Clean Water Act discharge permit · NPDES FL0041441

VENICE EASTSIDE WWTP, Venice, FL: NPDES FL0041441 discharge permit, effluent exceedances, inspections, penalties

VENICE EASTSIDE WWTP, held by Venice, City of, holds NPDES permit FL0041441, which discharges to Curry Cr, Class Iii Fresh, Wbid 2009c, Roberts Cl. EPA’s file records it issued February 1, 2017 and expiring January 31, 2022. The status and dates are as EPA’s permit file stood when Velarion loaded it (September 14, 2026); EPA’s free Detailed Facility Report on ECHO carries the permit’s current standing.

Identity

Facility as filedVENICE EASTSIDE WWTP
Permittee as filedVenice, City of
NPDES IDFL0041441
Permit statusAdministratively continued (past its expiration date and still in force until reissued)
Permit typeIndividual permit
Discharger classMajor discharger
Facility typePublicly owned treatment works
ProgramPublicly owned treatment works
IssuedFebruary 1, 2017
Expiration dateJanuary 31, 2022
Issuing agencyFlorida Department of Environmental Protection
AddressVenice, FL 34275
Receiving waterCurry Cr, Class III Fresh, WBID 2009C, Roberts Cl
Receiving water impaired303(D) Listed
SubwatershedVenice Inlet Frontal (HUC 031002010202)

Cited to the EPA ICIS-NPDES permit file (ECHO download).

Effluent limits and exceedances

An effluent exceedance is a discharge monitoring report value over the permit’s numeric limit (EPA’s violation code E90). A violation of any kind also counts a report not filed. Each row is EPA’s own count for that pollutant.

Pollutant or measureLimitsViolations, any kindEffluent exceedancesLatest exceedanceLargest exceedance, as filed
Nitrogen, total [as N]105825August 31, 2025103% over the limit
Dichlorobromomethane42414September 30, 2025190% over the limit
Phosphorus, total [as P]8305September 30, 2024110% over the limit
Chlorine, total residual4165October 31, 2024600% over the limit
Flow, in conduit or thru treatment plant7191February 29, 20166% over the limit
Oxygen, dissolved [DO]051September 30, 201310% over the limit
NOEL Static Renewal 7Day Chronic Ceriodaphnia dubia011March 31, 201050% over the limit
LC50 Static Renewal 96Hr Acute Ceriodaphnia dubia3410
LC50 Static Renewal 96Hr Acute Cyprinella leedsi3410
Solids, total suspended11310
BOD, carbonaceous [5 day, 20 C]9260
Overflows0160
Duration of discharge0160
pH4120
Dibromochloromethane060
Coliform, fecal general250
Chlorodibromomethane440
% of fecal coliform samples < detectable140
Coliform, fecal MF, MFC broth, 44.5 C020
Plant capacity fact. percent of capacity110
Oxygen, dissolved percent saturation110

Cited to the EPA ICIS-NPDES limits and effluent violations files (ECHO download); up to 60 rows shown, most exceedances first.

Inspections, violations and enforcement

The newest 50 of 107.

DateWhat EPA recordedAgency
July 27, 2026WW SSO - Overflow to Dry Land or Building BackupST6
June 4, 2026WW SSO - Overflow to Dry Land or Building BackupST6
June 1, 2026WW SSO - Failure to monitorST6
June 1, 2026Reporting Violations - Failure to submit required report (non-DMR non-pretreatment)ST6
June 1, 2026Monitoring Violations - No Flow Measurement DeviceST6
April 9, 2026WW SSO - Discharge to WatersST6
February 9, 2026WW SSO - Overflow to Dry Land or Building BackupST6
February 5, 2026WW SSO - Overflow to Dry Land or Building BackupST6
January 21, 2026WW SSO - Overflow to Dry Land or Building BackupST6
January 16, 2026WW SSO - Overflow to Dry Land or Building BackupST6
January 13, 2026WW SSO - Overflow to Dry Land or Building BackupST6
January 2, 2026WW SSO - Overflow to Dry Land or Building BackupST6
November 26, 2025WW SSO - Overflow to Dry Land or Building BackupST6
August 15, 2025WW SSO - Discharge to WatersST6
July 30, 2025WW SSO - Overflow to Dry Land or Building BackupST6
July 24, 2025WW SSO - Overflow to Dry Land or Building BackupST6
July 10, 2025WW SSO - Overflow to Dry Land or Building BackupST6
May 19, 2025WW SSO - Overflow to Dry Land or Building BackupST6
May 8, 2025Reporting Violations - Failure to submit required report (non-DMR non-pretreatment)ST6
May 8, 2025Monitoring Violations - Analysis not ConductedST6
April 14, 2025WW SSO - Overflow to Dry Land or Building BackupST6
April 7, 2025WW SSO - Overflow to Dry Land or Building BackupST6
March 26, 2025WW SSO - Overflow to Dry Land or Building BackupST6
March 19, 2025WW SSO - Overflow to Dry Land or Building BackupST6
March 5, 2025WW SSO - Overflow to Dry Land or Building BackupST6
January 25, 2025WW SSO - Overflow to Dry Land or Building BackupST6
November 21, 2024WW SSO - Overflow to Dry Land or Building BackupST6
November 15, 2024WW SSO - Overflow to Dry Land or Building BackupST6
November 6, 2024WW SSO - Overflow to Dry Land or Building BackupST6
October 10, 2024WW SSO - Overflow to Dry Land or Building BackupST6
August 23, 2024WW SSO - Discharge to WatersST6
August 5, 2024WW SSO - Overflow to Dry Land or Building BackupST6
August 4, 2024WW SSO - Overflow to Dry Land or Building BackupST6
July 11, 2024WW SSO - Overflow to Dry Land or Building BackupST6
May 6, 2024WW SSO - Overflow to Dry Land or Building BackupST6
April 3, 2024WW SSO - Overflow to Dry Land or Building BackupST6
March 13, 2024WW SSO - Overflow to Dry Land or Building BackupST6
February 13, 2024WW SSO - Overflow to Dry Land or Building BackupST6
December 15, 2023WW SSO - Overflow to Dry Land or Building BackupST6
November 20, 2023WW SSO - Overflow to Dry Land or Building BackupST6
November 15, 2023WW SSO - Overflow to Dry Land or Building BackupST6
October 4, 2023WW SSO - Overflow to Dry Land or Building BackupST6
August 1, 2023WW SSO - Overflow to Dry Land or Building BackupST6
July 10, 2023Reporting Violations - Failure to submit required report (non-DMR non-pretreatment)ST6
January 18, 2023WW SSO - Overflow to Dry Land or Building BackupST6
January 3, 2023WW SSO - Overflow to Dry Land or Building BackupST6
December 5, 2022WW SSO - Overflow to Dry Land or Building BackupST6
October 20, 2022WW SSO - Overflow to Dry Land or Building BackupST6
September 8, 2022WW SSO - Overflow to Dry Land or Building BackupST6
June 24, 2022WW SSO - Overflow to Dry Land or Building BackupST6

Velarion’s copy of EPA’s ICIS-NPDES files does not include the inspections, formal enforcement actions and informal enforcement actions files, so this page shows none of them. EPA’s free Detailed Facility Report on ECHO lists this permit’s inspections, enforcement actions and penalties.

Cited to the EPA ICIS-NPDES violation, inspection and enforcement files (ECHO download); up to 50 rows of each shown, newest first.

Watch this permit

One permit holder, $99/month. Watch the register for one permit holder and the places and receiving waters tied to its permits. Choose “One permit holder” and enter this permit’s NPDES ID, FL0041441.

Start the watch

How often?
  • One permit holder — $99/month
  • One watershed — $2,990/year
  • One state — $4,990/year
  • The whole register — $18,000/year

How we handle your data → Privacy

EPA publishes a free Detailed Facility Report for every permit on ECHO: its compliance status quarter by quarter, its inspections, and its enforcement actions and penalties. EPA also sends free notices of new inspections and enforcement actions through ECHO Notify; enter NPDES ID FL0041441 there.