLE PB1 PB2, Crystal River, FL: NPDES FL0000159 discharge permit, effluent exceedances, inspections, penalties
CITRUS COMBINED CYCLE PB1 PB2, Crystal River, Florida: Individual permit FL0000159, held by Duke Energy Crystal River; Administratively continued; issued March 13, 2020, term to March 12, 2025, by Florida Department of Environmental Protection; discharges to Gulf of Mexico WBID 8039 Class II Marine; Hydroelectric Power Generation.
19 of the 34 pollutants listed for NPDES FL0000159 have no violation or effluent exceedance.
- LC50 Static Renewal 96Hr Acute Americamysis bahia (formerly Mysidopsis bahia): 0 limits, 3 violations of any kind, 3 effluent exceedances, latest October 31, 2011, largest 99,999% over the limit.
- pH: 16 limits, 10 violations of any kind, 2 effluent exceedances, latest February 28, 2013.
- Temperature, water deg. fahrenheit: 8 limits, 2 violations of any kind, 2 effluent exceedances, latest June 30, 2009, largest 0% over the limit.
- Nickel, total recoverable: 2 limits, 2 violations of any kind, 2 effluent exceedances, latest July 31, 2012, largest 2,310% over the limit.
- Cadmium, total recoverable: 2 limits, 2 violations of any kind, 2 effluent exceedances, latest July 31, 2012, largest 639% over the limit.
- Copper, total recoverable: 2 limits, 2 violations of any kind, 2 effluent exceedances, latest July 31, 2012, largest 224% over the limit.
- LC50 Static Renewal 96Hr Acute Menidia: 0 limits, 2 violations of any kind, 2 effluent exceedances, latest October 31, 2011, largest 99,999% over the limit.
- Oil & Grease: 2 limits, 27 violations of any kind, 1 effluent exceedance, latest February 28, 2010, largest 4% over the limit.
- Solids, total suspended: 4 limits, 19 violations of any kind, 1 effluent exceedance, latest July 31, 2012, largest 14% over the limit.
- Arsenic, total recoverable: 2 limits, 1 violation of any kind, 1 effluent exceedance, latest September 30, 2008, largest 64% over the limit.
- Iron, total recoverable: 2 limits, 1 violation of any kind, 1 effluent exceedance, latest September 30, 2008, largest 33% over the limit.
- Flow, in conduit or thru treatment plant: 20 limits, 12 violations of any kind.
- Oxidants, total residual: 12 limits, 12 violations of any kind.
- Total residual ooxidant-discharge time: 4 limits, 6 violations of any kind.
- Spectrus CT 1300: 0 limits, 1 violation of any kind.
- Nitrogen, total [as N]: 10 limits.
- Nitrogen, Kjeldahl, total [as N]: 10 limits.
- Nitrite + Nitrate total [as N]: 10 limits.
- Phosphate, ortho [as PO4]: 10 limits.
- Phosphorus, total [as P]: 10 limits.
- Specific conductance: 4 limits.
- Chlorination duration: 4 limits.
- IC25 Static Renewal 7 Day Chronic Americamysis bahia (formerly Mysidopsis bahia): 4 limits.
- IC25 Static Renewal 7 Day Chronic Menidia menidia: 4 limits.
- Selenium, total recoverable: 2 limits.
- Zinc, total recoverable: 2 limits.
- Aluminum, total recoverable: 2 limits.
- Lead, total recoverable: 2 limits.
- Chromium, total recoverable: 2 limits.
- Vanadium, total recoverable: 2 limits.
- Cycles Of Concentration: 2 limits.
- Temp. diff. between intake and discharge: 2 limits.
- Mercury, total recoverable: 2 limits.
- Beryllium, total recoverable [as Be]: 1 limit.
- February 10, 2026: Evaluation (S).
- May 13, 2023: WW SSO - Discharge to Waters (ST6).
- August 4, 2021: WW SSO - Overflow to Dry Land or Building Backup (ST6).
CITRUS COMBINED CYCLE PB1 PB2 among its neighbors
7 discharge permits are in the Little Rocky Creek-Cedar Creek Frontal subwatershed (HUC 031002070101); FL0000159 is one. Its county: 90, 2 major; FL0000159 is major permit.
Other permits in the Little Rocky Creek-Cedar Creek Frontal subwatershed (HUC 031002070101)
- CRYSTAL RIVER SYNTHETIC GYPSUM STORAGE & HANDLING FACILITY, Crystal River: FLR05H686, minor, term to 2024-05-25
- CRYSTAL RIVER UNIT 3, Crystal River: FL0A00004, minor, term to 2025-02-11
- CRYSTAL RIVER UNIT 3 FORMER NUCLEAR POWER PLANT, Crystal River: FLR05I568, minor, term to 2025-10-14
- DUKE ENERGY FLORIDA - CRYSTAL RIVER 4 5, Crystal River: FL0036366, major, term to 2016-07-17
- FLORIDA POWER CORP, Crystal River: FLR05H479, minor, term to 2018-02-28
- POWERLINE SUBSTATION, Crystal River: FLR20CC28, minor, term to 2023-05-17
What stands out
- Its term runs 4 years and 364 days, March 13, 2020 to March 12, 2025; the term ended 581 days before EPA's file was loaded on October 14, 2026, and the file lists the permit as administratively continued.
- Its newest dated event on file is an inspection on February 10, 2026, 246 days before EPA's file was loaded.
- In the 365 days to October 14, 2026, it was dated 1 inspection.
- EPA's file dates 3 events for it, from 2021 to 2026.
- 11 of its 34 pollutants on file have an effluent exceedance (32%); 31 are under a numeric limit; the largest exceedance is LC50 Static Renewal 96Hr Acute Americamysis bahia (formerly Mysidopsis bahia) at 99,999% over its limit.
- It is one of 23,564 discharge permits on the register in Florida; the file names no program for it, and it is a major discharger.
Identity
| Facility | CITRUS COMBINED CYCLE PB1 PB2 |
|---|---|
| Permittee | Duke Energy Crystal River |
| NPDES ID | FL0000159 |
| Status | Administratively continued |
| Type | Individual permit |
| Class | Major |
| Facility type | Non-POTW |
| Issued | March 13, 2020 |
| Expires | March 12, 2025 |
| Agency | Florida Department of Environmental Protection |
| Address | Crystal River, FL 34428 |
| Receiving water | Gulf of Mexico WBID 8039 Class II Marine |
| Receiving water impaired | 303(D) Listed |
| Subwatershed | Little Rocky Creek-Cedar Creek Frontal (HUC 031002070101) |
| NAICS | 221111 – Hydroelectric Power Generation |
| SIC | 4911 – Electric Services |
| Other EPA IDs (FRS) | RCRA handler FLT960054831; ICIS-AIR source FL0000001201700004 |
NPDES FL0000159: effluent limits and exceedances
CITRUS COMBINED CYCLE PB1 PB2 (NPDES FL0000159): 34 pollutants on file, 31 limited; 15 with a violation of any kind, 11 with an exceedance.
| Pollutant | Limits | Violations | Exceedances | Latest | Largest, as filed |
|---|---|---|---|---|---|
| LC50 Static Renewal 96Hr Acute Americamysis bahia (formerly Mysidopsis bahia) | 0 | 3 | 3 | October 31, 2011 | 99,999% over the limit |
| pH | 16 | 10 | 2 | February 28, 2013 | |
| Temperature, water deg. fahrenheit | 8 | 2 | 2 | June 30, 2009 | 0% over the limit |
| Nickel, total recoverable | 2 | 2 | 2 | July 31, 2012 | 2,310% over the limit |
| Cadmium, total recoverable | 2 | 2 | 2 | July 31, 2012 | 639% over the limit |
| Copper, total recoverable | 2 | 2 | 2 | July 31, 2012 | 224% over the limit |
| LC50 Static Renewal 96Hr Acute Menidia | 0 | 2 | 2 | October 31, 2011 | 99,999% over the limit |
| Oil & Grease | 2 | 27 | 1 | February 28, 2010 | 4% over the limit |
| Solids, total suspended | 4 | 19 | 1 | July 31, 2012 | 14% over the limit |
| Arsenic, total recoverable | 2 | 1 | 1 | September 30, 2008 | 64% over the limit |
| Iron, total recoverable | 2 | 1 | 1 | September 30, 2008 | 33% over the limit |
| Flow, in conduit or thru treatment plant | 20 | 12 | 0 | ||
| Oxidants, total residual | 12 | 12 | 0 | ||
| Total residual ooxidant-discharge time | 4 | 6 | 0 | ||
| Spectrus CT 1300 | 0 | 1 | 0 | ||
| Nitrogen, total [as N] | 10 | 0 | 0 | ||
| Nitrogen, Kjeldahl, total [as N] | 10 | 0 | 0 | ||
| Nitrite + Nitrate total [as N] | 10 | 0 | 0 | ||
| Phosphate, ortho [as PO4] | 10 | 0 | 0 | ||
| Phosphorus, total [as P] | 10 | 0 | 0 | ||
| Specific conductance | 4 | 0 | 0 | ||
| Chlorination duration | 4 | 0 | 0 | ||
| IC25 Static Renewal 7 Day Chronic Americamysis bahia (formerly Mysidopsis bahia) | 4 | 0 | 0 | ||
| IC25 Static Renewal 7 Day Chronic Menidia menidia | 4 | 0 | 0 | ||
| Selenium, total recoverable | 2 | 0 | 0 | ||
| Zinc, total recoverable | 2 | 0 | 0 | ||
| Aluminum, total recoverable | 2 | 0 | 0 | ||
| Lead, total recoverable | 2 | 0 | 0 | ||
| Chromium, total recoverable | 2 | 0 | 0 | ||
| Vanadium, total recoverable | 2 | 0 | 0 | ||
| Cycles Of Concentration | 2 | 0 | 0 | ||
| Temp. diff. between intake and discharge | 2 | 0 | 0 | ||
| Mercury, total recoverable | 2 | 0 | 0 | ||
| Beryllium, total recoverable [as Be] | 1 | 0 | 0 |
NPDES FL0000159: inspections, violations and enforcement
NPDES FL0000159: 2 single-event violations
| Date | What EPA recorded | Agency |
|---|---|---|
| May 13, 2023 | WW SSO - Discharge to Waters | ST6 |
| August 4, 2021 | WW SSO - Overflow to Dry Land or Building Backup | ST6 |
NPDES FL0000159: 1 inspection
| Date | What EPA recorded | Agency |
|---|---|---|
| February 10, 2026 | Evaluation | S |
NPDES FL0000159 (CITRUS COMBINED CYCLE PB1 PB2): no formal enforcement action and informal enforcement action on file.
Watch NPDES FL0000159
NPDES FL0000159: one email when its EPA record changes — $99/month.
Permits near NPDES FL0000159
NPDES FL0000159: 34 pollutant rows, 3 dated events; ICIS-NPDES download, loaded October 14, 2026.